The plaintiff was given 28 days within which to carry out that work.
11 By facsimile dated 25 March 2008 Messrs Colin Biggers and Paisley, the solicitors for the plaintiff, wrote to Messrs Minter Ellison, the solicitors for the defendants, disputing the validity of the direction purportedly made under s 61 of the SERM Act. In that letter the plaintiff's solicitors disputed that "a danger area" existed. They submitted that because of the stabilisation work performed in relation to the wall, there no longer existed any danger to persons or animals as specified by the Act. They disputed that reasonable grounds existed for issuing the direction and they asserted that the works required to be performed by the plaintiff pursuant to the direction were not authorised by the Act.
12 On 26 March 2008 Messrs Minter Ellison responded on behalf of the defendants and disputed the matters raised by the plaintiff's solicitors.
13 The plaintiff's solicitors responded to that letter on the same day and said:
"[Our client]
1. Considers that the methodology for the works proposed by the purported direction may not now be possible. Our client has already constructed a berm against the face of the wall to stabilise the same with a view to allowing the commencement of testing of the anchors. However, due to water continuing to ingress through the damaged wall, the bottom of the berm is water charged such that the integrity of the berm is being considerably compromised. As our client understands, the objective of paragraph (a) and (c) of the works proposed by the purported direction is not only to stabilise the wall, but to provide a safe working platform from which the testing of the anchors, the installation of any additional anchors, and the performance of any other work for a permanent stabilisation of the wall can be undertaken. Given the current ongoing problem with water ingress and its effect upon the integrity of the berm, it would now appear that the construction of a berm will not allow for a safe working platform and accordingly, the safe performance of the aforementioned activities;
2. Considers that the works proposed by the purported direction (assuming (which is not now conceded) such works can be performed safely - see above) are substantial and reiterates that the period by which the works proposed by the purported direction are required to be carried out (28 days) is most unrealistic. To this end, our client points to the fact that there are some three rows of anchors that need to be tested, and accordingly there are possibly three rows of additional anchors that may be required. Each row of anchors is located at different heights in the wall. It is not possible to test all three rows at the same time. Testing can only occur consecutively. In summary, the top (first) row of anchors must first be tested, the results of the same analysed, and additional anchors designed and installed and then one must "dig out" the berm down to the next row of anchors (being the middle (second) row of anchors). The same goes before one can move from the middle (second) row of anchors down to the bottom (third) row of anchors. Accordingly, having regard to the above, the works proposed by the purported direction will be very time consuming.
3. Request that you clarify what is precisely meant by the words "the New South Wales Police Force would pay so that the work could commence". Does this mean that your client would pay for all the costs of the works (likely to run into several millions of dollars but then seek to recover the same from our client) and if not, which costs and how much? Please clarify and
4. Reiterates, for the avoidance of any doubt, that it is ready and willing to co-operate and do all reasonable things to resolve the situation which has arisen following the water main burst on Botany Road. Our client is not intending to be obstructive by the aforementioned paragraphs, but simply wishes to convey that further thought needs to be given to the resolution of the situation. We note your client is prepared to discuss with our client how to expedite the work. Please advise when your client's representatives are available to meet in this regard."
14 The defendants' solicitors responded on 27 March 2008 as follows:
"In view of the emergency situation that remains at Botany Road and the issues raised by your client, NSWPF has agreed to the following in order to expedite the starting of the work:
1. The work and time limit in the direction may need to be revised from time to time. If considered necessary by Assistant Commissioner Byrne (AC), a revised Direction will be issued.
2. BBB Constructions (BBB) will do the work as directed from time to time by the AC. In formulating directions, the AC may consult with but not be bound to accept in whole or in part the views of BBB. BBB will provide its views within any time limit set by the AC.
3. The Commissioner of Police will pay the reasonable costs of third parties retained by BBB to do the work, such costs to be approved in writing by the AC. The Commissioner of Police will do so on the clear understanding, and with BBB's acknowledgment of the facts, that the Commissioner of Police will recover such costs, and any NSWPF costs, under s 61 of the SERM Act on the basis that they are costs which should be borne by BBB as the owner and can be recovered from the owner under that section.
The Department of Commerce will act as the agent of NSWPF to assist in directing and supervising the work.
Please note that while the emergency remains, and in view of your client's delay in complying with the Direction and starting the work required to be undertaken to render the danger area safe, NSWPF is considering other options including issuing a Direction to an independent third party to undertake the work."
15 The plaintiff's solicitors responded on 27 March. While once again challenging the defendants' right to issue the direction, they agreed that the plaintiff was ready and willing to co-operate with the NSWPF and denied that it was being obstructive. They pointed out that even before the issue of the purported direction the plaintiff had already undertaken at its own cost the work referred to in paragraph (a) of the purported direction.
16 Thereafter attempts were made in correspondence between the two firms of solicitors to achieve an agreement whereby the plaintiff would perform work as required by the first defendant. Those negotiations did not achieve agreement. The final position reached is summarised in a report from David Wilkins, the Engineering Services Functional Area Co-ordinator for the Department of Commerce to the Department of Premier and Cabinet dated 4 April 2008.
"The position at the conclusion of negotiations is as follows:
1. The Developer has agreed at a high level to the proposed broad scope of work covered by the order in my letter, dated 3.4.08. However the Developer was interpreting the scope as covering some damage rectification works and indirect costs such as legal fees and prolongation costs.
