Australian Building and Construction Commissioner v Mamudi
[2017] FCA 134
At a glance
Source factsCourt
Federal Court of Australia
Decision date
2017-02-21
Before
Siopis J
Source
Original judgment source is linked above.
Judgment (10 paragraphs)
- Each of the respondents has contravened s 417(1)(a) of the Fair Work Act 2009 (Cth) by reason of engaging in industrial action on 20 February 2015, being a time from the day on which the York Civil Pty Ltd SA & WA Enterprise Agreement 2013-2017 was approved by the Fair Work Commission until its nominal expiry date had passed.
- Each of the respondents is to pay a pecuniary penalty of $1,000.00.
- The pecuniary penalties are to be paid to the Commonwealth. Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
BACKGROUND 1 On 20 February 2015, York Civil Pty Ltd (York Civil) was carrying out work, as a contractor, on a project for the construction of a waste water treatment plant in East Rockingham, Western Australia (the project). The head contractor was TASK JV Pty Limited (TASK JV), being a corporate vehicle for a joint venture between Thiess Pty Ltd and Sinclair Knight Merz Pty Ltd. 2 The work being performed by York Civil on the project included civil works and structural, mechanical and piping work. York Civil was responsible for the construction of the concrete and the below-ground piping of the East Rockingham plant, as well as the structural, mechanical and piping package. York Civil was the main contractor on the project site with a workforce of between 100 to 130 employees. Work on the project site was completed around the end of February 2016. 3 At about 6:00 am on 20 February 2015, a number of union officials from the Construction, Forestry, Mining and Energy Union (CFMEU) and the Australian Manufacturing Workers' Union (AMWU) attended the project site. They addressed the assembled persons who had congregated at the front gate. There were employees of York Civil among the crowd. At the conclusion of the address, the employees voted by a show of hands in favour of leaving work for the day. Prior to the address, a number of union officials were seen distributing a bullying survey to employees, including employees of York Civil, as they arrived at the front gate of the project site. 4 At the conclusion of the address by the union officials, sometime between 6:30 am and 7:30 am, the employees who were at the meeting, left the project site and did not return to work that day. Those employees who did not attend for work that day included 23 employees of York Civil. There was no authorisation given by York Civil for those employees to be absent from work on 20 February 2015. 5 Not all York Civil employees failed to attend work that day, but the absence of those employees that day meant that a concrete pour scheduled for 20 February 2015, was unable to proceed. York Civil's construction progress was, accordingly, delayed by one day. 6 The applicant's predecessor, the Director of the Fair Work Building Industry Inspectorate, commenced a proceeding in this Court against the 23 York Civil employees who did not on 20 February 2015 attend work at the project site, alleging that each of the respondents had contravened s 417(1)(a) of the Fair Work Act 2009 (Cth) (the Act) by failing or refusing to attend for work, or by failing or refusing to perform any work, at the project site on that day, and so unlawfully engaged in industrial action. 7 The applicant sought relief by way of declaration and the imposition of a civil penalty payable by each respondent. 8 Section 417(1)(a) of the Act provides as follows: 417(1) A person referred to in subsection (2) must not organise or engage in industrial action from the day on which: (a) an enterprise agreement is approved by the FWC until its nominal expiry date has passed;… 9 The applicant subsequently discontinued the application against four of the respondents. 10 It was common cause that each of the respondent's employment with York Civil was covered by the York Civil Pty Ltd SA & WA Enterprise Agreement 2013-2017 whose nominal expiry date had not passed at the time of the impugned conduct. 11 Before the date of the hearing of the applicant's application, the parties reached agreement as to the disposition of the litigation. In furtherance of that agreement, the applicant amended his statement of claim and each of the respondents made admissions in the defence that by his or her conduct on 20 February 2015 he or she had contravened s 417(1)(a) of the Act. 12 The parties also agreed that in considering the appropriate penalty to be imposed, the Court was to have regard to the following affidavit evidence: (a) Affidavit of Christian Joder, dated 3 May 2016: paras 1 to 15 and paras 57 to 82; and (b) Affidavit of Luke Benjamin Spagnolo, dated 5 May 2016: paras 1 to 9 and paras 21 to 37. 13 Mr Joder was, at the material time, the senior project manager employed by York Civil at the project site. Mr Joder's evidence was, relevantly, to the effect as set out at [1] to [5] above. Mr Joder also deposed that the employees who did not attend work on 20 February 2015 were recorded as having taken leave without pay. 14 Mr Spagnolo was, at the material time, employed by Thiess Pty Ltd as the site superintendent. Mr Spagnolo said that on 19 February 2015, the day before the events in question, at about 6:30 am, he observed a meeting of persons at the front gate of the project site. The meeting was conducted by Mr Mick Buchan of the CFMEU and Mr Steve McCartney of the AMWU, with Mr Terry Hayes of the Electrical Trades Union in attendance. After the meeting, Mr Buchan and Mr McCartney spoke to Mr Spagnolo and informed him that they had concerns about health and safety on the project site, as well as harassment and intimidation by York Civil and its subcontractors of workers who were members of the CFMEU and AMWU on the project site. Mr Spagnolo informed Mr Buchan and Mr McCartney that he would discuss their issues with the TASK JV construction manager, Mr Brett McGrane. As Mr Buchan was leaving the project site, he told Mr Spagnolo he would be back the following day for another meeting. 15 Later that day, following his discussion with Mr McGrane, Mr Spagnolo spoke again with Mr Buchan and Mr McCartney and informed them of a plan to conduct a series of "toolbox meetings" onsite to address the unions' concerns. 16 Each of the parties made submissions to the Court to the effect that the appropriate penalty to be imposed upon each of the respondents in respect of his or her contravention was $1,000.00. 17 The Court is not bound to impose a penalty which the parties have agreed as part of the settlement of litigation. However, it is recognised that there is a public benefit in the settlement of litigation because it relieves the parties and the court from conducting a hearing, thereby saving the parties the expense and time involved in the hearing and also freeing the resources of the regulator and the court to be deployed on other cases (Commonwealth v Director, Fair Work Building Industry Inspectorate (2015) 326 ALR 476). 18 In these circumstances, the Court will consider whether the penalty which the parties propose is a penalty which falls within the range of appropriate penalties, having regard to the relevant factors. 19 The question of an appropriate penalty is to be determined by a process of "instinctive synthesis" involving consideration of all relevant factors (Australian Opthalmic Supplies Pty Ltd v McAlary-Smith (2008) 165 FCR 560 at [27] and [55]). 20 One such factor is the maximum penalty which may be imposed. The Court will in an appropriate circumstance have regard to the maximum penalty for a contravention as being reserved for the worst cases, and then to assess the proper penalty by reference to that circumstance. In this case, the maximum penalty is $10,200.00. 21 I consider other relevant factors below.