The events of 21 February 2006
59 Between 17 February 2006 and the crane incident on 21 February 2006, there was no further communication between Mr Goss and Mr Mates.
60 As already noted, the contraventions alleged in respect of the events on site on 21 February 2006 and the picket line on 22 February 2006 and following were the subject of a no case submission. The question for the Court on a no case submission of the kind made is whether there is evidence upon which the Court could enter judgment for the applicant. Plainly enough, logically speaking, rejecting a no case submission does not necessarily entail the consequence that the claim succeeds. The difference between a ruling on a no case submission and final judgment is clear where a judge sits with a jury. Where a judge sits alone the distinction may be less easily seen. As Toohey J said in James v Australia and New Zealand Banking Group Ltd (1986) 64 ALR 347 at 400:
Where a judge is sitting with a jury, the distinction between the arbiter of law and the arbiter of fact is of course apparent. If the judge decides that there is a case to go to the jury, it is then for the jury to uphold or dismiss the claim. While there is no logical inconsistency in rejecting a no case submission and thereafter rejecting the claim, the distinction is a fine one when a judge sits without a jury, given that the standard of proof is on the balance of probabilities and that inferences may be drawn by reason of the respondent's failure to adduce evidence.
…
If a defendant elects not to call evidence, the judge has before him all the evidence upon which he is called to make a decision. Any distinction between the role of the judge in ruling on a no case submission and the role of the judge as an arbiter of fact becomes largely illusory … The inconvenience of not putting the defendant to an election is apparent. If the judge's decision on the no case submission is upset on appeal, there must inevitably be a retrial.
61 In Residues Treatment & Trading Co Ltd v Southern Resources Ltd (1989) 52 SASR 54 at 73-4, Perry J determined that the defendants should be put to their election and said:
I realise that by putting the defendants to their election, I have effectively rendered it impracticable for the defendants to make any submission of no case to answer, even if they elect not to call any evidence. This is so, as if they do not call any evidence, it would not be appropriate for the court then to embark on the artificial exercise of determining whether there was a case to answer. The orderly disposal of the proceedings in those circumstances would require the defendants to proceed with their final submissions: see Toohey J, James v ANZ Bank at 400. But those considerations cannot deflect me from ruling in favour of the defendants being put to their election, if it is otherwise proper to do so.
62 As noted above, this was also the view I came to and the course taken in this case. Accordingly, I turn to the evidence as it now stands.
63 On 17 February 2006, Transit Joint Venture booked and paid for a crane crew and a crane from IC Hire Pty Ltd, trading as Independent Cranes, to attend the site on Tuesday, 21 February 2006. Monday, 20 February 2006, was a rostered day off for workers at the site.
64 On 21 February 2006, Mr Mates attended Mount Street shortly after the crane and crane crew had come onto the site and begun to set up. The Union and Mr Mates did not dispute that Mr Mates told the crane crew to shut down the crane and leave. The crane crew spoke with Mr Mitchell at the office of Independent Cranes and left the site.
65 Mr Cahill alleged that, by this conduct, the Union and Mr Mates contravened s 43 by taking action with the intent to coerce Hardcorp to employ Mr Deans, Ms Singleton and Mr O'Donnell; and/or (2) allocate and/or designate to Ms Singleton the duties or responsibilities of an OH&S officer: see [13] and [19] of the Statement of Claim. There was a further related allegation concerning s 38, which is discussed below.
66 In their Defence, the Union and Mr Mates denied the case made against them under s 43 (and s 38): see [17] and [25] of the Defence. The Union and Mr Mates provided particulars, which, as amended, stated that:
Mates raised safety concerns with a crane operator on the site. Mates was informed by the crane operator that he had been instructed by his employer to leave the site.
67 The two site managers at Mount Street at the time, Mr Palmer and Gregory Moresi, gave evidence about the events of 21 February 2006, as did the site engineer, Ryan McMahon, and Steven Mitchell then of Independent Cranes.