Our position was that the reimbursement of costs is more narrowly defined to that required only to the direct costs needed to stabilise the wall to make safe and not to fully rectify the damage to the wall or any consequential matters. The Developer was also concerned at how the fair and reasonable test would be applied to costs reimbursement. This was not considered a major sticking point to an agreement.
2. The Developer was mobilised at present to start work however would be de-establishing this week as there was no more building construction work.
3. The Developer stated that they do not know at this stage whether either of its two insurers will cover any costs in relation to this incident.
They claim that the Section 61 Order has complicated their insurance recovery ie which insurer's cover applies to compliance with a Section 61 Order, which of their two insurers is liable, and whether undertaking the Order work will prejudice their cover. They are trying to get a resolution but the insurers were not being co-operative.
4. The Developer is not prepared to commence work without either (a) agreement from its own insurers to cover costs that Police may seek to recover from them at a later date; or (b) Police agreeing to recover costs from it only to the extent of their insurance cover. They state that otherwise they would be in a position to be made bankrupt.
The time to get their insurers' agreement is indeterminate.
The Developer maintains that Police should agree to recover costs from the party found liable for causing the incident. However the incident may be settled out of court on agreement with no party liable. The Developer has also offered to give Police subrogation rights to recover costs directly from its insurers.
The Developer concluded by stating they still believe the use of s 61 is not valid in this case; and were still strongly of the opinion that Sydney Water's pipeline break was the cause of the incident and that they were being expected to carry the financial implications for both parties while the cause of liability takes years to be determined through the courts. Sydney Water is disputing this as the cause of the incident. The alternate argument is if the wall had not been constructed there and in that manner, there would be no issue with a water main break.
Way Forward
1. Engineering.
With the Developer unwilling or incapable of undertaking stabilising work, the only engineering option to "make safe" in a timely manner appears to be utilising a third party contractor to undertake works necessary to temporarily stabilise the wall, reopen the surrounding area to normal use. This would probably be initially limited to berm construction and some anchor restressing and replacement, and not the complete scope formerly offered to the Developer. By this time the Developer's insurance issues may be resolved.
For this we would need:
· Access to all the plans, calculations and other technical information from the Developer and subcontractors and consultants.
· Access to the whole of the site and cessation of the Developer's work.
This solution will take longer than if the Developer commenced now and undertakes the work, probably cost more, and also exposes government to other potential risks and liabilities …"
17 On 4 April the first defendant issued a notice to the plaintiff purporting to be made pursuant to s 61 of the SERM Act. That notice terminated the direction previously given to the plaintiff. On the same day the first defendant issued a further direction to the second defendant purporting to be made pursuant to s 61 of the SERM Act directing the second defendant to carry out specified works on the site. The direction designated the site as a danger area and stated that the first defendant was satisfied that "for the purpose of protecting persons or animals from injury or death or protecting property threatened by an actual or imminent emergency there are reasonable grounds for making a direction under section 61(1)(c) of the Act".
18 By email dated 7 April 2008 the solicitors for the plaintiff objected to the notice and direction of 4 April. As before they asserted that the notice and direction were beyond power. The substance of the factual position of the plaintiff is conveniently set out in paragraph 2 of that email as follows:
"2. Our client has continued to engage its insurer and their assessor to commence the necessary rectification works as soon as practical and then proceed with those works in a timeframe and sequence that our client and the insurer will agree on.
Your client must appreciate that, given that it has not been established that our client was in any way responsible for the movement of the secant retaining wall, and the parties that were circumstantially responsible have refused to accept responsibility for the problem, it falls upon our client to look to its insurers to help it to restore the work with the minimum of cost to our client.
The re-opening of Botany Road is only one consideration of this timing and sequencing. Our client remains most concerned that NSWPF, and its agent, Department of Commerce, continue to underestimate the complex series of issues that need addressing.
More importantly, the proposal to date for NSWPF to offer to fund certain work under the auspices of the SERM Act has its own problems, eg:
(i) The Act does not appear to respond to the circumstances as they now exist (see above).
(ii) The work directed was beyond that which was appropriate to direct under section 61(1)(c) of the SERM Act (as above).
(iii) The NSWPF's continued insistence that it maintained the "right" to recover from our client any costs that it might incur in the restoration work raises a serious question as to whether, if our client were to later receive such a demand, its insurance would respond to that claim?
As we had informed you, our client was attempting to work through those issues with its insurers at the time that NSWPF has purported to issue the further directions on Friday afternoon."
19 Notice was given by the solicitors for the defendants that the contractors retained by the second defendant would attend the site at 3pm on 7 April. The solicitors for the plaintiff responded to the effect that the plaintiff would not oppose entry by the Police Service but would not agree to the second defendant or its contractors entering the site. Entry to those contractors was in fact refused by the plaintiff on the afternoon of 7 April.
20 On the morning of 8 April in purported reliance upon s 60D of the SERM Act, Police officers using bolt cutters gained access to the site and allowed representatives of the second defendant and its contractors onto the site and directed that the plaintiff and its contractors depart from the site. The plaintiff and its contractors complied with those directions.
21 That was the situation as it existed when the matter came before the court at 11.15am on 8 April.