© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2022] NSWCA 24
Court of Appeal (NSW)
2021-08-18
Macfarlan JA, Gleeson JA, Payne JA
Original judgment source is linked above.
: Emmett AJA File Number(s): 2016/139580
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
HEADNOTE [This headnote is not to be read as part of the judgment] On 14 October 2014, Mr and Mrs Stepanoski ("the Owners") and Mr Aslan ("the Builder") signed a Cost Plus Contract for the construction by the Builder of two residences on the Owners' land. In late 2014 or early 2015, the Owners and the Builder signed a Lump Sum Contract relating to the same construction. The Lump Sum Contract was held to govern the parties' relationships from the date it was signed and was effective retrospectively from 14 October 2014. As the works progressed, the Builder issued a number of progress claims under the Lump Sum Contract, including Progress Claim 4 which was issued on 14 September 2015. The Builder gave evidence that on or about 16 September 2015 he was prevented from "coming back to the job" because he was "locked out" by the Owners. On 21 September 2015 the Builder emailed the Owners a Notice of Ceasing Building Works which, inter alia, stated that work would not recommence until Progress Claim 4 was paid. The Owners subsequently commenced proceedings in the Technology and Construction List of the Equity Division claiming damages for breach by the Builder of the Lump Sum Contract. The Owners claimed that, inter alia, by reason of the Builder's Notice of Ceasing Building Works, and of his cessation of work, the Builder evinced an intention to no longer be bound by the contract. The Owners claimed that they accepted the Builder's repudiation and terminated the contract on 1 May 2016. In the proceedings the Owners claimed loss arising from the cost of rectification works and a loss of rental income that would have been earned if the works had been completed on time. The Owners further alleged that they had overpaid the Builder and that they were entitled to recover the amounts of the overpayment because they had made the payments in the mistaken belief that they represented the Builder's true contractual entitlement. The primary judge found that the Builder had repudiated the Lump Sum Contract but that the Owners had not proved that they suffered any loss as a result of their acceptance of the repudiation ([2019] NSWSC 1445). In a subsequent judgment, his Honour granted the Owners leave to reopen their case in the proceedings and tender additional evidence concerning the loss they had allegedly suffered ([2020] NSWSC 139). In a final further judgment, the primary judge awarded damages in the sum of $2,698,656.28 to the Owners ([2020] NSWSC 900). The Builder then appealed to this Court and the primary issues on appeal were: (1) Whether the Builder repudiated the Lump Sum Contract; (2) Whether the Owners' payments to the Builder were recoverable to the extent that they exceeded the value of the work done; (3) Whether the Owners should have been granted leave after the primary judge's judgment was given to reopen their case to tender additional evidence concerning their alleged loss. The Court unanimously allowed the appeal: In relation to Issue 1 (repudiation) The Owners did not establish that, in making Progress Claim 4, the Builder was claiming an amount to which he was not entitled. In making Progress Claim 4, the Builder sought to hold the Owners to the Lump Sum Contract and that claim did not therefore constitute repudiation: [76], [78]. Further, there was evidence that the Owners locked the Builder out of the building site. The Builder's "failure to resume work" therefore could not be categorised as repudiatory conduct: [79], [81]. In relation to Issue 2 (restitution) A comparison of the sums paid under a contract with the value of the work completed does not necessarily reveal whether there has been an overpayment under the contract: [88]. For the purpose of considering a restitutionary claim based on the payment of money under mistake of fact or law, the correct question was whether the payments made by the Owners were in fact in discomformity with what the Lump Sum Contract provided. The primary judge did not to answer this question: [89], [90]. In relation to Issue 3 (leave to reopen) There were no special circumstances that justified departure from the ordinary rule that a party is bound by the case that it conducts to judgment, particularly where it has made a deliberate decision to put its case on a limited basis: [103].
Judgment
Development approval
The Lump Sum Contract
The progress of the works
THE TECHNOLOGY AND CONSTRUCTION LIST PROCEEDINGS
The Owners' Amended Technology and Construction List Statement ("ATCLS")
The No 1 Judgment - Lump Sum Contract
The No 2 Judgment - Summary Judgment for $225,710.38
The No 3 Judgment - Repudiation and Damages
The No 4 Judgment - Stay on Summary Judgment lifted
The Reopening Application
The No 5 Judgment - Grant of Leave to the Owners to Reopen
The No 6 Judgment - Damages Re-quantified
THE GROUNDS OF APPEAL
THE REPUDIATION ISSUE
Whether the Builder claimed amounts to which he was not entitled
Whether the Builder locked out from the works
Conclusion on repudiation
THE OWNERS' RESTITUTIONARY CLAIM
LEAVE GRANTED TO THE OWNERS TO REOPEN THEIR CASE ON DAMAGES
ORDERS
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 08 March 2022
Aslan
Stepanoski
[1985] HCA 28
(1993) 176 CLR 300
(2013) 87 ALJR 1159
(1978) 138 CLR 423
(1989) 166 CLR 623
(2019) 267 CLR 560
(1992) 176 CLR 256
(1985) 59 ALJR 481