Council also appears to have assumed that the condition imposes some obligation 'in respect of undergrounding the overhead cables now in the air space of O'Riordan Street' (sic). Whatever that phrase means it does not form part of condition 32. More importantly, it emphasises the point that the condition has not been expressed in clear and unambiguous terms. "
77 There was subsequent correspondence between Lorus and Council (Exhibit C1, tabs 29-30), before a letter of demand was sent by Tim O'Connor to the Secretary of Ralansaab on 12 October 2007.
78 Mr O'Connor, in his affidavit sworn 12 January 2009, deposes to his exchange of correspondence with Patrick O'Brien, and copies of various letters are annexed to his affidavit.
79 On 19 October 2007, Patrick O'Brien responded to Tim O'Connor's letter of 12 October, and sought, on Ralansaab's behalf, particulars of Council's claim.
80 Mr O'Connor replied on 25 October 2007 (Annexure 'D') "that it is quite clear as to what the condition required in that it required the undergrounding of all aboveground electricity and telecommunication cables within the road reserves adjoining the site". He went on to assert that "your client clearly understood the meaning of that requirement in relation to the Church Avenue, Mascot Road frontage but failed to undertake that work in the O'Riordan Street frontage", and continued "we do not propose debating definitions of various words used in the condition. Conditions of consent are not interpreted in the same way as legislation and simple a (sic) reading of the consent and the condition makes it plain as to the requirements of the condition".
81 Patrick O'Brien responded at length on 5 November 2007 (Annexure 'E'), repeating the respondents' earlier contention that the requirements of the relevant condition were not clear. His letter also asserted that "Council has misconceived and misstated the nature and extent of the relevant works carried out by our client. Our client has placed power and telecommunication cables underground in Church Avenue, O'Riordan Street and Hughes Avenue, Mascot … Those works were carried out under the development consent as modified and in accordance with relevant construction certificates and also consents issued under section 138 of the Roads Act". The works in Hughes Avenue Mascot were never raised by Council, in either its letter to the principal certifying authority, and/or in its letter to Ralansaab on 12 October 2007.
82 Mr O'Brien enclosed the Energy Australia document dated 23 August 2002, and confirmed that Enerserve "A Business of Energy Australia" had been retained to carry out the cabling works. Also enclosed was a certificate of practical completion, dated 20 February 2006, which had been furnished to Council under cover of a fax from Saab Corp on 21 May 2006. Mr O'Brien indicated that any proceedings would be resisted and that the correspondence would be relied upon for an order that Council bear costs on an indemnity basis.
83 It is noted that many of the arguments now raised in the respondents' primary defence, and on discretionary issues, were raised by Mr O'Brien in his letter of 5 November 2007. Mr O'Connor replied on 5 December 2007 (Annexure 'F'), distinguishing the import of the respective conditions.
84 Mr O'Connor also deposed to having sent a letter of demand to Saab Corp on 9 July 2008 (Annexure 'G'), enclosing a copy of the letter to Ralansaab of 12 October 2007. On 17 July 2008, Patrick O'Brien sought particulars on behalf of Saab Corp (Annexure 'H'). Detailed particulars were not provided, but Mr O'Connor responded on 14 November 2008 (Annexure 'J') that both the owner and the builder were responsible for any failure to comply with condition 32, and/or condition 34. On 18 November 2008, Mr O'Brien sought copies of documents relied upon by Council (Annexure 'JJ').
The Owners' Corporation
85 Mr O'Connor had also sent a letter of demand to the Owners Corporation on 12 October 2007 (Annexure 'K'), raising the access question. The Strata Managers, Linders Property Group, sought particulars on 25 October 2007 (Annexure 'L'). On 14 November 2007, O'Connor replied to Linders (Annexure 'N'), indicating that Council thought it unlikely any work would be required on the common property. He sought confirmation that electricity into the subject site was already undergrounded. On 9 July 2008 (Annexure 'M'), O'Connor advised Linders that, as there had been no response to the letter of 14 November, Council would join the Owners Corporation in these proceedings, to ensure that any orders made could be complied with.
The Council officers
86 Phoebe Mikhiel has been with the Council since May 2006 as a "team leader development assessment". She is qualified as a town planner and has been employed in that capacity with various councils in Sydney.