68 Mr Moresi said that he arrived at the site at about 6:00 am and that the crane came on site just after 7:00 am. About 8:00 am, Mr Palmer told him that Mr Mates had stopped the crane. Mr Moresi said that he, Mr Palmer and Mr McMahon went to find Mr Mates to ask him what was going on. They found Mr Mates quite close to the crane. When asked why he had shut the crane down, Mr Mates replied that this was because there was no OH&S officer, no shop steward and also no first aid. Mr Moresi reiterated this evidence in cross-examination. Mr Moresi said that he told Mr Mates that this was wrong and that "Geeza" (Mr Van Senten) was the shop steward and OH&S representative on site. In a diary note around the same time, Mr Moresi recorded that Mr Mates "then told the crane to pack up and leave the site". According to Mr Moresi, as the crane crew were packing up, Mr Mates said "make sure you write it all down and I will swear by it in Court".
69 Further, Mr Moresi said that he was standing about 4 to 5 metres away from Mr Mates, when Mr Moresi overheard Mr Mates say in a mobile phone conversation "tell Maurie Hill to ring Sergi and all the others to make sure". Mr Moresi wrote this down in his diary the same day. Sergi Cranes Pty Ltd was a well-known crane company from which Transit Joint Venture sometimes hired cranes and Mr Hill was the Union's (FEDFA Division) crane organiser. According to Mr Moresi's diary note, Mr Mates left the Mount Street site around 9:00 am that day. Mr Moresi said that he telephoned Mr Goss shortly afterwards to let him know what had happened.
70 Mr Palmer said that, at about 7:50 am, he and Mr Van Senten set out the location for the crane to commence work and the crane was driven into position and set up on outriggers. Mr Palmer said that the crane was ready for the first lift at about 8:15 am, when Mr Mates arrived at the site. Mr Palmer said that he then went to find Mr Moresi and Mr McMahon.
71 According to Mr Palmer, when the three men found Mr Mates, they asked him why he had shut down the crane and Mr Mates replied that he had done this because there was no shop steward or OH&S representative on the site. When corrected, Mr Mates replied "No you don't and I have shut down your crane. You can write that down in your diary." Mr Palmer and Mr McMahon repeated that the site had a shop steward and OH&S officer. In response to Mr Mates' question "who is that?", they said it was "Geeza" (Mr Van Senten). According to Mr Palmer, Mr Mates then said "the crane is not working. I have sent them (the crew) away". A diary note that Mr Palmer made that morning was to the same effect. Mr Palmer's evidence was that he and Mr McMahon went to meet with the crane crew and that he asked the crew to check with the office of Independent Cranes. Mr Palmer saw one of the crew finish a phone call and then motion to the other to continue packing.
72 In a statement adopted at the trial, Mr McMahon stated that he arrived at the site at about 6:50 am on 21 February 2006. The crane and crane crew from Independent Cranes came on site just after 7:15 am. Mr McMahon said that he inducted the driver and dogman and then told the crane crew to set up the crane.
73 Mr McMahon's evidence was that, at about 8:20 am, one of the carpenters told him that Mr Mates had entered the site. Mr McMahon went to inform Mr Moresi, and they were joined by Mr Palmer. The three men decided to find Mr Mates to ask him what was happening. According to Mr McMahon, they found Mr Mates reasonably close to the crane and asked him what he was doing on site. Mr Mates said that he was shutting down the crane, because there were no OH&S representative and shop steward on site. Mr McMahon said that Mr Moresi told Mr Mates that "Geeza" (Mr Van Senten) had been voted shop steward and OH&S representative. Mr Mates replied that he "didn't fucken care" and that he was shutting down the crane. Mr McMahon said that Mr Mates walked off from the crane crew followed by Mr Palmer and Mr Moresi, whilst he (Mr McMahon) went to receive a telephone call elsewhere. According to Mr McMahon, Mr Mates drove off in his car shortly afterwards and the crane crew told Mr Palmer (in Mr McMahon's presence) that Mr Mitchell from Independent Cranes had instructed them to pack up. In a statement in reply, Mr McMahon added that he subsequently called Mr Mitchell from Independent Cranes.
74 Mr McMahon made contemporaneous notes of the events of 21 February 2006, which stated:
Bobby Mates entered the site without seeking management's approval. Once it became aware he was on site management, Greg, Bryan, Ryan sought him out. He told us there was no shop steward or [OH&S] on site. We replied that yes there was. Geeza was shop steward & cert II qualified. He told us that he didn't fucken care and then he's shutting us down.
