NSWNSWDC
Betta Build Group Pty Ltd v El Baba
[2020] NSWDC 272
District Court of NSW|2020-06-04
View original sourceAt a glance
Source factsCourt
District Court of NSW
Decision date
2020-06-04
Source
Original judgment source is linked above.
Judgment (10 paragraphs)
[1]
BACKGROUND
- These reasons concern an application for costs by the defendant/cross-claimant ('the Owner') following proceedings brought against the plaintiff ('the Builder') in respect to construction works over a residential property at Bankstown undertaken in the period from October 2015 to February 2017. Proceedings were originally commenced in the New South Wales Civil and Administrative Tribunal ('NCAT') but were transferred to this Court.
- The Owner was substantially successful in the proceeding, resisting claims brought by the Builder and establishing his own claims for an overpayment made to the Builder (for the sum of $29,961.36) and an additional claim for the cost of defective works [1] . Following a referral of the issue of the costs of rectification, the Owner obtained a monetary judgment in the sum of $227,941.21 in relation to the latter claim. Orders were also made for pre-judgment interest on each claim [2] .
- The Owner now seeks a partial order for indemnity costs of the proceeding (embracing also the costs of the proceeding when it was before the NCAT) on various alternative bases. They are that the Owner achieved a no less favourable ultimate result than that which he offered to the Builder in (a) a Calderbank offer made on 3 July 2018 (the 'First Offer'); or (b) an offer of compromise served on 5 February 2019 (the 'Second Offer'); or (c) a Calderbank offer and offer of compromise served on 29 April 2019 (the 'Third Offer').
- The Builder opposes the application for a special costs order up to 5 February 2019 when the Second Offer was made. The Builder contends that it should pay the Owner's costs of the proceeding on the ordinary basis up to and including 5 February 2019 and thereafter on an indemnity basis.
[2]