Belongil Progress Association Inc v Byron Shire Council & Anor
[2000] NSWLEC 118
At a glance
Source factsCourt
Land and Environment Court (NSW)
Decision date
2000-06-15
Before
Cowdroy J, Mr J, Mr P
Source
Original judgment source is linked above.
Judgment (17 paragraphs)
- The applicant's claim is predicated upon the fact that it was vindicated in its challenges to the LEP. It submits that in consequence it should be entitled to its costs pursuant to the costs principles as discussed in Latoudis v Casey (1990) 170 CLR 534.
- The first respondent submits that the applicant's success in the proceedings resulted only from an issue raised during the Court proceedings. It says that at the commencement of the proceedings the applicant abandoned the three original issues of its challenge. The remaining challenges to the validity of the LEP were then distilled into three issues.
- The first issue ("the first issue") raised the question of whether there was a need for the first respondent to carry out an environmental study. On this issue the Court held that the provision of an environmental study was not mandatory provided the Minister's attention was drawn to the absence of such a study in the report prepared pursuant to s 69 of the Environmental Planning and Assessment Act 1979 ("the EP&A Act"), ("the s 69 report"). However since the s 69 report contained no notification to the Minister of the absence of such study the factual basis for the exercise of the Minister's discretion to make the LEP was flawed. The applicant succeeded in establishing that the Minister's attention had not been drawn to the absence of the environmental study.