Findings
20In considering the different submissions and the alternative Orders proposed by the applicant, I am satisfied that the approach adopted by the council should be preferred for a number of reasons.
21First, there was no dispute that the building, as constructed, does not reflect the DA 242/2006 plans, the Construction Certificate plans or the amended Construction Certificate plans. Mr Cox refers to the difference as significant whereas Mr Ayache's submissions describes the differences as substantially the same as the DA 242/2006 plans. In my view, the description of Mr Cox is more accurate.
22While Mr Ayache submitted that that the Court cannot place any reliance on the amended Construction Certificate plans as they were not part of the evidence in proceedings, the evidence of Mr Cox is clear (and unchallenged) in that he had viewed the amended Construction Certificate plans and these plans were simply photocopies of the original development consent drawings, did not reflect the building work as constructed and were unsuitable for Construction Certificate plans. There is no reason why I should not accept his evidence on the amended Construction Certificate plans.
23I also note that the survey plans referred to by the applicant in their alternative Orders (survey report of Barry James Inwood) do not reflect the building, as constructed, as the area opposite Unit 1 (and referred to by Mr Cox as the area of additional excavation) is not shown on these plans. The consequence is that there are no plans before the Court that reflect what has been constructed. In my view, it would be inappropriate to allow work to continue on the site, even for minor work suggested in the applicants alternative Orders, without a clear understanding of what work is to be carried out and in what area. I do not accept that the applicants alternative Orders provide sufficient certainty to be considered as viable or reasonable options in the proceedings. The uncertainty of the applicants alternative Orders was raised by Mr Griffiths however no amendments were made.
24Second, I agree with Mr Cox that the fire safety assessment and compliance with the BCA is uncertain, at best. I accept his unchallenged evidence that the Construction Certificate plans do not satisfy the deemed to satisfy provisions of Part D1.3 of the BCA and the amended Construction Certificate do not allow a proper assessment of the BCA requirements. In any event, any reliance on the assessments for fire safety carried out as part of the Construction Certificate plans and amended Construction Certificate plans (as referred to in Exhibit 3, pp 40 and 61) must be fundamentally flawed as these assessments relate to plans that are different to the building, as constructed.
25I also agree with the submission of Mr Griffiths that the concerns of the council may have been addressed through a further fire safety report that provided a performance based assessment to the BCA requirements (rather than the deemed to comply standards in the BCA) however this sensible approach was not adopted by the applicant.
26Third, I accept that the absence of a BASIX Certificate may be easily addressed however without a BASIX Certificate, it is inappropriate to dismiss the valid legal concerns raised by the council. Again, the suggestion of Mr Griffiths that any concerns of the council may have been addressed through a fresh BASIX Certificate was also not adopted by the applicant..
27Mr Griffiths raised the question of power in relation to the amended Construction Certificate although it was not fully explored by the parties. In my view, it is not necessary to address this matter beyond stating that if there was power to amend the Construction Certificate, then it would not alter my conclusions for the reasons set out earlier in the judgment. Conversely, if the amended Construction Certificate was found to be issued contrary to power, and reliance was placed on the Construction Certificate, then my conclusions would be the same.
28Section s 121K(4) provides:
(4) On hearing an appeal, the Court may:
(a) revoke the order, or
(b) modify the order, or
(c) substitute for the order any other order that the person who gave the order could have made, or
(d) find that the order is sufficiently complied with, or
(e) make such order with respect to compliance with the order as the Court thinks fit, or
(f) make any other order with respect to the order as the Court thinks fit.
29In this case, I do not accept that the applicant has provided sufficient justification for the proposed alternate Orders and I propose that the Terms of Order be endorsed and the Reasons for the Order be modified, in accordance with s 121K(4)(b), to read:
The Reasons for the Order are:
3.1.The building under construction at Lot 36 DP 4724 being 19 Elizabeth Street Allawah is not being built in accordance with the "Construction Certificate" of Dix Gardner Pty Ltd 137/11 dated 25 May 2011, or
3.2.The building under construction at Lot 36 DP 4724 being 19 Elizabeth Street Allawah is not being built in accordance with the "amended Construction Certificate" of Dix Gardner Pty Ltd 137/11 dated 25 May 2011