The Finding on Good Faith
41 As indicated above, in the reasoning of Gzell J leading up to his conclusion on nuisance in paragraph [56], as quoted, the relevant conduct constituting the nuisance encompassed both the construction and operation of the drainage system and the Council's conduct in permitting the urbanisation process.
42 There was no evidence to suggest that the original construction of the drainage system and the approvals leading to urbanisation, were in any way affected by conduct which could be said to be other than in "good faith." The only aspect of his Honour's findings on nuisance that, on the evidence, could do so, was the Council's conduct in continuing to operate the drainage system as its inadequacies became increasingly clear, without constructing works that would ameliorate the risk of flooding to the Respondent's land. However, his Honour's judgment does not refer to the failure by the Council to take remedial action in the form of construction works to the unlined channel over any period of time prior to the commencement of proceedings.
43 His Honour referred to correspondence in 1989 in which a representative of the Respondent drew the Council's attention to the problem, indicating that the Respondent was prepared to contribute to the cost of the requisite works. At that stage officers of the Council estimated the costs of a concrete channel at about $1.6 million and of a reinforced concrete box culvert at approximately $2.7 million. The Respondent was informed that this work was not listed in the Council's forward works program. However, his Honour did not rely on this first communication, shortly after the Respondent acquired the land, in his reasoning on good faith. Nor did he rely on the period of about nine years that elapsed thereafter.
44 His Honour's consideration of the issue of good faith commenced with events in 1998. His Honour noted that a site meeting was held on the land in July 1998. Mr Morrison, the Manager of Roads and Infrastructure of Bankstown Council, attended this meeting. Mr Morrison thereafter requested consultants to investigate a number of matters relating to the channel including options for improvement. The consultants prepared a report in September 1998 which, inter-alia, recommended further study of options to reduce inundation. Thereafter the following steps occurred:
· In February 1999 the Respondent wrote requiring the defendant to construct a drainage channel, so that its property would not be affected in the future.
· Mr Morrison, upon receipt of the above letter, recorded his undertaking to the Respondent that he would arrange an investigation of possible solutions with a view to including the project in the works program, subject to funding.
· The Respondent's letter was acknowledged. That acknowledgement included a statement that urgent advice had been sought from the defendant's engineering staff and that when that was given, the Respondent would be informed.
· In March 1999 the Respondent complained that he had not received a reply to his letter and gave notice that legal action would be taken. There was no response to this letter.
· These proceedings were commenced in May 1999
· The defendant's consultants produced a memorandum in May 1999 which concluded that the property probably would be flooded at quite frequent intervals and recommended further investigation.
· In November 1999, the consultants produced a preliminary report which recommended the acquisition of the plaintiff's land with a view to demolishing the buildings, and the rezoning and redevelopment of a portion of site as residential property. The object oof the plan was to produce a cost neutral solution by the sale of the residential portion of the land. Subsequent investigation by the Council's property manager indicated a higher cost of acquisition and this option was abandoned.
45 His Honour found:
"[36] No further steps have been taken by the defendant to alleviate the problem. In particular, no proposal has been included in the defendant's forward works program. Mr Morrison said that nothing had been done pending the resolution of these proceedings."
46 Gzell J found against the Appellant on the issue of good faith in the following passage:
"[68] In my view, the defendant did not act in good faith in the instant circumstances. Mr Morrison was of the view that there was a potential problem. He initiated a detailed investigation. A solution was the acquisition of the land and its use, partially as a detention basin and partially for on-sale of residential lots. Further investigation led to the rejection of that plan because the cost of acquisition of the land would not make the proposal cost neutral. Notwithstanding recognition of a continuing problem, the defendant did nothing thereafter. It made no prospective plans but relied solely on the argument that these proceedings having been commenced, further investigation should await their outcome.
[69] Having recognised the problem, the defendant was, in my view, obliged to take reasonable steps to deal with it. Had the defendant continued its investigations, arrived at an alternative solution and introduced it to its rolling works programme so that its priority might be established as against other works, a different result may have eventuated. Its abandonment of any further investigation pending the outcome of these proceedings put it, in my view, outside the protection of the Local Government Act 1993, s 733."
47 The centrality of the conduct after May 1999 is reiterated in that part of his Honour's reasons dealing with discretion:
"[85] Finally, the defendant submitted that in the exercise of my discretion, I should refuse to grant injunctive relief because the plaintiff purchased the land in its flood-prone state with knowledge.
[86] While this is a matter to be taken into account in the exercise of my discretion, I am of the view that it is far outweighed by the abandonment of investigation of further proposals for the elimination or amelioration of the flooding problem by the defendant."
48 His Honour's conclusion on the absence of good faith is expressly based only on the Council's conduct, or rather inaction, over the period commencing in about February 1999 to the date of the hearing before his Honour. In my opinion, it was not open to his Honour to find that the Council's conduct over this period was such that the Council could not rely on s 733 of the Act.
49 The first reason for this conclusion is that the issue about the Council's inaction during this period was not properly examined at the trial. The relevant Council officer had been cross-examined by counsel for Alamdo to the effect that nothing had been done after the February 2000 report. In re-examination he was asked why. An objection from counsel for Alamdo, that this question did not arise from the cross-examination, was rejected. The Council officer answered: "Primarily because of these proceedings".
50 There was no exploration of any of the other facts and matters, the relevance of which is suggested by the word "primarily". Nor was there any further consideration of the link between the proceedings and the ordering of Council priorities. The fact that this matter arose in a question in re-examination, which was objected to, indicates that it formed no part of the Respondent's case. Although the Council has the onus of proving good faith, the limited evidence in this respect provided an inadequate basis for a finding that the Council's conduct was not in good faith.
51 Secondly, the terminology of s733 is that a council "does not incur any liability in respect of… anything done or omitted to be done in good faith by the council". Although the words "in respect of" do not require a precise causal relationship, nevertheless, s733 requires the basis of liability of the Council in nuisance to be the focus of attention. As the extract from Suatu quoted above indicates, in an exemption provision words such as "in respect of" do not receive a liberal interpretation.
52 Mr Ireland submitted that there was no connection between the acts found to constitute a nuisance and the abandonment of investigations about remedial work in 1999. This submission should be accepted.
53 Liability did not attach to the Council for its conduct in the nature of non-feasance over the period from early 1999 until the date of the hearing. The pleadings asserted liability on the basis of Council decision-making which led to the progressive urbanisation of the region and its construction and operation of the stormwater drainage system leading to the discharge from the two stormwater pipes into the channel. This is a much broader basis of liability than that to which his Honour referred in his findings on good faith.
54 As will presently appear, I do not believe that a good faith standard can be applied to future conduct at all. In any event, in order for his Honour to find that the Council was not entitled to the protection of s733 on the basis of lack of good faith, he had to decide, at the least, that its continued operation of the stormwater drainage system was not in good faith, in the sense that, absent remedial measures, such operation was unreasonable in some way. This was not the approach his Honour took.
55 The Council did not incur liability in nuisance in respect of its failure to investigate remedial works in the period after February 1999. Its conduct during that time period was barely relevant to the issue of good faith that arose under s733, let alone determinative of it