Facts, findings and issues
- Although not identified with precision, the works the subject of the Contract included such items as demolition, footings, supply of concrete, formwork and steel for slabs and construction work in relation to a retaining wall and inside walls.
- The Builder was an unlicensed contractor. As such, he was prohibited from contracting to do any residential building work: s 4(1) of the Home Building Act 1989. As a consequence, the Contract was unenforceable by the Builder but the Builder was liable for damages for breach of contract: s 10(1) of the Home Building Act 1989.
- The Contract provided for a fixed price of $115,720.00, inclusive of GST. However, soil removal was expressly excluded from this price and was to be charged at an "extra cost of $250 + GST". Progress payments were to be made.
- Over the period from 26 March 2013 to 27 May 2013 the Owner made eight payments to the Builder totalling $108,250.00. Some amount of this total was for soil removal. Hence, such latter payment was not made in respect of work the subject of a fixed price.
- It was implicit in the decision of the Tribunal below that the Contract was lawfully terminated by the Owner after the Builder refused to return and complete the works. There was no challenge to that positon on appeal. The time when this occurred seems to have been in November 2013, after considerable work had been done by the Builder and after the inspecting engineer would not certify the works.
- The work required to complete the contracted works was done by other contractors. This consisted of formwork for a suspended slab and the supply and fixture of that suspended slab.
- The Tribunal below found on the "only evidence before it" that the Owner's cost to complete the works was $46,869.24, inclusive of GST: at [8] and [9]. This was the total of two invoices - one from Slavco Duric and the other from Kadric Building Services.
- The invoice from Kadric Building Services included charges totalling $4,108.40 under the category of "Extra charges …". These charges were additional to a charge of $24,000.00 for the supply and fixture of a suspended slab. In the Tribunal below, and on appeal, the Builder disputed the Owner's entitlement to these extra charges on the basis that they were for work that was additional to the contracted works (Issue 1).
- The other element of the Owner's claim in the Tribunal below was for rectification work to walls that the Owner claimed were installed by the Builder. The claim here was for the amount of $4,510.00, inclusive of GST. This was the subject of an invoice from Hills Stonemasonry dated 25 January 2014.
- In respect of this claim, the Builder did not dispute the Tribunal's finding at first instance that the "brickwork was defective" (at [7]) nor did he dispute the quantum of the cost of rectification. His argument was that "brickwork" was not part of the contracted works (Issue 2).
- The Owner's claim for $46,869.24 for the cost to complete the fixed price component of the contracted works was based upon the premise that the fixed price for those works had already been paid to the Builder. Hence, the whole of this additional cost was the financial loss to the Owner of not having these works carried out at the fixed price of $115,720.00.
- However, it was accepted by the Owner in the Tribunal below, and on appeal, that soil had been removed, and that if invoices were provided for such work money was owing to the Builder for that removal and that money had to be deducted from the damages the Owner was entitled to receive. This was because soil removal was separate from the fixed price component of the contracted works.
- When the Builder belatedly supplied invoices for the soil removal there were three invoices totalling $39,930.00, inclusive of GST (this excludes a separate charge for excavation).
- The Owner disputed the quantum of these charges for soil removal. The Tribunal below upheld the Owner's objection. The Tribunal below found that the amount for soil removal that the Builder was entitled to was only $17,250.00.
- The Tribunal below also found that part of the amount actually paid to the Builder by the Owner had been for soil removal and that the sum of $17,250.00 "be allowed in the amounts paid" by the Owner: at [9] and [12(iv)].
- On appeal, the Builder contended that it was entitled to the above sum of $39,930.00, inclusive of GST, for soil removal and that this sum had, in fact, been covered by the payments made by the Owner on 17 April 2013, 1 May 2013 and 8 May 2013 (Issue 3).
- A fourth issue on the appeal concerned five payments totalling $5,204.68 made by the Owner to suppliers in July 2013. The Tribunal below found that these were paid to suppliers "at the request" of the Builder and formed part of the total amount of $118,448.68 paid by the Owner in respect of the contracted works: at [6].
- On appeal, the Builder disputed that the payments were made at his request and claimed that these payments were for items additional to the contracted works (Issue 4).
- In determining the damages award the Tribunal below proceeded on the basis that following the termination of the Contract, the whole of the cost to complete the fixed price component of the contracted works, namely $46,869.24, was recoverable by the Owner. However, such cost was only recoverable to the extent that the total cost to the Owner of the fixed price component of the contracted works exceeded the agreed fixed price of $115,720.00. The Builder contended that the Tribunal below erred in failing to carry out this calculation (Issue 5).