Aztech Science v Atlanta Aerospace
[2005] NSWCA 319
At a glance
Source factsCourt
Court of Appeal (NSW)
Decision date
2005-08-09
Before
Handley JA, Bryson JA, Basten JA, Barrett J
Source
Original judgment source is linked above.
Judgment (45 paragraphs)
Background 46 Atlanta Aerospace was jointly owned by Dr Daevys and a colleague, Mr Michael Burke. Their respective roles in the business of the company are not apparent from the evidence, but it appears that, pursuant to their efforts, the company had acquired or developed a monitoring device known as a sub-aquatic monitor, or colloquially "SAM", which could be used for monitoring water quality. That, and other devices, were the subject of discussion during an unidentified period in 2002 between Dr Daevys and Mr Antonio Azzi, with the intention of Mr Azzi forming a company through which capital could be provided to develop and market the identified devices. A further element in the proposal was that Atlanta Aerospace would contract with the new company to provide the services of Dr Daevys to assist with various aspects of the venture. 47 By 11 November 2002 Mr Azzi, identified as "the promoter", entered into a contract with Atlanta Aerospace and Dr Daevys in terms which foreshadowed the registration of Aztech. Thus recital A in the agreement provided: "A. The Promoter intends to apply to incorporate an Australian proprietary company under the provisions of the Corporations Act 2001 to be named 'Aztech Sciences Pty Ltd' or such similar or other name as may be approved by the Australian Securities and Investment Commission ('the Principal')."
Clauses 1-4 of the agreement read: "1. The Promoter intends to enter into this Agreement on behalf of the Principal before it is registered. 2. If the Principal is not registered or fails to ratify this Agreement within sixty (60) days from the date hereof, this Agreement shall be at an end, and notwithstanding Section 131 of the Corporations Act , neither party shall have any further rights against the other to require performance of this Agreement or to claim damages or costs. 3. If this Agreement ends because of the operation of the preceding provision, the Contractor and the Nominee agree that they do hereby release the Promoter from any liability that he would otherwise be under by law in the absence of this provision. 4. The termination of this Agreement pursuant to Clause 2 shall not affect any rights or remedies of either party against the other for any act event or default occurring prior to the date of termination." 48 Although the agreement was executed by Mr Azzi "for and on behalf of Aztech Sciences Pty Ltd", and by Dr Daevys, in his own right, on 11 November 2002, it was not executed on behalf of Atlanta Aerospace until 19 December 2002. The primary judge held that each of Mr Azzi, Dr Daevys and Atlanta Aerospace were parties to the agreement and that, accordingly, the agreement was not entered into until Atlanta Aerospace executed the agreement on 19 December. His Honour further found, in accordance with the submissions of Aztech, that "the date hereof" in clause 2 of the agreement was not the date on which the contract stated that it was made, namely 11 November 2002, but the date on which the last party executed the agreement, namely 19 December 2002. 49 On the basis that clause 2 of the contract required registration and ratification within 60 days of 19 December 2002, that period expired on 17 February 2003. Aztech, however, was not registered until 20 February 2003. Accordingly, neither registration nor ratification occurred within that agreed period. 50 The fact of registration not being in doubt, the first condition could be satisfied if the Court were satisfied that the 60 day period was waived or extended by three days. The question of ratification, however, involved greater difficulty. Aztech provided no unequivocal evidence that it had ratified the contract nor, if it had, when the ratification occurred. For reasons noted below, the primary judge was satisfied that ratification may have occurred on or shortly prior to 1 April 2003, but was satisfied that that did not constitute timely ratification within the terms of the contract. 51 On 17 March 2003 a meeting was held between officers of the two companies, including the solicitor acting for Aztech. It was clear that, by that date, serious differences of opinion had arisen and that Dr Daevys was asserting that he and Atlanta Aerospace were not bound by the agreement. The representatives of Aztech apparently complained at the meeting that Atlanta Aerospace had been unwilling to disclose details of its intellectual property rights. The reason for such reluctance was expressed to be a concern that there was no binding agreement and hence such disclosure would jeopardise its intellectual property. According to the Aztech letter of the same date, those concerns had been raised "for the first time today". The Aztech letter, written by a representative of the company, Mr Robert Somosi, also asserted: "My principal has always regarded that we have had a binding contract even though some of its terms were waived mutually on your side and on his [sic], these included amounts to be paid and other matters."