Was the work undertaken by Downer under the Contract tunnelling or boring of the constructing of underground works "for the purpose of" extraction of minerals?
- As the images set out at [79] above reveal, the tunnelling, boring and underground construction work undertaking by Downer did not lead to a situation where mineral extraction could take place immediately
- Before that could happen, the tunnelling depicted in blue on those images must take place so that the Under Cut and Extraction Levels are created.
- I have set out the five stages of panel cave mining described by Mr Brannigan at [53] to [58] above.
- Downer did none of the work described in the second, third, fourth and fifth stages.
- At the time Downer effected work in the Mine, none of those stages had been reached. That will not occur until 2022.
- In relation to the first stage, the construction of the Undercut Level and the Extraction Level, as the images I have set out at [79] above show, Downer did little more than construct an access to the proposed Undercut and Extraction Levels.
- The work that Downer did was in what Mr Indian described as the development phase. The production phase, that is the phase when minerals will be extracted, has not yet commenced.
- It is common ground that the question of whether the work required under the contract was for the relevant purpose is to be determined objectively.
- Mr Hume submitted that the relevant purpose was that of the party performing the work, Downer, objectively determined. An alternative view is that the relevant purpose is that of the commissioning party, Cadia, also objectively determined.
- However, in my opinion, the better view is that expressed by Fryberg J in Thiess where his Honour said that the relevant purpose should be decided "by reference to what a reasonable person in the position of the parties would conclude as to the object of what purpose of the contract". [24]
- Both Mr Hume and Mr Shipway submitted that when considering whether an activity is for its stated purpose, it is necessary to consider the connection or relationship between the two.
- The authorities dealing with statutory provisions prescribing the existence of a particular purpose, speak of whether there is "sufficient proximity" [25] between a specified act and the "prescribed end purpose". [26]
- The question here is whether the work in question, the tunnelling, boring and underground construction work, has a "sufficient proximity" with the "prescribed end purpose" of extraction by underground working of minerals so that it can be said that the former is for the purpose of the latter.
- Here,
1. Cadia's case is that it is sufficient if the tunnelling, boring or construction of underground work is for the "ultimate purpose" of extraction of minerals; and
2. Downer's case is that it is necessary that there be a "close and proximate" connection between the tunnelling, boring and construction of underground works and the extraction of minerals; that is, that it is necessary that the tunnelling, boring and construction of underground works be for the "very process of extraction".
- In my opinion, Downer's construction is to be preferred for a number of reasons.
- First, consistently with the principles I have set out above, the Mining Exception is to be construed beneficially to the subcontractor, here Downer; that is, it should be construed narrowly.
- Second, as Mr Hume submitted, the extension of the usual meaning of "extraction" by inclusion of tunnelling, boring or construction of underground works for that purpose, suggests the need for there to be a close "proximity" between the two.
- Third, as it has been held in the cases I have set out earlier, that "extraction" does not include work "associated with" extraction or work "preparatory to" extraction, it is hard to see why tunnelling, boring or construction of underground works, which is only in anticipation of ultimate extraction of minerals, should be held to be work "for the purpose of" such extraction.
- Fourth, the Act, and s 5 itself, specifies circumstances where a less proximate connection is required. Thus subs 5(1)(e) includes as "construction work" work that is "preparatory" to such work. As Mr Hume submitted, the "Act says so expressly when there is an intention to bring in ancillary activities". No such words are used in the Mining Exception. For example, the Mining Exception does not specify tunnelling, boring or construction of underground works "preparatory to" extraction of minerals. Rather the Mining Exception simply specifies such works "for" the purpose of extraction of minerals. That suggests to me a legislative intention that tunnelling, boring or construction of underground works referred to in the Mining Exception must be for the actual purpose of extracting minerals.
- As Mr Hume submitted, an example of such work would be where a subcontractor undertakes to extract minerals and to do all things necessary to that end, including tunnelling or boring and constructing underground works.
- Another example would be where a subcontractor does tunnelling, boring or construction of underground works to the point at which extraction is actually to take place and for the purpose of that extraction.
- Contrary to Mr Shipway's submissions, I do not see this construction as rendering the words "tunnelling" or "boring" otiose. The work done in these circumstances may well be other than tunnelling or boring and may well involve construction of underground works otherwise than by tunnelling or boring.
- Contrary to Mr Shipway's submissions, I do not see the observations of Fryberg J that I have set out at [31] above to be inconsistent with this conclusion. His Honour's remarks were directed to his conclusion that the reference to tunnelling, boring or construction of underground works showed that the Mining Exception extended the ordinary meaning of "extraction". All his Honour was saying was that as long as the tunnelling, boring and construction of underground works was "for the purpose" of extraction, it was not necessary to show that the tunnelling, boring and construction of underground works itself resulted in extraction.
- For those reasons, my conclusion is that the object and purpose of the Contract was not to cause Downer to undertake work for the purpose of extracting minerals, but was rather work preparatory to, and in anticipation of the ultimate and later extraction of minerals. The object and purpose of the Contract was not to cause Downer to undertake work for the purpose of actually extracting minerals.
- In these circumstances, in my opinion, the Mining Exception was not engaged.
- It follows that the work called for the Contract was "construction work", that the Contract is accordingly a "construction contract", that the Act was engaged and that the adjudicator had jurisdiction.