What weight should be given to the draft LEP?
10Mr Drury, for the council, and Mr Hemmings, for the applicant, agreed on the relevant authorities for considering the weight that should be given to the draft LEP, although they ultimately come to different conclusions. They agree that the weight to be attributed to a draft environmental planning instrument will be greater if there is a greater certainty that it will be adopted ( Terrace Tower Holdings Pty Ltd v Sutherland Shire Council (2003) NSWCA 289 at par 5). Relevantly, in Terrace Tower , Spigelman CJ states at pars 6 and 7 that:
6. Notwithstanding 'certainty and imminence', a consent authority may of course grant consent to a development application which does not comply with the draft instrument. The different kinds of planning controls would be entitled to different levels of consideration and of weight in this respect.
7. Where a draft instrument seeks to preserve the character of a particular neighbourhood that purpose will be entitled to considerable weight in deciding whether or not to reject a development under the pre-existing instrument, which would in a substantial way undermine that objective.
11They agreed that the draft LEP is imminent and certain given that it has been gazetted but differ on whether the proposed development will preserve the character anticipated by Zone R2 Low Density Residential and whether the proposed development will substantially undermine the objectives of the zone. The objectives of the zone are set out below although Mr Drury and Mr Hemmings agree that only the first objective is relevant:
Zone R2 Low Density Residential
1 Objectives of zone
· To provide for the housing needs of the community within a low density residential environment.
· To enable other land uses that provide facilities or services to meet the day to day needs of residents.
· To ensure that non-residential land uses are located in a context and setting that minimises impacts on the amenity of a low density residential environment.
· To allow for a range of community facilities to be provided to serve the needs of residents, workers and visitors in residential neighbourhoods.
12Mr Drury and Mr Hemmings also rely on the findings in Blackmore Design Group Pty Ltd v North Sydney Council [2001] NSWLEC 279, where Lloyd J relevantly states:
30. Whether one applies the test of "significant weight", or "some weight", or "considerable weight" or "due force" or "determining weight" to the later instrument is not, however, the end of the matter. The savings clause still has some work to do. The proposed development is a permissible development by dint of the savings clause. In giving the 2001 LEP the weight of being imminent and certain, that does not mean that there is no further inquiry. It is necessary to look at the aims and objectives of the later instrument and then see whether the proposed development is consistent therewith. Various expressions have been used to define this concept, but the approach which has been favoured in the Court of Appeal is to ask whether the proposal is "antipathetic" thereto ( Coffs Harbour Environment Centre Inc v Coffs Harbour City Council (1991) 74 LGRA 185 at 193).
31. This approach was adopted in the cases to which I have referred. In Mathers v North Sydney Council Talbot J (as noted in par [22] above) attributed significant weight to the then draft LEP to the extent the Court ought to be satisfied that approving the development would not detract from its objectives as expressly stated or reflected in the proposed controls.
32. In that case Talbot J refused the appeal on the ground that the proposed development was inconsistent with the proposed planning controls in the draft local environmental plan.
33. Similarly, in Architects Haywood & Bakker v North Sydney Council after stating that significant weight should be placed upon the provisions of the draft plan, Pearlman J considered whether the proposed development accorded with the planning approach and objectives of the proposed controls in the draft local environmental plan. It was the fact that the proposed development ignored the planning approach adopted by the draft LEP that led Her Honour to refuse the application in that case.
34. In Edward Listin Properties v North Sydney Council Talbot J said (at par [15]):
Although it may not be appropriate to dwell too heavily upon the detailed controls implemented by the draft LEP, it is certainly important to have regard to the broad objectives which the draft planning instrument seeks to achieve.
35. His Honour further stated (at par [35]):
...If what is proposed is unsatisfactory in general terms and inconsistent, in particular, with the expressed future planning objectives for the area, then it should be rejected.
36. In Walker v North Sydney Council Cowdroy J found that the evidence established that the development application was contrary to the planning objectives of the locality, for which reason His Honour rejected the development application.
13The findings in Blackmore Design and Terrace Tower provide that notwithstanding that the proposed development is prohibited under the draft LEP, it is a permissible development because of the savings clause. Even if the draft LEP is imminent and certain, it does not mean that there is no further inquiry. It is necessary to look at the aims and objectives of the later instrument and then see whether the proposed development undermines the relevant aims and objectives, in a substantial way. In this case, Mr Drury submits that the proposed development undermines the relevant objective of the R2 Low Density Residential zone in a substantial way whereas and Mr Hemmings submits the opposite.
14In considering the approach in Blackmore Design and Terrace Tower, I am satisfied that development consent should be granted for a number of reasons. First, there was no disagreement that the proposed development is permissible by way of the savings clause in LEP 2011. Second, there was no disagreement that the proposed development satisfies all the relevant requirements in DCP 2005 and that there are no merit concerns with the proposed development. Third, and having regard to the relevant objective, I do not accept that the proposed development substantially undermines the objective of the R2 zone of providing housing within a low density residential environment. Low density residential environment is not defined in LEP 2011 however any consideration of the proposed development against the objective cannot reasonably be undertaken without a consideration of the existing built form in the area. I agree with Mr Hemmings that given that the proposed development enjoys the benefits of the savings provisions, the test of whether the proposed development undermines the relevant objective of the R2 Low Density Residential zone, in a substantial way, is essentially a test of whether the proposed development sits comfortably in its local environment or setting, particularly given the wide range of building forms within the R2 Low Density Residential zone.
15The southern boundary of the site forms part of the boundary between the R2 zone and the higher density R3 zone. Because of the down zoning of the site from LEP 2001 to LEP 2011, there are unsurprisingly, and a number of multi unit housing developments already constructed within the R2 zone on the northern side of Belmore Street. There are also a number of multi unit housing developments in Gladstone Street, to the south of the site, and to the east on the opposite side of adjoining playing fields within the R3 zone. A duplex development is located directly to the south of the site, in Corry Court, within the R3 zone. There are also many single residential dwellings located within both the R2 and R3 zones. These single residential dwellings are varied and range from older single storey style cottages to large two-storey contemporary designs.
16In this context, I am satisfied that the proposed development is acceptable. I note that the amended plans sought to address the relationship with adjoining development by a reduction in the height of the roof adjoining the duplex development in Corry Court. When viewed from Corry Court, and the adjoining playing fields, there is a compatible visual relationship between the proposed development and the adjoining duplex development. When viewed from the narrower Belmore Street frontage, the proposed development presents a well articulated elevation that is compatible with the existing streetscape and less bulky than the existing multi unit dwellings in this street. While having a larger appearance than the existing single dwellings in this street, I do not accept that it is unacceptable in this context.