… I rang Steve [Mitchell] and he said that he had not instructed his boys to pack up but called 5 min later to say that now he had been instructed by the union also to remove the crane from site. He said he was sorry but he was just the meat in the sandwich and that if he didn't follow instructions they wouldn't be able to work on any other sites. Crane left at 9:30 am.
75 Mr Mitchell, at that time employed by Independent Cranes to take and organise customer bookings, made a statement that he adopted at trial in which he said that he received a phone call from one of the crane crew on the morning of 21 February 2006, in which the crew member said: "Here comes the union now. We'll talk to him and call straight back." Shortly afterwards, Mr Mitchell received another phone call in which the crew member said: "The union has knocked the job on the head". Mr Mitchell's evidence was that he told the crew to pack up the crane and come back to the yard at Independent Cranes.
76 Mr Goss was not on site when Mr Mates arrived there on 21 February 2006. Mr McMahon and Mr Moresi kept him informed by telephone. When Mr Goss learned that the crane and crane crew had left the site, he instructed Mr McMahon to ask other crane companies about the availability of a crane and crane crew, upon the basis that Transit Joint Venture would pre-pay any booking. Mr McMahon's evidence was that later on 21 February 2006 he unsuccessfully called about eight crane companies.
77 Counsel for the Union and Mr Mates submitted that Mr Moresi's account of the events of 21 February 2006 showed that he was not being frank in his evidence. Counsel referred to one occasion. Mr Moresi's evidence fell to be considered in its entirety, however, and, so considered, he was a credible witness, who gave his evidence carefully and conscientiously.
78 Counsel for the Union and Mr Mates argued that Mr McMahon's evidence was unreliable because he exaggerated his evidence in order to implicate the Union. Mr McMahon was the least experienced person to give evidence, although he begun at Mount Street in early 2004. There were occasions when he corrected his evidence, when he was shown to be in error, and other occasions when he became confused. Allowing for these deficiencies, however, he endeavoured to give his evidence as best he could. I would not regard his evidence as unreliable to the extent that the Union and Mr Mates argued.
79 What happened on site between 8 and 9 am on the 21 February 2006 was tolerably clear. By this time, the crane and crane crew had arrived, been inducted by Mr McMahon, and set up the crane. Shortly before the first lift, Mr Mates arrived on site, found the crane and crane crew and shut the crane down by telling the crew to pack up and leave. When Mr Moresi, Mr Palmer and Mr McMahon found Mr Mates close by the crane and asked for an explanation, Mr Mates admitted that he had shut the crane down, saying this was because there was no OH&S representative or shop steward on site. In the presence of Mr Palmer and Mr McMahon, Mr Moresi told him that this was incorrect because Mr Van Senten was shop steward and OH&S representative. Mr Mates responded that he did not care about this and was in any event shutting the crane down. Meanwhile the crew, who had already spoken to Mr Mitchell at Independent Cranes once, phoned him again and received Mr Mitchell's instruction to return to Independent Cranes.
80 Did Mr Mates' action in stopping the crane amount to action taken with the intent to coerce Hardcorp to employ Mr Deans, Mr O'Donnell and Ms Singleton and, in Ms Singleton's case, to allocate OH&S responsibilities to her?
81 Over the history of the proceeding, the Union and Mr Mates put forward various explanations for Mr Mates' conduct on 21 February 2006, some of which were not pursued at trial and others were not pressed in final submissions, whether because of the Union's and Mr Mates' election not to call evidence or otherwise. Thus, [17A] of an amended defence dated 17 August 2007 pleaded that the crane was removed because of a malfunction and/or because of concerns about payment. Neither explanation was pursued at trial. I reject counsel for Mr Cahill's submission that I should treat this conduct on the Union's and Mr Mates' part as evidence of consciousness of guilt. I would not regard the relevant principle as applicable in the circumstances shown: compare Australian Competition and Consumer Commission v Leahy Petroleum Pty Ltd (2004) 141 FCR 183 at 215-6 [244]-[248]. It is undeniable, however, that there is no evidence that might explain Mr Mates' conduct other than that to which I have already referred. For the reasons that appear below, I would not regard the evidence concerning the events of 22 February 2006 and thereafter as having much, if any, bearing on this incident.
