BlueSky Property Builders Australia Pty Ltd v Dey
[2023] NSWCATAP 153
At a glance
Source factsCourt
NCAT Appeal Panel
Decision date
2023-04-04
Source
Original judgment source is linked above.
Judgment (12 paragraphs)
Introduction
- This is an appeal against a decision of the Consumer and Commercial Division of the Tribunal by which the appellant (the builder) was ordered to pay the respondent (the homeowner) the sum of $218,441.78 in respect of defective building work carried out by the builder on the homeowner's property. The builder and the homeowner had entered into a contract on 8 June 2020 for the renovation of and additions to the homeowner's existing home at Rooty Hill in New South Wales.
- The amount the builder was ordered to pay included: 1. $27,692 for the rebuilding of the balcony and columns (decision at [95]), to which the Tribunal determined should be added margin (30%), preliminaries (ancillaries) (5%) contingencies (10%) and GST (10%) (decision at ([191] - [193]). Those additions brought the amount awarded in respect of the balcony and columns to $45,737.49. 2. $93,789 plus GST ($103,167.90) for the remediation of the "rear alfresco slab" ([109] and [196]). 3. $14,150 plus margin, preliminaries, contingencies and GST ([144] and [191]), amounting in total to $23,370.85, for the rectification of the falls to floor wastes in the bathroom, ensuite and first floor bathroom. 4. Accommodation and relocation costs of $14,620 (decision at [180] - [188]).
- The Tribunal considered the provisions of s 48MA of the Home Building Act 1989 (NSW) which provides: 48MA Rectification of defective work is preferred outcome in proceedings A court or tribunal determining a building claim involving an allegation of defective residential building work or specialist work by a party to the proceedings (the responsible party) is to have regard to the principle that rectification of the defective work by the responsible party is the preferred outcome.
- The Tribunal concluded that it should not make an order requiring the builder to carry out the required rectification work. The Tribunal's substantial reasons for that conclusion were set out in the decision at [203] as follows: "203 The Tribunal finds that in these proceedings, it is not appropriate to give effect to the preferred outcome provided for in s. 48MA of the Act. The Tribunal is troubled by the fact that as the evidence showed, during an inspection of the alfresco slab in July 2020, the private certifier had expressly revealed during the certification process that that work had been done by Bluesky in breach of the contract. The certifier had plainly stated that the pods relating to the slab were at the wrong height, that there was no step down as required by the contract and that these matters had to be addressed. The evidence suggests that Bluesky paid no heed to what the certifier had stated but went ahead with work which it must then have appreciated was in breach of contract. Extensive rectification work will now have to be completed to rectify the defects arising in regards to the alfresco area constructed by Bluesky. Because of this issue, the Tribunal does not have confidence that if it makes a work order, that Bluesky will complete the rectification works completely and in accordance with the contract's requirements and the terms of any work order."