87 In her first affidavit, dated 12 March 2009, she traced the history of the DA 03/013 dated 5 July 2002, the consents, and the deeds. In her second affidavit, dated 20 August 2009, she dealt with the Energy Australia quote dated 23 August 2002, and the design plan issued on or about 6 April 2004. The quote refers to the removal of eight poles, and the plan to the removal of only three. The quote provides for the installation of five light standards while the design provides for the installation of only three. She inspected the subject premises and surrounding areas on 13 August 2009, and observed three new steel light poles located in the vicinity - one in Church Avenue approximately 32m from O'Riordan Street, one at the corner of Church and O'Riordan, and one opposite the subject site between Hughes Avenue and "Caryina" (sic) Avenue along O'Riordan Street. Three wooden poles remained on O'Riordan Street adjoining the development.
88 Ms Mikhiel also swore affidavits on 10 September 2009 and 2 November 2009, following the production of documents by Energy Australia. Of the 8 identified poles (see [58] above), those numbered B, C and D remain in the locations shown on the relevant plan at Annexure 'A' of her November affidavit.
89 Rodger Dowsett is the Council's Director, Planning and Development. In his affidavit of 13 November 2009 he responded to some evidence given by Joe Saab, and refuted some of the alleged conversations, but he acknowledged that the Saab interests have undertaken works and commitments to Council, that were not strictly their obligation, for example, the construction of the footpath in Church Avenue to the boundary line of the Sydney Water land, and the agreement reached in respect of under-assessed s 94 contributions.
90 Mr Dowsett became aware in late September 2006 of a possible undergrounding non-compliance on another property within sub-precinct 1 of Mascot Station precinct, 149-161 O'Riordan Street. It occurred to him that a similar non-compliance might have occurred on the subject site, but he did not inspect the environs of the subject premises until about 16 July 2007. He wrote to the certifier, Lorus, on 18 July 2007. He corroborates Mikhiel's evidence regarding the three wooden telegraph poles remaining on the footpath adjacent to the premises, and says that they had been in that position from at least 2002.
91 He asserts that, as a certifier had been engaged, "it was not the role of the council to check the accuracy or otherwise of the occupation certificate sent to the council by the PCA".
92 Mr Dowsett's second affidavit, dated 26 February 2010, mainly concerns the s 94 issue (pars 1 to 9). Mr O'Connor had advised the Council on 24 November 2003 that the "under-assessed" s 94 contributions could not be recovered, as the consent had been issued and the applicant had acted upon it in preparing the development of the site. Agreement was reached on a supplementary payment when a modification was approved in December 2003. The Saab interests agreed to make an additional payment of $100,000 on the basis that they may seek to add further apartments to the building. In the end, two payments of $100,000 were made, in addition to the original s 94 contribution, but the levy of $30,885.81 in respect of the additional apartments (an increase from 108 to 111) was not pressed. The overall payment is still approximately $165,000 less than the correctly calculated total s 94 contributions.
93 Dowsett denies (par 10) that, at the time of a conversation with Anthony Saab regarding timber edging to the landscaped areas on the O'Riordan Street frontage, he asked Anthony for a certificate certifying that the undergrounding work had been completed.
94 In the final paragraph of this affidavit (par 11) he says:
" Based upon my knowledge of approvals granted for residential flat buildings in Council's area and in particular the Mascot Station Precinct, this was the first residential flat building approved in the Mascot Station Precinct and following this approval it then became Council's practice to:
(a) Incorporate a condition which requires the applicant to enter into a Deed which is then supported by a caveat registered over the title to the property when the development requires road widening such as to ensure that the road widening is undertaken and dedicated as a road before the development is completed. Condition 34(a) was imposed in relation to the Stage 1 development approval and was the first of such conditions imposed upon a consent for a residential flat building in the Mascot Station Precinct where road widening was proposed.
(b) Where undergrounding of electricity and telecommunications cables within the road reserve was required, that condition is not normally supported by requirement for the applicant to enter into a Deed with Council supported by a caveat registered over the title to the property. Condition 32 of the Stage 2 consent did not impose a requirement for a deed to be entered into in relation to the undergrounding works for O'Riordan Street.
The deed prepared was only prepared in relation to Church Avenue in accordance with condition 34 of the Stage 1 Development Consent. Once the works covered by the deed were completed Council was then obliged to withdraw the caveat over the title to the property."
95 Two other Council officers, Peter Ward, an administrative planner, and Martyn Perry, the human resources manager at the Council, provided affidavits in February 2010, in response to evidence given by the Saabs, asserting that many Council officers made many visits to the site, but, relevantly, the Saabs say, those officers made no complaint regarding the cabling works being inadequate.
96 Mr Ward denies that he ever actually visited the site, although he is familiar with it, and Mr Perry deposed to the periods of service, and assigned duties, of various other officers mentioned in the Saab evidence, namely Phillip Cornish (8 December 2003-3 March 2006), Julie Gee (since 28 February 1994), William Marsh (29 July 1996-19 June 2009); Gary Wright (since 28 February 1977); Oman Wijayaratana (27 July 1998-11 April 2008), Michael Lee (13 December 1999-19 December 2003). Exhibit C5 is a copy of Michael Lee's letter of resignation dated 2 December 2003.
G. The Respondents' Evidence
97 All five individual respondents swore affidavits and gave oral evidence at the hearing of these proceedings.
98 William O'Dwyer swore one affidavit before Tony Saab was joined in the proceedings and one after. In his role with Ralan Group he came to know and work with Tony as "a builder and real estate developer". In June 2003 he learned that Colliers was marketing the subject site with the benefit of the residential apartment consent and discussed with Tony Saab the formation of a joint venture to acquire and develop the site. (The Colliers materials are Annexure 'A' to his 30 July 2009 affidavit).
99 Ralansaab was incorporated, the contract of sale was exchanged, and O'Dwyer began marketing apartments "off the plan" with great success. Once 60% had been sold, the finance was secured and development commenced. O'Dwyer deposes (1) that he had little involvement in the actual development, other than signing occasional documents as a director of Ralansaab, and (2) that he knew no details of the conditions of consent until he learned from Tony that Council had written to the certifier in July 2007 about the undergrounding. He left it to Tony Saab to liaise on the owner's behalf with the contracted builder, Saab Corp, but Tony asked him to attend meetings with the Council, commencing December 2003, regarding the s 94 issue and various modifications of consent (see Exhibit C2, tab 2, re February 2005). It was O'Dwyer who put to Council the offer of $100,000 by way of extra s 94 contributions, which Dowsett accepted. As the building neared completion, the marketing continued until all apartment sales were finalised in mid 2006.
100 Tony Saab deposed that his involvement in the actual development was limited to signing documents as a director of Ralansaab, and attending a few meetings with Council, once the s 94 issue was raised at the time Council was considering modification of the consent in late 2003.
101 The three Saab sons' evidence indicates that Joe and Anthony jointly assessed the prospects for successful development on the subject site, when O'Dwyer and Tony Saab were deciding to buy it. Michael was not involved with Ralansaab at the time the site was acquired. Nor was Anthony directly involved in the acquisition, but he deposes to deciding, with Tony and Joe, at the time of acquisition, that some modifications of the Moscat consent would be desirable.
102 Joe and Anthony provided almost identical affidavit evidence on most matters. They say that, "with the help of other family members", they undertook, in about June 2003, a detailed review of the conditions of consent and approved plans, as contained in the Colliers material, and prepared a preliminary estimate of the project cost. They did not see the URBIS report, nor retain a consultant planner to review any documents, including the DCP. They were aware of conditions 34 and 32, and their inquiries of Colliers brought them the 23 August 2002 Energy Australia quote, provided to Caverstock on Moscat's behalf. Joe and Anthony both depose that they "also reviewed the design referred to in [that] quote".
103 In June or July 2003, Joe telephoned Jason Henniker of Energy Australia (see [47]ff above), had a conversation with him, and then met him, with Anthony, at the subject site. They walked the perimeter, and observed the poles and overhead lines in both streets. They "also looked at power lines adjacent to the property that crossed O'Riordan Street and that were (sic) connected to a wooden pole opposite the property in Hughes Avenue, Mascot" (Joe's par 15, 1 April 2009).
104 Both brothers gave the court clearly co-ordinated accounts of a rather controversial conversation they allege took place with Mr Henniker during that meeting in June or July 2003 (see Joe's par 16, and Anthony's par 19).
105 Joe says that, at that meeting, he showed Henniker a copy of the Energy Australia quote of August 2002, and, according to Joe's version, which is fully corroborated by Anthony's version, the following conversation took place:
"[Joe] said to him: 'Can you tell us what the work set out in this quote generally involves?'