82 There was no evidence to support a suggestion that safety concerns motivated Mr Mates' conduct: compare [17] of amended defence and further amended defence dated 14 July 2008. In cross-examination, Mr Moresi, who had 10-15 years experience in the construction industry and with cranes, said that he had not heard Mr Mates or anyone else raise any safety issue when Mr Mates was on site on 21 February 2006. Mr Moresi said that responsibility for any safety issue affecting the crane lay with the crane crew and the site safety officer, managers and engineer. Mr Palmer's evidence was to the same effect, including that no safety issues touching the crane were raised with him on 21 February 2006. Mr McMahon's evidence was that, if there had been a safety issue with the crane, then, as a matter of practice, the crane crew would have immediately notified him as one of the site management personnel. Mr McMahon added that no-one from Independent Cranes and none of the crane crew had raised any safety, location, or other problem concerning the crane on 21 February 2006.
83 The evidence established that Mr Mates told Mr Moresi, Mr Palmer and Mr McMahon that he had shut down the crane because there was no shop steward or OH&S representative on site. When Mr Moresi informed him that Mr Van Senten was shop steward and OH&S representative, Mr Mates persisted, saying he did not care. There is no reasonable explanation for Mr Mates' conduct once he was given this explanation. The only tenable explanation is that Mr Mates was carrying out his threats of 15 and 17 February 2006 that the project at Mount Street would not recommence unless Mr Deans, Mr O'Donnell and Ms Singleton were re-employed and took on their former responsibilities, including that Ms Singleton assumed OH&S responsibilities. It was telling that Mr Mates gave as his reason for his action that there was no shop steward or OH&S representative, because this reflected the demands that he had made to Mr Goss at his earlier meetings with him on 15 and 17 February 2006. The nature of Mr Mates' demands was reflected in that fact that, when he was told that Mr Van Senten was shop steward and OH&S representative, he said he did not care. In effect, Mr Mates signalled that he was only interested in his people being appointed to these positions. This too was consistent with his demands of 15 and 17 February 2006.
84 Counsel for the Union and Mr Mates contended that the evidence of Mr Mitchell as to what he was told by the crane crew that Mr Mates had said to them showed that Mr Mates' reason for shutting down the crane was not to coerce Hardcorp to employ Mr Deans, Mr O'Donnell or Ms Singleton. Rather, the shut down was because sub-contractor payments and employee entitlements had not been met. Even if admissible on this point, I would not regard this evidence as probative of Mr Mates' intent and, even if probative, it would not outweigh the considerations addressed in the preceding paragraph.
85 Accordingly, having regard to the evidence of Mr Moresi, Mr Palmer, Mr McMahon and Mr Mitchell and s 140 of the Evidence Act, I find that, on the morning of 21 February 2006, Mr Mates demanded that the crane crew from Independent Cranes shut down the crane and leave the site, which they ultimately did after speaking to their own office. In so doing, Mr Mates was carrying out his threats of 15 and 17 February 2006. Having regard to this fact and to Mr Mates' statements to Mr Moresi, Mr Palmer and Mr McMahon on the morning of 21 February 2006, I find that his intention in shutting down the crane was to coerce Hardcorp to re-employ Mr Deans, Mr O'Donnell and Ms Singleton at the Mount Street site, and, amongst other things, to have Ms Singleton appointed as OH&S officer on site: compare Telstra Corporation Ltd (2000) 108 FCR at 61 [24] and National Tertiary Education Industry Union (2002) 117 FCR at 142-143 [102]. For the reasons stated above, Mr Mates' conduct and intent are to be taken as that of the Union.
86 Accordingly, I find that Mr Mates, in his own right, and the Union, through Mr Mates' conduct on 21 February 2006, breached s 43 of the Building and Construction Industry Improvement Act.
