Bauen Constructions Pty Ltd v Sky General Services Pty Ltd & Anor
[2012] NSWSC 1123
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2012-09-13
Before
Sackar J
Source
Original judgment source is linked above.
Judgment (11 paragraphs)
Proceedings 1The plaintiff Bauen Constructions Pty Ltd, (Bauen) seeks relief on various bases in relation to two adjudication determinations, each of which raises identical issues for consideration. 2Bauen seeks a declaration that each of the adjudication determinations is void or alternatively an order that they be quashed. 3Briefly there are three issues. The first is whether Bauen is entitled to relief in circumstances where the payment claim underlying it was served outside the twelve month period prescribed by section 13(4)(b) of the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Act). 4The second issue relates to the first and it is whether the adjudicator failed, bona fide to address the requirements of section 22(2)(a) by misconstruing section 13(4)(b) of the Act. 5The third issue is whether Bauen was denied natural justice in circumstances where the adjudicator failed to consider Bauen's adjudication response. 6The defendant Sky General Services Pty Ltd, (Sky General) denies that the plaintiff is entitled to any of the relief sought.
The Legislation 7Section 13 relevantly of the Act is in the following terms: (4) A payment claim may be served only within: .... (b) the period of 12 months after the construction work to which the claim relates was last carried out (or the related goods and services to which the claim relates were last supplied); whichever is the later. 8Section 17 of the Act relevantly states: Adjudication applications (1) A claimant may apply for adjudication of a payment claim (an adjudication application) if: (a) the respondent provides a payment schedule under Division 1 but: (i) the scheduled amount indicated in the payment schedule is less than the claimed amount indicated in the payment claim, or (ii) the respondent fails to pay the whole or any part of the scheduled amount to the claimant by the due date for payment of the amount, or (b) the respondent fails to provide a payment schedule to the claimant under Division 1 and fails to pay the whole or any part of the claimed amount by the due date for payment of the amount. (2) an adjudication application to which subsection (1)(b) applies cannot be made unless: (a) the claimant has notified the respondent, within the period of 20 business days immediately following the due date for payment, of the claimant's intention to apply for adjudication of the payment claim, and (b) the respondent has been given an opportunity to provide a payment schedule to the claimant within 5 business days after receiving the claimant's notice. (3) an adjudication application: (a) must be in writing, and (b) must be made to an authorised nominating authority chosen by the claimant, and ... 9Section 20 of the Act relevantly states: (1) Subject to subsection (2A), the respondent may lodge with the adjudicator a response to the claimant's adjudication application (the adjudication response) at any time within: (a) 5 business days after receiving a copy of the application, or (b) 2 business days after receiving notice of an adjudicator's acceptance of the application, whichever time expires later. (2) the adjudication response: (a) must be in writing, and (b) must identify the adjudication application to which it relates, and (c) may contain such submissions relevant to the response as the respondent chooses to include. (2A) The respondent may lodge an adjudication response only if the respondent has provided a payment schedule to the claimant within the time specified in section 14(4) or 17(2)(b). 10Section 22 relevantly provides: 22 Adjudicator's determination (1) An adjudicator is to determine: (a) the amount of the progress payment (if any) to be paid by the respondent to the claimant (the adjudicated amount), and (b) the date on which any such amount became or becomes payable; and (c) the rate of interest payable on any such amount. (2) In determining an adjudication application the adjudicator is to consider the following matters only: (a) the provisions of this act,... 11There are a number of definitions also relevant. Section 4 defines a construction contract as follows: construction contract means a contract or other arrangement under which one party undertakes to carry out construction work, or to supply related goods and services, for another party. 12The term "construction work" is defined in section 5, relevantly as follows: (f) the painting or decorating of the internal or external surfaces of any building, structure or works,... 13The term "related goods and services" is defined relevantly in section 6, as follows: (1) In this Act, related goods and services, in relation to construction work, means any of the following goods and services: (a) goods of the following kind: (i) materials and components to form part of any building, structure or work arising from construction work, (ii) plant or materials (whether supplied by sale, hire or otherwise) for use in connection with the carrying out of construction work, (b) services of the following kind: (i) the provision of labour to carry out construction work, (ii) architectural, design, surveying or quantity surveying services in relation to construction work, (iii) building, engineering, interior or exterior decoration or landscape advisory services in relation to construction work, (c) goods and services of a kind prescribed by the regulations for the purposes of this subsection.