He said: 'Energy Australia will remove the existing poles in Church Avenue and O'Riordan Street adjacent to the property as well as the pole on the other side of Church Avenue near the Caltex station and the pole in Hughes Avenue near the real estate agent's office. The footpath areas on both sides of Church Avenue and O'Riordan Street will be excavated and low voltage cables installed. The roadway in Church Avenue, O'Riordan Street and Hughes Avenue will also be excavated and cables installed underground across the roadway. High voltage underground mains will be relocated and electrical pillars and light standards will be installed in Church Avenue and O'Riordan Street. The footpaths and roads will be reinstated and other ancillary work undertaken".
Anthony said: 'Have you seen the Council's conditions of consent for the development?'
He said: Yes. They were provided to Energy Australia and we inspected them and also spoke to Council before we issued the quote?'
Anthony said: 'So all of the undergrounding work that Council requires to be carried out has been detailed in the quote?'
He said 'In relation to the relocation of aboveground electricity cables, Yes. You will still need to liaise with Optus and Telstra regarding the relocation of telecommunications cables. We don't do anything in relation to the Optus cable that is carried on our poles'."
106 Both Joe and Anthony say they formed the opinion that, if they did what the Energy Australia quote detailed, it would satisfy both conditions 32 and 34: "The plans forming part of the development consent did not contain any detail in relation to these matters and were of no assistance to me in identifying what work had to be undertaken in order to comply with that aspect of those conditions" (Joe's par 17).
107 They also reviewed documents obtained on Moscat's behalf from Optus and Telstra for the purpose of ascertaining costs to be incurred relocating telecommunication cables to satisfy the relevant parts of condition 32 and 34. Tony Saab and O'Dwyer, presumably after a favourable opinion from the brothers, then responded positively to the invitation from Moscat, and Ralansaab went on to retain Saab Corp to carry out the development. Saab Corp appointed Russell O'Brien of Lorus on or about 27 January 2004 to obtain a construction certificate (2004/0003a) for the stage 1 works. Construction of the development commenced following the issue of the stage 1 construction certificate. Saab Corp appointed Bill Gereige as its project manager.
108 In "about March 2004" Joe requested Energy Australia to issue an updated quote to carry out the works described in the Energy Australia quote. At around that same time the DA for the Church Avenue road widening and associated civil works was lodged with Council (No.04/395 - Exhibit C2, tab 6).
109 Jason Henniker contacted a colleague in Energy Australia on 19 March 2004 by email, saying (Exhibit C3, vol 2, tab 15, fol 541):
" Back in 2002, Doug Chalker provided cost (sic) to carry out the UG of some services in O'Riordan St. The project is now back up and running however the number of services required to be UG has changed and it is now only two services. Is it possible to get an updated price on the UG of the services. The services are 128 O'Riordan St (100amp three phase) & Caltex Service Station cnr O'Riordan & Church Ave (200amp)."
110 On 5 April 2004, Henniker wrote to "Saab Constructions" (Exhibit C3, vol 2, tab 15, fol 540) referring to "our verbal conversations on site discussing the road widening in Church Avenue and how this will impact on Energy Australia's existing assets". No timeframe was put on those "conversations", but the court notes the use of the plural, c.f. the evidence of the Saabs that there was only one on-site conversation involving them, that being the one held in June/July 2003.
111 Henniker advised that Energy Australia had investigated, and had determined "that the overhead low voltage mains including street lighting will need to be removed and installed underground. The existing underground high voltage cables in Church Avenue will also need to be relocated to ensure correct cover is maintained over the cables". At law, only Energy Australia could carry out such works.
112 On the other hand, the removal of overhead low voltage mains was expected to result in the need to underground two low voltage services, namely 128 O'Riordan Street and the Caltex Service Station. That latter work is "contestable", so other accredited service providers could carry it out.
113 A customer initiating a request for undergrounding of overhead mains has to gain agreement and written approvals from parties affected by the proposal. It was also the obligation of the customer to negotiate and pay for the removal of any Optus or Telstra cables on Energy Australia poles (Exhibit C3, vol 2, fol 540 in tab 15).
114 In Exhibit S2, tab 4 (also Exhibit C4), is a plan numbered CCZ011063 and dated 6 April 2004, clearly referable to the works. The "scope of works" described on that plan is as follows:
" Removal of four spans of LV open wire
Removal of one 100amp three phase service & one 200amp three phase service.
Removal of three LV wood poles.
Replacement of two wood poles.
Installation of three steel street light standards.
Installation of two LV pillars.
Installation of LV UG cable (incl two services) & associated conduits to replace the overhead wires.