87 Mr Cahill also alleged that, on 21 February 2006, Mr Mates telephoned the office of Independent Cranes and said that its crew were not to work on the Mount Street project. At trial, this allegation became an allegation that Mr Mates arranged for Mr Tadic and/or Mr Hill to contact Independent Cranes to ensure that the crane left the Mount Street site and did not return. Mr Cahill further alleged that, around the same time as Mr Mates shut down the crane, Mr Mates telephoned the Union's offices or a representative of the Union (whose identity is unknown) to instruct Mr Hill (the Union organiser responsible for crane services in Victoria (FEDFA Division)) that he should ring Sergi Cranes and other crane operators to warn them off working at the Mount Street site.
88 Mr Cahill's allegation about Mr Mates' telephone call concerning Mr Hill depended on Mr Moresi's evidence that he overheard Mr Mates say "tell Maurie Hill to ring Sergi and all the others to make sure". I accept that Mr Moresi honestly believed that he heard Mr Mates say these words. Assuming Mr Mates said them, the evidence does not disclose the identity of the person to whom he was speaking at the time (if in fact he was speaking to anyone). There was no evidence that Mr Hill or anyone else on the Union side called Sergi Cranes in the relevant period. Moreover, the statement attributed to Mr Mates does not disclose what was to be made "sure". There is no evidence, or at least no direct evidence, about this matter. I reject the proposition that I should infer from this statement alone (assuming it were made) that Mr Mates telephoned the Union's offices or a representative of the Union to instruct Mr Hill that he should ring Sergi Cranes and other crane operators to warn them off working at the Mount Street site. Moreover, having regard to the lack of corroborative evidence, I have some real doubts about whether the statement attributed to Mr Mates was in fact said by him. Ultimately, I am not satisfied on the balance of probabilities that Mr Mates in fact spoke the words alleged.
89 Mr Cahill relied on mobile telephone records to support both the warning off allegations. The telephone records disclosed that, on 21 February 2006:
(1) Mr Mates called Mr Tadic at 8:26 am (1 minute), 8:35 am (1 minute), 8:48 am (1.5 minutes) and at 1:18 pm (2 minutes);
(2) Mr Mates called Mr O'Donnell at 8:52 am (2 minutes);
(3) Mr Tadic called Independent Cranes at 8:31 am (2 minutes and 8 seconds), 1:25 (46 seconds) and 1:26 pm (1 minute and 22 seconds);
(4) Mr Tadic called Mr Hill at 10:17 am (2 minutes and 31 seconds);
(5) Mr Tadic called Mr Mates at 1:29 pm (duration 23 seconds);
(6) Mr Hill called Independent Cranes at 9:49 am (1 minute);
(7) Mr Hill called Tutt Bryant Crane Hire at 3:18 pm and Jatco Engineering Australia Pty Ltd (a crane company) at 3:39 pm; and
(8) Mr Hill called Mr Mates at 3:44 pm.
Mobile phone records also showed that, on 24 February 2006, Mr Hill called National Crane Hire (at 8:40 am), Rebel Cranes (at 4:01 pm and 5:22 pm) and, on 27 February 2006, he called Independent Cranes (at 1:20 pm).
90 Mr Mates' mobile phone records did not show that he made any call to the Union's offices when he was on the Mount Street site. These records indicated that Mr Mates did not call the Union until around 12:08 pm. Further, the records did not record any call on Mr Mates mobile phone to the offices of Independent Cranes. Mr Mates' mobile phone records showed that, whilst at Mount Street, Mr Mates made some brief calls from his mobile phone to Mr Tadic and a call to Mr O'Donnell. The records did not show that Mr Tadic called Mr Hill until about 10:17 am, although the records indicated that Mr Tadic called Independent Cranes shortly after Mr Mates first called him. There was also evidence that Mr Hill called Independent Cranes very briefly about three-quarters of an hour after Mr Mates had left the site. Furthermore, as indicated above, there was no evidence that, on 21 February 2006, Mr Hill called Sergi Cranes. There was little, if anything, to connect Tutt Bryant and Jatco Engineering with the matters at issue in this proceeding and, in consequence, little turned on the evidence that Mr Mates might have called them. There was no evidence that Mr McMahon rang these companies to inquire about the availability of a crane.
