(b) Submitted to Council a contamination report, satisfactory to Council, within 90 days of the L&EC Order, (as required by paragraph 2 of the Remediation Program), or at all;
(c) Removed all unauthorised fill within 12 months of the L&EC Order, (as required by paragraph 7 of the Remediation Program), or at all;
(d) Submitted to Council a landscape plan, satisfactory to Council, within 90 days of the L&EC Order, (as required by paragraph 11 of the Remediation Program), or at all:
(e) Completed the landscape works set out in the landscape plan within 12 months, (as required by paragraph 7(c) of the Remediation Program), or at all.
7 On the return date of the Notice of Motion it had not been served and accordingly was stood over to 12 September 2002, when directions were made. The matter was adjourned on six further occasions until 21 February 2003 when it was set down for hearing on 1 and 2 July 2003. On the second day of the hearing the matter was adjourned to 23 July 2003 to allow relevant experts to confer, and if practicable, to agree on the appropriate method of remediation of the site. By that time it had become clear to both parties that the remediation program stipulated by Order 3 made on 13 March 2000 could not, as a matter of practicality, be implemented.
8 A joint expert report was filed on 17 July 2003 and was before the Court on 23 July 2003. The matter was again stood over to 20 August 2003 to facilitate a process where both parties were to formulate a form of appropriate orders to be made, together with a statement of reasons for disagreement in any respect. That process was not complete when the matter came before the Court again on 28 August 2003. Eventually more specific orders were made on 2 September 2003 to enable the preparation of an appropriate specification and schedule of work for the remediation of the property.
9 Various circumstances prevented completion of the work, including a lack of capacity to finance the project, until by consent on 11 December 2003 the remediation works were identified and the first and second respondents directed to carry out the remediation works by 31 March 2004.
10 On 29 July 2004 the Court was informed that the work had been completed and that the only outstanding issue that remained was a dispute in relation to costs. The hearing in relation to costs took place on 7 October 2004 following the formal dismissal of the applicant's Notice of Motion dated 1 August 2002.
11 There is no evidence that the first and second respondents either placed or consented to the placing of fill on the subject land by the third respondent or anybody else. The fourth respondent is the owner of the adjoining land over which the material was transported. A plea of guilty to the charge of contempt has never been entered on behalf of the first or second respondent. It is agreed that the first and second respondents have caused the remediation of the land to be completed to the satisfaction of the Council in accordance with the Report made by the experts following the joint conference on 15 July 2003.
12 Initially the respondents contended that each party should pay its own costs. However, in light of the Council's position they now seek an order that the Council pays their costs in respect of the two day hearing of 1 and 2 July 2003 and costs incidental to the applicants' Notice of Motion seeking an order for costs.