Diversion of two HV cables " (emphasis added)
115 In Exhibit C3, vol 2 (at tab 15, fols 526-536), there is a series of "plans" entitled "Underground LV Overhead Wires & Diversion of HV cables in O'Riordan St and Church Ave, Mascot", some of which (fols 528-535) appear to be partially annotated enlargements of parts of the 6 April 2004 plan. Two others (fols 527 and 536) are explanatory of the LV system (existing and proposed) and the location of poles, respectively.
116 The remaining page of the series (fol 526), again dated 6 April 2004, carries a "Detail (sic) Description of Work". It sets out lists of tasks under the headings "Overhead Work", "Jointing Work", and "Cable Laying work".
117 Under "Overhead Work" the following listed items are of interest regarding poles and light standards:
"…
B,C,F: Remove pole and associated equipment on poles.
A: Replacement of existing pole …
D: Replacement of existing pole …
…
G: Installation of steel street light standard …
H: Installation of steel street light standard …
F: Installation of steel street light standard …
…"
118 On 27 May 2004, Enerserve wrote to Joe Saab (Exhibit C3, vol 2, tab 15, fols 509ff, Exhibit S1, tab 5 and Exhibit S2, tab 5) to thank him "for the opportunity to submit a proposal for the above project", summarised as "underground mains work in Church Ave and O'Riordan St Mascot". (It is to be noted that the reference on the top of the 27 May letter is CCZ011603, instead of CCZ011063).
119 The letter pointed out that Energy Australia "must carry out the works", as they are deemed "recoverable". "Enerserve carries out Recoverable works on behalf of EnergyAustralia". A contract/proposal was submitted, "based on the works being carried out in accordance with Energy Australia's design CCZ 011603 dated 6 April 2004", and Joe was invited to accept the proposal by signing Acceptance of Offer form. The price (on fol 517) is $238,777 including GST. The general terms and conditions are set out (at fols 520-523), and include a process for "changing the specifications" (Part C, clause 7, on p 12 of 17). The works were to be completed in ten weeks.
120 The "project brief" (Exhibit C3, vol 2, fol 513) is described as follows:
" Relocate high voltage underground mains and underground the existing overhead low voltage mains in Church Avenue and O'Riordan Street, Mascot adjacent to the premises of SAAB Constructions, 109-123 O'Riordan Street Mascot as detailed in Energy Australia design CCZ011603 dated 6 April 2004."
121 Joe signed the acceptance form (at fol 508) on behalf of "Saab Constructions".
122 On 17 June 2004, Henniker wrote to Joe Saab (see Exhibit C1, tab 10, and Exhibit S2, tab 6) thanking him for his "new application for supply concerning the provision of electricity supply to the proposed development at 109-123 O'Riordan Street", and confirming Saab Corp's acceptance of the proposal. The letter confirmed that a new substation would not now be needed for the project, and explained that the work would involve "both non-contestable and contestable components". The letter indicated that Enerserve, "an accredited service provider", would provide "a complete design and construction package". Anthony faxed a copy of this letter to Dowsett (par 26 of Anthony's affidavit 30 July 2009).
123 On 18 October 2004 (Exhibit C3, vol 2, tab 15, fols 505-6), Energy Australia sent a letter to Council addressed to "Will Marsh" headed "Street Lighting - 109-123 O'Riordan Street, MASCOT". The letter outlined that certain work was to be done by Energy Australia - 2 wooden light poles in O'Riordan Street and one wooden light pole in Church Avenue were to be removed and replaced by steel columns, The Council was invited to accept the terms in the quotation (which also had the number CCZ011063).
124 The Council accepted (fol 506) all the terms of that quotation on 22 October 2004.
125 Council approved the widening of Church Avenue and other civil works required under condition 34(b). The apartment building "and other improvements" erected on the property were largely completed by late October to early November 2005. When the cranes were removed, Saab Corp began widening the road in Church Avenue in conjunction with (a) the cabling works the subject of the Enerserve proposal, (b) the relocation of telecommunication cables underground by both Optus and Telstra, and (c) associated kerbing, guttering, paving, and landscaping works. Those works were generally supervised by Phillip Cornish, a Council engineer, who the Saab brothers say regularly visited the site. He "made no comment regarding any inadequacy in the cabling works". Joe also deposes that Dowsett took a close interest in the project and visited it frequently, but at no time drew any attention to, or made a comment or complaint, regarding any alleged inadequacy in the cabling works.