91 There was no evidence as to what was said in any of these mobile phone calls, many of which were very brief indeed and therefore indicated that very little (if anything) was said. There was no evidence from any person from any crane company that the Union had warned the company off working at the Mount Street site.
92 Mr Mitchell was called by Mr Cahill to give evidence, but he gave no evidence that he had received a call from Mr Mates or any other Union representative that day or on any subsequent day. Indeed, Mr Mitchell was not asked whether Mr Mates or anyone else from the Union had telephoned him at Independent Cranes on 21 February 2006 or any other date. As counsel for the Union and Mr Mates said, it has to be borne in mind that, at this time, Mr Mitchell was in charge of bookings at Independent Cranes. If there had been a warning off as alleged, he might reasonably have been expected to know about it. Counsel for the Union and Mr Mates relied on the rule in Jones v Dunkel (1959) 101 CLR 298. Counsel argued that the inference that there was no warning off might, in the absence of testimony from Mr Mitchell, be more comfortably drawn. I accept this submission in part: see Braverus Maritime Inc v Port Kembla Coal Terminal Ltd (2005) 148 FCR 68 at 112 [159]-[160] and Australian Securities and Investments Commission v Citigroup Global Markets Australia Pty Ltd (2007) 241 ALR 705 at 758 [384] per Jacobson J. I accept that, in the absence of any testimony from Mr Mitchell on the subject, it may be more comfortably inferred that, leaving aside what had happened earlier on 21 February 2006, no-one from the Union directly or expressly warned off Independent Cranes.
93 The mobile phone records established that Mr Mates, Mr Tadic and, to a lesser extent, Mr Hill and Mr O'Donnell were in communication with one or the other on 21 February 2006. Mr Tadic and Mr Hill were in limited communication with Independent Cranes. It was, perhaps, to be expected that the Union would be in contact with the crane company and crane organisers and others interested in the site, given what had occurred. I would not regard this evidence as probative of anything more. These records established that Mr Hill was in contact with some other crane companies, but this was not shown to be unusual and might be explained by reference to the nature of his responsibilities.
94 Mr Cahill relied on the fact that that day and subsequently Hardcorp was unable to get a crane to attend the Mount Street site. Mr Goss gave evidence that, on the basis of his thirty years' experience in the construction industry, it was very unusual to be unable to hire a crane of the kind he was seeking for work the following working day. However, Hardcorp's inability to obtain a crane and Mr Goss's evidence must be evaluated in light of the attendant circumstances. Mr McMahon gave evidence that, once the picket formed (see below), he told all the crane companies that he called that there was a picket in place. Thus, Hardcorp's own representative provided a reason for crane companies not to want to supply a crane to the Mount Street site.
95 As counsel for Mr Cahill noted, this did not explain Mr McMahon's inability to hire a crane when he called the eight crane companies on 21 February 2006, before the picket formed. However, Mr McMahon's summary of 1 March 2006, which was faxed to Mr Goss on that date, disclosed some reasonable explanations for his failure to obtain a crane. The contents of this summary do not entirely bear out the allegation that Mr Cahill made that the Union and Mr Mates took steps to ensure that any crane companies were warned off the Mount Street site. Furthermore, as counsel for the Union and Mr Mates noted, when Mr McMahon asked Sergi about a crane and crew on 2 March 2006, Sergi agreed to send them for the morning of the next day.
96 In summary, having regard to s 140 of the Evidence Actand the evidence before me, I reject as unproven Mr Cahill's further allegations that: (1) Mr Mates telephoned the Union's offices or a representative of the Union to instruct Mr Hill to ring Sergi Cranes and other crane operators to warn them off working at the Mount Street site; and (2) Mr Mates arranged for Mr Tadic and/or Mr Hill to contact Independent Cranes to ensure that the crane left the Mount Street site and did not return. See generally Neat Holdings Pty Ltd v Karajan Holdings Pty Ltd (1992) 110 ALR 449 and Granada Tavern v Smith (2008) 173 IR 328, [2008] FCA 646 at [85] and following.
97 Further, I am not persuaded that anything that occurred subsequently at the site should lead me to a different conclusion.