24 Mr Dallen then provided three schedules which, briefly described, were as follows: The first calculated interest at each of those three rates, namely, the 2.78%, the 3.83%, and 3.33% on the principal sum in the United States currency as calculated by Pacific. That was the principal sum of US$4,237,207.47.
25 The comparable interest rates were then calculated up to and including today. The difference reflected could not be described as a highly significant sum unless one took the extremes. The calculation of interest by Pacific resulted in an interest component of US$141,581.13. That, based on a 2.78% rate, yielded a figure of US$102,802.44, and interest calculated at 3.33% resulted in the figure of US$123,138.66.
26 The second calculation was based upon the adoption of a rate at 16 October 2001, and using the United States Federal Reserve Bank Certified Custom rate. For the reasons given, I think that that approach should not be adopted, at least so far as the date of calculation.
27 The final calculation proffered by Mr Dallen adopts the two interest rates of 2.78% and 3.83%. That was applied to a principal sum calculated at the time that Pacific contends the loss occurred, but using the United States Federal Reserve Bank Certified Custom rate. As an indication of the consequence of that, the principal sum so derived is US$4,218,850.74 as compared with the sum as calculated on behalf of Pacific of US$4,237,207.47 and interest rates so calculated appear not to change markedly the interest components calculated by Mr Dallen in his first schedule.
28 Again, for the reasons I have given, I think the method of calculation on behalf of Pacific is to be preferred, geared as it is to the date of incidence where applicable of the payment and the exchange rate applicable at that time, not ignoring the areas that fell outside that description of the calculation. Accordingly, the calculation of the conversion and of the interest should be that as adopted on behalf of Pacific in its revised submissions of 17 October 2001.
29 One matter I think needs to be specifically referred to in relation to interest. Under the February settlement between SSOE, Pacific and others, an interest rate of 7.75% was agreed upon as payable in relation to the principal sum payable under that settlement. That is in strong contrast to the rate of interest which I have allowed on the sums to which Pacific has been found entitled in the course of the principal reasons.
30 However, the reconciliation of the two rates may be found in a perhaps rough fashion in the fact that the rate of interest or the interest component in respect of the February settlement covers interest entitlements of SSOE from date of conversion. Viewed in that way, I see no disparity in the rate of interest allowed in the course of supplementary reasons and the rate of interest claimed by Pacific as part of the February settlement.
31 In the course of my principal reasons for judgment, I deferred a finding as to the reasonableness of that calculation of interest and for the reasons now given, I think that interest component payable under the February settlement should be allowed, noting that Pacific does not claim interest upon that interest component in its calculations for the purpose of making final orders for judgment.
32 In referring to the adoption of the interest rates as outlined in the course of these supplementary reasons, I would adopt what was observed by Bristow J in Miliangos v George Frank (Textiles) Ltd No 2 (1977) 1 QB 489 at 495, namely, that the Court is concerned in an exercise of this kind with fixing a rate applicable for plaintiffs in general and not identifying a rate at which that particular plaintiff may be able to obtain borrowed funds in a particular case. See also Helmsing v Malta Dry Docks (1977) 2 Lloyds Rep. 444 at 449 and BP Exploration v Hunt (No 2) (1979) 1 WLR 783 at 850. I think those observations are particularly pertinent to Mr Dallen's approach in relation to the Hong Kong Interbank Offer Rate referred to earlier in these reasons.
33 As to costs, except in relation to what has been, in effect, an exchange of cross-claims between SSOE and NEAT, I see no reason to depart from the usual order as to costs. In the case of SSOE and NEAT, I think the appropriate order is that each party pay their own respective costs of the cross claims, save for the costs the subject of my judgment of 26 July 2000.
34 In the case of the proceedings between Pacific and BNP, although I have dismissed the summons, save for the cause of action in negligence, I do not see that as any reasonable basis for apportioning costs in any way. The various causes of action relied upon by the parties have overlapped substantially and in viewing the result of the main proceedings I think it is plain that Pacific has succeeded on most factual issues. The judicial exercise involved an identification of what cause of action, if any, those facts may have established. Subject to the order as to the costs of 26 July 2000, BNP is ordered to pay Pacific's costs of the proceedings.
35 It has been submitted on behalf of Pacific that those costs should be assessed on an indemnity basis, having regard to an exchange of communications between the parties as support for that. That refers to an exchange of communications between the solicitors for Pacific and BNP in mid 2000, the effect of which was an offer on behalf of BNP of $100,000, in settlement of Pacific's claims, and on the basis that SSOE paid its own costs. That offer was rejected and a counter offer made which called upon BNP to indemnify Pacific in terms of NEAT's letters of indemnity, with Pacific bearing its own costs of the proceedings. That offer was rejected and although there were other communications, that was the substance of the exchange.
36 In my view, that formed no reasonable basis for ordering costs on an indemnity basis. While BNP's position represented no reasonable offer, the response of Pacific could not be regarded as a true compromise and, in the circumstances as stated, I see no reason to depart from the usual order as to costs.
37 As between BNP and NEAT, it has been submitted on behalf of NEAT that its cross-claim against BNP was purely defensive. There is some substance in that. The history of NEAT's involvement in these proceedings began with its joinder as second defendant by Pacific. Those proceedings were discontinued on 18 June 1999 and NEAT was only brought into the proceedings by BNP's cross-claim on 13 August 1999. NEAT did not respond by way of cross-claim until 10 March 2000, the same date as its cross-claim against SSOE, who had initiated the fifth cross-claim against NEAT on 7 October 1999.
38 Having regard to that sequence of events, I think it is reasonable to treat NEAT's cross-claim as one which would not have been brought had not BNP brought NEAT into the proceedings by way of its cross-claim. Notwithstanding, I think NEAT's claim in negligence went beyond a mere defensive claim, in particular, in relying upon NEAT's case of negligent advice by BNP. While both BNP and NEAT's cross-claims have been dismissed, I think the appropriate order in the circumstances I have outlined is that BNP should pay two-thirds of NEAT's costs of those cross-claims.
39 In the case of BNP's cross-claim against SSOE, BNP must pay SSOE's costs.
40 It has been submitted on behalf of SSOE that a special order as to costs should be made on an indemnity basis, having regard to BNP's failure to make any substantial admissions of fact, notwithstanding the service of a notice to admit by SSOE on 2 June 2000. It was also submitted that it should have been known by BNP that its cross-claim against SSOE would fail, that it raised time wasting defences which were unjustified: in particular, that BNP alleged illegality of the switches of the subject bills of lading, that BNP was unaware of the switch and that BNP conducted a large part of its case in assisting NEAT in its claim against SSOE. In that respect, it was noted that BNP was NEAT's secured creditor.
41 Further, it was contended that BNP have unreasonably rejected settlement overtures as evidenced by the affidavit of Elizabeth Jacqueline Rusiti sworn 5 October 2001. That affidavit evidenced a more significant attempt at settlement between BNP and SSOE than that between BNP and Pacific.