A The original proceedings BU2000/5370 were between the same parties as the present proceedings and sought orders for the payment of $37,470.00 as compensation for defective mouldings as made by the first respondent and installed by the second respondent.
B These proceedings were the subject of consent orders on 28/11/00 in which the first respondent was to pay the sum of $6,400.00 and to supply new mouldings to be installed by the second respondent.
C As the consent orders contained a work order, the applicant was given the right to relist the application, initially to 31/3/01, but extended to 31/8/01.
D Member Mr Jeffrey Smith subsequently held that the purpose of the relisting was to allow the applicant to pursue monetary compensation if the work order was not adhered to by the respondents.
E The Member also determined that the failure to relist the application by 31/8/01 effectively meant that the applicant could not pursue orders further to those agreed on 28/11/00.
F The result of the orders of 28/11/00 and subsequent determinations in proceedings BU2000/5370 is that the applicant's claim for compensation arising from the fabrication and installation of the moulding at her premises, has been finally determined.
G The failure of the applicant to relist the application in the time provided gives rise to an issue estoppel in respect of any further compensation claim against the respondents arising from the supply and installation of the mouldings at the applicant's premises in Coogee.
31 The applicant's solicitor first saw the notice of 19 December 2002 when his office re-opened on 13 January 2003.
32 The notice of appeal filed on 6 February 2003 was some ten months out of time in relation to the decision of 27 February 2002 and a little out of time in relation to the decision of 19 December 2002 after taking into account the court vacation.
33 There is an explanation for the delay relative to the decision of 19 December 2002 involving an injury received by the applicant's solicitor in January 2003. Counsel for the respondent Savage fairly and properly concedes that leave should be granted in relation to the appeal from the decision of 19 December 2002.
34 As to the application for an extension of time in relation to the appeal from the decision of 27 February 2002, the relevant rule is Pt 51A r3(3) of the SCR which confers an unqualified discretion on the court.
35 Counsel for Savage has referred the court to two decisions at first instance by McHugh J, where applications to extend time for appeal after lengths of time similar to that involved in the present case had occurred: Gallo v Dawson (1990) 93 ALR 479; Re Commonwealth of Australia; Ex Parte Marks (2000) 75 ALJR 470. His Honour was of the view that, where there is delay of that order, the circumstances would have to be exceptional to warrant an extension of time. However, the over-arching consideration is whether the strict application of the time limitation will or may occasion injustice: Gallo (supra); Re Manchester Economic Building Society (1883) 24 Ch D 488 per Bowen LJ; Outboard Marine Australia Pty Ltd v Byrnes [1974] 1 NSWLR 27; Moulieux v Girvan NSW Pty Ltd (rec and mgr apptd) (NSWCA, 20 September 1991, unreported, Kirby P, Priestley and Handley JJA).
36 The present case is exceptional and the refusal to extend time would occasion injustice. When the applicant's legal advisers opted to proceed as they did following the decision of 27 February 2002, rather than appeal at that stage, there was at least a prospect that the Tribunal would reverse its decision on reconsideration and then that the Tribunal would entertain the fresh application.
37 In the latter regard, it was at least reasonably arguable that the applicant was not estopped by the earlier determination: first, because as at 31 August 2001 (when the order of 9 May 2001 was said to have operated to terminate the proceedings) no claim had been notified to the Tribunal for monetary compensation for non-performance of the agreement of 28 November 2000 (that claim having first been notified on 14 September 2001); and, secondly, because of the Tribunal's statutory charter "to act with as little formality as the circumstances of the case permit and according to equity, good conscience and the substantial merits of the case without regard to technicalities or legal forms" (Consumer, Trader & Tenancy Tribunal Act 2001, s28(3)).
38 For the applicant's legal advisers to act as they did in these circumstances was not unreasonable. There was no serious delay in the prosecution of proceedings before the Tribunal following the decision of 27 February 2002. On the evidence led on the hearing before me, the applicant has a bona fide claim supported by evidence which the Tribunal would have entertained under the original application but for the decision of 27 February 2002. The respondent Savage suffers no unfair prejudice, not being the beneficiary of any favourable determination of the claim made against it on the merits, and knowing soon after the decision of 27 February 2002 that the applicant intended to continue to prosecute her claim notwithstanding that decision.
39 For these reasons, the time for appeal in relation to the decision of 27 February 2002 should be extended to accommodate the appeal.
40 As for the appeal from the decision of 19 December 2002, it is unnecessary for me to decide whether the Tribunal erred in holding that the applicant was estopped from prosecuting her claim for monetary compensation for non-performance of the agreement of 28 November 2000, if the decision of 27 February 2002 were to stand. The earlier decision is foundational to the later one. The consequence of my decision that the appeal from the earlier decision should be allowed is that the appeal from the later decision must also be allowed.
41 The proceedings should be remitted to the Tribunal for redetermination in accordance with this judgment. It would be appropriate, in that regard, for the Tribunal to relist both applications for hearing and determination concurrently so that all outstanding matters (including costs) may be determined at the one hearing.
42 Counsel should bring in short minutes of order to implement this decision, including proposed orders in relation to the costs of the appeals.
-o0o-