126 The Strata subdivision of 111 residential units and one commercial unit received consent on 9 November 2005 (Exhibit S1, tab 7).
127 On 23 November 2005 (Exhibit C3, vol 2, tab 15, fol 504 and Exhibit C1, tab 22) Henniker faxed "Bill" (presumably the Saab Corp project manager, Bill Gereige) in the following terms:
" In regards to the removal of overhead wires underground in Church Ave, Mascot, EnergyAustralia can confirm that final notice to pay outstanding money on the project has been received. EnergyAustralia still has some further works to be completed which will be programmed for completion in the coming weeks ".
128 Enerserve's Tony Gale faxed Bill on 12 December 2005 (fol 503) to confirm that all invoices had been issued to Saab Corp, and paid in full, regarding the work at 109 O'Riordan Street, namely:
" The relocation of Underground High Voltage cables, Undergrounding of Overhead Low Voltage cables, Removal of all associated poles streetlights & Optus cables and the installation of 3 steel streetlight standards and underground cables. Also the transferring of supply to 2 premises from overhead to underground in the dedicated area. Other works that have been invoiced & paid in full is the installation of a 400 amp low voltage supply to the above premises ".
129 On about 23 November 2005, Cornish told Joe Saab that Enerserve/Energy Australia had not erected two light standards in the Church Avenue road reserve, but had agreed with Cornish to fix the omission before Christmas (Joe's affidavit 21 January 2010, par 7). This work would, however, require reinstatement of the footpath in Church Avenue, and Joe undertook that Saab Corp would do so (see written undertaking at Exhibit C1, tab 23, and Exhibit C2, tab 5). Dowsett asked Joe to extend the paving work along Church Street to the west past the adjoining Linear Park. Joe deposes that, although there was, indeed, no obligation on Saab Corp under the development consent to carry out any such paving work, the company willingly committed to doing it.
130 The Council's Julie Gee inspected the reinstatement work, and faxed Anthony on 21 December 2005 regarding some landscaping issues, and some concerns she had about trees.
131 Anthony deposes that, when the installation of the outstanding two light standards in Church Avenue had been completed, Enerserve certified that the cabling works were completed, and issued a certificate of practical completion on about 20 February 2006.
132 The certificate of practical completion of the Enerserve works, signed by Tony Gale, issued on 20 February 2006 (Exhibit C3, vol 2, tab 15, fol 502), and says:
" This work was carried out in accordance with certified design drawing reference CCZ 011063 and EnergyAustralia's Network Standards ".
133 Saab Corp then reinstated the road reserve areas that had been disturbed by their work, and completed the footpath and landscaping in those areas, in accordance with approved plans for reinstatement, the letter Joe issued to the Council on 23 November 2005, and the deed of 12 December 2005.
134 Anthony applied, on behalf of Saab Corp, in early May 2006, for the return of the builders' security deposit of $10,000, securing, among other things, the reinstatement works after completion of the development. Anthony deposed he had to "chase Dowsett" to get this money back. Well after he inspected the site Dowsett rang requiring some timber edging along the O'Riordan Street footpath to "lock in" the paving. Anthony personally attended to the installation of the timber edging along the full length of the O'Riordan Street frontage immediately adjacent to the power poles remaining in O'Riordan Street.
135 Following completion of that work, he wrote to Dowsett on 21 May 2006 (Exhibit S1, tab 10 and Exhibit S2, tab 8), asking him to "please note that undergrounding of overhead low voltage mains, relocation of high voltage underground mains and installation of street lights at the above named property have been completed". He enclosed the Certificate of Practical Completion from Enerserve and confirmed that "upon your request, the timber edging along O'Riordan Street has been installed". He asked for the return of the builders' security deposit, which was subsequently released.
136 On 18 July 2007, Dowsett complained to Lorus about non-compliance with condition 32 and the correspondence between solicitors commenced (see pars [75]ff above).
137 On 22 November 2007, Anthony faxed to Julie Gee an expert report on the trees (see Exhibit C1, tab 31, and Exhibit C2, tab 12). She then asked for some more work to be done, and the expert updated his report in January 2008 (Exhibit C1, tab 32). Gee noted on it "Inspected 30/1/08. Satisfactory". The court assumes that any outstanding bonds were then refunded.
138 Joe and Anthony say that they have always believed that, once the cabling works were certified as completed, they would have satisfied condition 32. Joe says that he was "reassured" in that belief because none of the Council officers he named as site visitors made any complaint (his par 55(a)).
