Bocce Pty Ltd v Woollahra Municipal Council
[2013] NSWLEC 1249
At a glance
Source factsCourt
Land and Environment Court (NSW)
Decision date
2013-12-18
Source
Original judgment source is linked above.
Judgment (4 paragraphs)
Judgment 1Bocce Pty Ltd (Bocce) appealed under s97AA of the Environmental Planning and Assessment Act 1979 (the Act) against the deemed, and subsequent actual, refusal by the respondent Council of an application made under s 96AA of the Act to modify development consent DA706/2010 relating to a residential dwelling at 12 Olola Avenue Vaucluse (the site). 2Development consent DA706/2010 approved the demolition of the existing dwelling and construction of a new residential dwelling at the site. That consent was granted on 5 August 2011 by the Court, in accordance with an agreement reached by the parties under s 34(3) of the Land and Environment Court Act 1979 in proceedings 10355 of 2011. 3Modification Application DA706/2010/1 was made on or about 30 April 2013, after construction work had commenced on the site. The application was stated to be for "internal and external alterations and additions to an approved dwelling house development, including relocation of approved garage, raising of floor levels, provision of undercroft landscape area + external works". On 16 July 2013 Bocce commenced these Class 1 proceedings. On 16 July 2013 the Council refused the application. 4Other proceedings relating to the construction work presently being undertaken on the site are an appeal against an Order issued on 15 May 2013 under s 121B of the Act, which was finalised in consent orders on 9 August 2013, and an appeal against the deemed refusal of an application under s 149B of the Act for a building certificate. The appeal under s 149F of the Act in proceedings 10571 of 2013 (the Building Certificate appeal) is adjourned pending resolution of this appeal. 5The reasons which follow should be read in conjunction with the reasons in Bocce Pty Ltd v Woollahra Municipal Council (No 2) [2013] NSWLEC 1169. In those earlier reasons I outlined the background to the three appeals, and considered the evidence relevant to the issues arising in this appeal as identified in the Council's Statement of Facts and Contentions. At [13] I summarised the issues in the following terms: 13.The Council's position as submitted in the hearing is that the excess in the building size, bulk, scale and presentation of the development as modified is the main issue; then the exceedence in floor space ratio (FSR) and setbacks and the increased height (acknowledging the building is still within the height limit), and then the architectural design, are such that the development as modified is inappropriate for the site. The Council does not consider that of itself the impact of the proposal on the heritage item at 11 Olola Avenue would be such as to warrant refusal of the application, however it is an element in considering the excessive bulk and scale of the development. 6At [14]-[23] I outlined the relevant planning controls provided in the Woollahra Local Environmental Plan 1995 (the LEP) and the Woollahra Residential Development Control Plan (the DCP). At [24]-[26] I outlined the evidence provided at the hearing on 8 and 9 August, including the expert evidence on engineering, planning and heritage issues, and objections made on behalf of the owners of the two adjoining properties, No 11 Olola Avenue to the west (which was listed under the LEP as a local heritage item on 14 June 2013) and No 13 Olola Avenue, which is on the other side of Macarthur Place, a pedestrian walkway incorporating stairs on the eastern boundary of the site. 7In the earlier reasons I made findings in relation to the impact on Macarthur Place, impacts on the setting of the heritage item at No 11 Olola Avenue, and in relation to the height, bulk, scale and presentation of the building and garage. The two aspects of the modification application which I identified in those reasons as being of particular concern related to the upper level of the dwelling, and the relocation of the garage. My conclusions on those two aspects of the modifications proposed were as follows: ... 53 Having regard to the lack of articulation, the increased FSR and bulk, and the privacy impacts of the extension of the upper bedroom level, I am not persuaded that that part of the modification application relating to the balcony on that level should be approved. It would be appropriate to delete all that part of the front balcony and planter area shown heavier pink on drawing A.05 (rev 10), and reduce the height of the walls forward of the northern wall of the master bedroom to a maximum height of 1m above balcony level. The roof should be stepped back consistent with the reduction in the balcony, and would require a column for support. ... 57 The Council submitted that the height of the garage roof should be reduced to ameliorate the impact of the relocation of the garage. There was some discussion between Mr Fotis and Mr Karavanas as to whether the garage could be reduced in height or depth, however while Mr Karavanas agreed that any reduction in height of the garage roof could assist in reducing perceived bulk, he considered that the requirement for adequate headroom and length in the garage, and the need to retain the internal steps up to the house, would limit any possible reduction in height or depth of the garage. Based on Mr Karavanas' evidence it would seem unlikely that any reduction in height or depth sufficient to address the impacts on streetscape of the relocated garage would be feasible or practicable. In those circumstances, and given that the circumstances specified in C4.13.4 of the DCP are not met, and given the impacts on the streetscape resulting from the bulk and location of the garage, I am not persuaded that that part of the modification application relating to relocation of the garage should be approved. That would have the consequence that the garage is incorporated within the building envelope as originally approved, and the further consequence that the proposed art studio on the basement level should not be approved. In fairness to Bocce, however, which submitted that it should have the opportunity to consider whether the garage roof could be lowered if that were the outcome, it is appropriate to provide an opportunity for Bocce to consider whether it would be feasible to reduce the height and length of the garage so as to overcome the adverse impact on streetscape. 8At [61]-[62] I concluded: 61 I am not satisfied that the modifications relating to the location of the garage, and the building articulation and front balconies, should be approved. Those modifications, and the resulting bulk and scale and presentation of the building, are not consistent with objective 2(2)(k)(iii) of the LEP, the objectives of the precinct controls and general controls in DCP, and the DCP performance criteria describing ways in which those objectives can be met. The departures from the applicable performance criteria result in a development that is not consistent with objective (a) of Residential A zone; and consistency with the LEP and zone objectives is a requirement under cl 8(5) of the LEP before any modifications can be approved. 62 Consideration needs to be given, as discussed in [57] above, to whether reduction in height or depth of the garage is feasible or whether that part of the modification application seeking approval for its relocation forward of the building should be refused. The plan relating to the upper level on the eastern side needs to be amended as outlined in paragraph [53]. 9Bocce availed itself of the opportunity to consider the matters raised in the earlier reasons. On 31 October 2013 Bocce was granted leave to re-open the proceedings to provide further engineering and planning evidence, and the matter was listed for further hearing on 18 December 2013. On 13 December 2013 the parties advised the Court that they had received joint reports from the planners and engineers which were in agreement as to certain modifications to the proposal that the experts considered are responsive to the earlier judgment, and the relevant controls, and would allow for final order to be made in the proceedings, and that Bocce had served the Council with amended plans reflective of the experts' agreed amendments. The parties advised that as a consequence of those amendments the Council was agreeable to the matter now proceeding by way of Consent Orders. 10At the request of the parties the matter was listed for mention on 16 December 2013. The parties clarified their position to be that they had reached agreement based on the experts' opinions, however were not seeking consent orders. At the hearing on 18 December 2013 the parties tendered the additional expert reports and the amended plans and made submissions. 11The plans for which Bocce now seeks approval are exhibit S. In summary, the amendments made to the plans that were considered in the earlier reasons (exhibit D) include the following changes to the design of the dwelling: