NSWNSWCATAP
Anel Kurtovic v Irfan Durmo
[2015] NSWCATAP 73
NCAT Appeal Panel|2015-03-17
View original sourceAt a glance
Source factsCourt
NCAT Appeal Panel
Decision date
2015-03-17
Source
Original judgment source is linked above.
Judgment (10 paragraphs)
[1]
Introduction
- Between March and about July 2013, the Appellant, Mr Kurtovic (the Builder) carried out some residential building work toward the construction of Mr Durmo's proposed new home in Marayong, Sydney. Mr Durmo (the Owner) is the Respondent in this appeal.
- The work was carried out under a contract dated 26 March 2013 (the Contract). It was common ground on the appeal that in breach of the Contract the Builder refused to continue with the work and as a consequence was liable for the increased cost of the contracted works resulting from this breach. However, there was a dispute about the quantum of such cost, as well as disputes about the Builder's liability for defective wall work and the quantum of the Owner's liability to the Builder for soil removal.
- In the Tribunal below, the Owner was awarded damages in the sum of $34,129.24. That sum was made up of three components: 1. cost to complete the work in the sum of $46,869.24, 2. cost of rectification of defective wall work in the sum of $4,510.00, 3. deduct from the total of the amounts in (1) and (2) the sum of $17,250.00 paid to the Builder for soil removal which was extra to the fixed contract price of $115,720.00.
- The Builder now appeals against the damages award. For various reasons he takes issue with aspects of each of the components making up the award of damages.
- The most significant issue concerning the size of the damages award concerns the Owner's liability for soil removal. With respect to that issue, in our opinion there are no valid grounds for appeal.
- However, we uphold the appeal in respect of some aspects of the decision of the Tribunal below. In our opinion, those aspects should be reconsidered by the Tribunal below constituted by the member who made the decision.
- It is clear that the Owner is entitled to damages in an amount adjusted to take account of the errors we have identified. Reconsideration by the Tribunal below of certain aspects of the decision can only result in the adjusted amount of damages increasing or staying the same. In the circumstances, it is appropriate that orders be made which provide for the Builder to pay the Owner the adjusted amount of damages which amount may or may not be increased following a reconsideration by the Tribunal below.