139 Joe also draws attention (in his par 51(i)) to the fact that existing above-ground electricity and telecommunication cables in O'Riordan Street adjacent to the Skyton property at 149-161, about 100m south of the subject land and also within the Mascot Station precinct, had not been replaced by underground cable and street light standards. Joe complains that Council's application of development control C98, and therefore of the DCP itself, has been inconsistent.
140 In his affidavit of 30 July 2009 Joe deposes to having by that date located a copy of the drawing by Energy Australia, dated 6 April 2004, which sets out the works that were subsequently carried out by Saab Corp "in accordance with Energy Australia's guidelines and requirements as evidenced by the certificate of practical completion".
141 All three of Tony Saab's sons deny that they "carried out the development" as alleged in the APOC filed on 9 June 2009. They admit signing various documents, but only as either directors of Saab Corp or as agents for Ralansaab. Joe relies upon a written authority given to him by Ralansaab on 18 May 2004 (see tabs 4 and 18 of Exhibit C2). Anthony mistakenly deposed (in par 3 of his affidavit) that he signed a document as a director of Ralansaab. In oral evidence he corrected that to Saab Corp.
H. Consideration
Liability of the non-corporate respondents
142 Liability of the non-corporate (or individual) respondents arises as an issue only if it can be shown that the company, of which any of them was a director, was "carrying out the development", and that a breach of the Act has occurred.
143 Mr Hale submits that the first and second respondents, being companies, cannot carry out the development without the direction and instruction of individuals. Reliance was placed on Performing Right Society Limited v Ciryl Theatrical Syndicate Limited [1924] 1 KB 1, at 14 and 15, where the relevant test was established by Atkin LJ in these terms (all emphasis added):
" Prima facie a managing director is not liable for tortious acts done by servants of the company unless he himself is privy to the acts, that is to say unless he ordered or procured the acts to be done .
…
If the directors themselves directed or procured the commission of the act …" .
144 In Microsoft Corporation v Auschina Polaris Pty Ltd (1996) 71 FCR 231, Lindgren J (at 243-244) referred to "the 'procured or directed' test, sometimes referred to as the 'authorised, procured, or directed' test …". See also Thomas J in Kalamazoo (Aust) Pty Limited v Compact Business Systems Pty Limited (1985) 84 FLR 101, at 127.
145 In Foxtel Management Pty Limited & Anor v The Mod Shop Pty Limited [2007] FCA 463; (2007) 165 FCR 149, Siopsis J said (at [141], "I prefer to apply the 'direct or procure' test on the basis that it is supported by the weight of the (sic) authority".
146 The implication of the Council's submissions is that some influence was brought to bear by or on behalf of the Saab family or companies (in particular Joe or Anthony), on Energy Australia, to reduce the scope of the undergrounding works to be done, from removal of eight poles and erection of five to removal of three and erection of three.
147 In particular, Mr Hale (written submissions in reply, at par 24) asks the court to prefer this interpretation of the evidence:
" On the Council's case, Joseph Saab (and perhaps also Anthony Saab Junior) contacted EnergyAustralia, and Mr Henniker, in March 2004 to reduce the scope of works compared with the 2002 quote. The Scope of Works was limited to what was necessary in relation to the Church Avenue road widening".
148 Mr Galasso sought to distinguish the cases referred to by Mr Hale as they deal with the tortious acts of a company, whereas the present case is "concerned with a breach of the [EPA] Act which is not in its nature or in its characterisation a tort" (T17.3.10, p13, LL5-7). Mr Galasso relies on Wilkie v Blacktown City Council ("Wilkie") [2002] NSWCA 284; (2002) 121 LGERA 444, where it was held (at [36]), that the EPA Act allows the court to make orders against only "persons who are in breach of or who have breached" the Act. It was also held in Wilkie (at [60]) that s 124 of the EPA Act did not contemplate common criminal activities such as "aiding or abetting" or "involvement in the contravention".
149 Mr Galasso also drew the court's attention to ss 168 & 169 of the Protection of Environment Operations Act 1979 (POEO Act) which provide:
" 168 Ancillary offences
A person who:
(a) aids, abets, counsels or procures another person to commit, or
(b) attempts to commit, or
(c) conspires to commit,
an offence under another provision of this Act or the regulations is guilty of an offence against that other provision and is liable, on conviction, to the same penalty applicable to an offence against that other provision.