(ii) alleged representations that design drawings for off site fabrication would be forwarded to WGE immediately after 8 January 1998.
16 The issues before Bergin J did not treat with those particular allegations.
17 There are two relevant elements to a consideration of the way in which the arbitrator dealt with the conduct pleaded at paragraphs 28(a) and (b) of the amended points of claim.
18 Firstly the matters, the subject of the alleged representations were claimed by WGE in its variation claim 22.00, which variation claim was not the subject of any challenge by any party to this Court in relation to the proceedings before Bergin J.
19 Secondly those variation claims that were the subject of challenge and dealt with by Bergin J were variation claims that never raised any issue of misleading or deceptive conduct as pleaded in paragraphs 28(a) and (b) of the amended points of claim.
Variation Claim 22.00
20 The alleged claims of misleading or deceptive conduct contained at paragraphs 28(a) and (b) of the amended points of claim were the subject of a specific claim for damages as part of WGE's variation claim 22.00 in the sum of $3,227,196 million. The arbitrator awarded WGE the sum of $2,709,556 for that claim. The first two pages of the claim submission for variation claim 22.00 submitted to BLL which was also in evidence before the arbitrator are appended to this Judgment.
21 The "Description" and "Basis of Claim" at pages 1 and 2 of that submission by WGE dealt with the very matters, the subject of the first alleged representation at paragraph 28(a) of the amended points of claim. There is a specific reference to the first alleged representation (paragraph 28(a)), namely, "insufficient information from BLL" that prevented shop detailing to proceed according to the contract program.
22 The second pleaded representation at paragraph 28(b) of the amended points of claim, namely that design drawings for off site fabrication would be forwarded to WGE immediately after the letter of acceptance/intent of 8 January 1998, is also dealt with at page 1 of the WGE claim submission. The design drawings referred to in the amended points of claim were the same as the project manager's working drawings and the architectural and mechanical drawings that were progressively issued by BLL referred to in the claim submission.
23 A copy of paragraph 124 of WGE's submissions to the arbitrator alleging misleading or deceptive conduct raised by paras 28(a) and (b) of the amended points of claim in the context of variation claim 22.00 is appended to this judgment.
24 WGE in the present notice of motion seeks that those variation claims, the subject of BLL's appeal and the Bergin J judgment, be reviewed by the arbitrator on the basis of alleged misleading and deceptive conduct, notwithstanding that misleading or deceptive conduct was never alleged by WGE in its submissions in relation to those variation claims before the arbitrator but was alleged only for variation claim 22.
25 An extract of WGE's submissions to the arbitrator in relation to each of those variation claims, the subject of BLL's appeal to Bergin J, namely variations 22.5, 22.7, 22.15, 22.18, 22.19, 22.20 and 22.26, (see paragraph 11 of the summons) is appended to this judgment.
26 None of the variations the subject of her Honour's judgment were part of WGE's "consolidated" variation claim 22.00. None of those variations were presented by WGE as a claim arising in relation to any allegedly misleading or deceptive conduct. Every claim was submitted as a variation claim or a claim for extra work by reason solely of a dispute between the parties as to whether WGE was obliged to perform works shown on the tender versus the contract drawings. The arbitrator found in favour of WGE on the basis that the works shown by the contract drawings constituted a variation because WGE's contact was said to be based on the tender documents. It was that matter and those variations against which BLL successfully appealed to her Honour.
27 WGE's submissions of misleading and deceptive conduct before her Honour were responded to by Mr Bathurst QC, counsel for BLL. A copy of the transcript page 19.11 to 19.32 is appended to this judgment. The matter was dealt with by her Honour at paragraph 43.
28 The exercise of the Court's discretion in relation to remitting of matters to the arbitrator, even assuming a relatively wide construction be given to s 43, mandates the dismissal of the notice of motion. Amongst the many reasons which mandate as it seems to me that the notice of motion be dismissed are the following:
· Having failed before Bergin J in terms of her Honour's upholding of the appeal and remitter of the award to the arbitrator to deal with contractual issues, WGE now and against the event that it may be unsuccessful upon that remitter, seeks by Court order under s 43, to have the arbitrator directed to consider the issue in a completely different way to that in respect of which WGE conducted its initial case in terms of the allegedly misleading or deceptive conduct.
· WGE seeks to have remitted to the arbitrator an approach to the matters the subject of the arbitration in respect of which no application by the defendant to the arbitrator for the same findings had ever been made.
· There is no relevant injustice as it seems to me suggested or shown by the defendant.
· There is no error by the arbitrator in terms of having dealt with the arbitration in the manner in which the respective parties put matters to the arbitrator suggested or shown.
· There is no appeal if there be such error, which appeal would necessarily have required to be regularly before the Court under s 38.
29 There is then the circumstance that Bergin J's judgment includes the following:
"It is apparent from paragraph M15 of the Award that the Arbitrator concluded that if the representations were made they were deemed to be part of the contract. The Arbitrator recorded his earlier conclusion that the representations were made "though possibly not completely to the extent" that the defendant contended (M16). There does not appear to me to be any finding that the plaintiff made any representations that were misleading or deceptive in respect of the subcontract issue. I reject the defendant's submission that the plaintiff's rights would remain unaffected."
[Paragraph 43 of the judgment of Bergin J of 26 June 2002].
30 The whole of the principles which inform the proper approach of the Supreme Court to the provisions within the Commercial Arbitration Act permitting judicial review of awards is based upon the significance of a relatively short period of time in which to invoke the jurisdiction of the Court [see part 72A rule 5 of the Supreme Court Rules], and is based upon the elementary proposition that the Court has a discretion in relation to the occasions when it may remit matters whether pursuant to s 38(3) on the determination of an appeal under s 38(2) or whether pursuant to s 42 or whether pursuant to s 43.
31 As I read the authorities to which I have referred, the interests of justice are untrammelled in the exercise of the Court's discretion insofar as s 43 is sought to be relied upon as the foundation for a remitter order. However of crucial significance, even where s 43 only is in focus, is the obvious necessity that a s 43 remitter be grounded upon some fundamental injustice generally in the sense explained and already referred to by Lord Donaldson.
32 The circumstances presently before the Court in relation to the subject notice of motion fall very far wide of satisfying me that there is any form of injustice at all, let alone a fundamental injustice in terms of the manner in which the subject arbitration was regularly dealt with by the arbitrator and in terms of the case put to the arbitrator by both parties and most particularly by the defendants.
33 The defendant's written submissions are appended to this judgment.
34 Paragraph 4 of the defendant's written submissions are incorrect. Whilst it may be that "particulars of damage at paragraph 25 are referred to at paragraph 22" of the amended points of claim (which refers to each and every variation claim listed at paragraphs 5 and 22 of the amended points of claim), as I have already said, on the materials presently before the Court, WGE did not conduct its case on the basis of any allegedly misleading or deceptive conduct as pleaded at paragraphs 28(a) and (b) of its amended points of claim other than in relation to variation claim 22.00.
35 Paragraphs 31, 32 and 33 of the plaintiff's written submissions are of substance and read as follows: