Birdon Contracting Pty Ltd v Hawkesbury City Council
[2009] NSWLEC 91
At a glance
Source factsCourt
Land and Environment Court (NSW)
Decision date
2009-07-01
Before
Lloyd J
Source
Original judgment source is linked above.
Judgment (45 paragraphs)
The application of the Limitation Act 1969 16 The order requires the payment of $48,472.06 representing the shortfall of all payments made since the grant of the development consent. Mr Webster submits that the demand is barred by s 14(1) and s 15 of the Limitation Act. 17 Section 14(1) of the Limitation Act relevantly states: "(1) An action on any of the following causes of action is not maintainable if brought after the expiration of a limitation period of six years running from the date on which the cause of action first accrues to the plaintiff or to a person through whom the plaintiff claims: ... (d) a cause of action to recover money recoverable by virtue of an enactment, other than a penalty or forfeiture or sum by way of penalty or forfeiture." 18 Section 15 of the Act states: "An action on a cause of action for an account founded on a liability at law to account is not maintainable in respect of any matter if brought after the expiration of a limitation period of six years running from the date on which the matter arises."
"Action" includes any proceeding in a court: s 11. 19 As I understand Mr Webster's submission, it is that the whole of the order is barred because it demands the payment of money beyond the six years limitation period. His alternative submission is that the Council cannot recover beyond the six years limitation period. The notice of intention to issue the order was sent to Birdon Contracting on 25 June 2008, so that on the alternative basis the amount of arrears can be recovered back to 2002. It is agreed that this is a figure of $45,040.23. 20 The submission that the claim is statute barred was not further developed. Mr S N Griffiths, appearing for the council, submits only that the Limitation Act does not apply to administrative law, citing Daemar v Industrial Commission of New South Wales [No. 2] (1990) 22 NSWLR 178. A reading of that case discloses, however, that it has nothing to do with the Limitation Act. In that case the claimant sought prerogative relief against the Industrial Commission. Kirby P (Clarke and Meagher JJA concurring) held (at 186) that there is no time limit for the commencement of proceedings for relief prerogative in nature, although delay will be taken into consideration by the court when determining whether to provide relief. Kirby P noted that there is no fixed time for the commencement of such proceedings. Unlike Daemar, however, the Limitation Act would, if it applies, fix a time for the commencement of proceedings. Again, unlike Daemar, the present case is not an application for prerogative relief. 21 The real question is whether the two provisions of the Limitation Act nominated by Mr Webster apply to an order of this nature.