The applicants' claims
85 The applicants claimed that Connelly and the developer:
a) breached the conditions in Part C of the development consent by undertaking work involving the removal of trees and the clearing of vegetation on or about 8 January 2008, without having approval for the requisite plans required under the development consent for the work to commence;
b) commenced work involving the clearing of vegetation and removal of trees without carrying out and having approved the requisite design plans required under Part B of the development consent; and
c) commenced work involving the clearing of vegetation and removal of trees without a certified construction certificate.
Undertaking to the Court by Connelly and the developer
86 During final submissions Connelly and the developer, by their counsel, gave an undertaking to the Court, without admissions, that "they will not conduct any further clearing work until the conditions in Part C of the consent have been satisfied, and will not conduct further clearing work on any part of the land until a construction certificate has been issued for that part of the work to be conducted".
87 The applicants accepted that this was sufficient relief, subject to the Court ordering that they be given five days' notice by Connelly and the developer of any intention to clear any trees. I am disinclined to make the additional order sought by the applicants, which would in effect specially empower them to police the undertaking. The powerful sanction of punishment for contempt of court is available for breach of an undertaking to the Court. I should not assume that there is a danger that Connelly and the developer will not comply with their undertaking to the Court without such a policing order.
88 The undertaking to the Court by Connelly and the developer substantively disposes of this part of the applicants' claim. However, the applicants are entitled to have the Court determine the liability of Connelly and the developer, which has not been admitted, and this determination may bear on the issue of costs. Therefore, I will address the issue of liability.
Findings of fact
89 Under Parts B and C of the development consent, prior to commencement of any works various plans have to be approved and a construction certificate has to be issued. It was not disputed on the pleadings or in evidence, and I find, that Connelly and the developer cleared trees and vegetation as alleged before these plans had been approved and before a construction certificate was issued.
90 The defence of Connelly and the developer is one of confession and avoidance. They submit that the clearing activities were not the subject of, or regulated by, the consent, nor were they prohibited by any environmental planning instrument.
The Ballina Local Environment Plan
91 The land on which the clearing occurred is zoned 2(a) under the Ballina LEP. Clause 9 of the Ballina LEP provides that development is only permitted in zone 2(a) with development consent. Clause 5 defines "clearing", in relation to land, as the "destruction or removal in any manner of native plants growing on the land". (It contains two presently irrelevant exceptions). Clause 5 defines "native plants" as "plants indigenous to the State of New South Wales, including trees, shrubs, ferns, vines, herbs and grasses indigenous to the State, but does not include plants grown for commercial purposes". I accept the evidence of Mr Andresen, who observed the clearing, which indicates that the clearing was of native plants.
First issue: was clearing permitted under the Ballina LEP?
92 Connelly and the developer submitted that, upon a contextual reading of the entire Ballina LEP, clearing activities in zone 2(a) are not prohibited. This is because the Ballina LEP contains a number of provisions in relation to tree clearing, which are limited to specified zoned areas, and which do not include land zoned 2(a). Connelly and the developer pointed to cl 23, which applies to zones 1(d), 7(c), 7(d), 7(d1), 7(f), 7(i) and 7(l), and cl 24, which applies to zone 7(a). Both cll 23 and 24 expressly prohibit clearing of land without the consent of the council. They submitted that, therefore, when the Ballina LEP is read as a whole, there is a coherent scheme within it to expressly prohibit clearing in certain zones, the result of which is that clearing in zones other than those listed in cll 23 and 24 is not prohibited.
93 Connelly and the developer also noted that, although empowered to do so by cl 8 of the Environmental Planning and Assessment Model Provisions 1980 (NSW), Ballina Shire Council has adopted only one Tree Preservation Order, which does not apply to the relevant area. Connelly and the developer submitted that the making of this Order, combined with the existence of specific prohibitions on clearing in the LEP in specified zones other than zone 2(a), suggests that the construction of the LEP by the council's "Community Information Sheet: Vegetation Removal in Ballina Shire" (CIS) is erroneous. The CIS, upon which the applicants relied, states that the "consent of council is required for the clearing, destruction or removal in any manner of native plants, including trees, shrubs, ferns, vines, herbs and grasses indigenous to NSW". Connelly and the developer submitted that the author of the CIS had mistaken the definition of "clearing" in the Ballina LEP, which the CIS reflects in its use of the defined term "native plants", for a general prohibition on clearing throughout the Shire.
94 I do not agree with the submission of Connelly and the developer that clearing was permitted under the Ballina LEP except where expressly prohibited by cll 23 and 34. If cll 23 and 24 did not exist in the Ballina LEP, the respondents' argument would clearly fail. If their submission is accepted, the result is that a person may clear any tree without consent on any land to which the Ballina LEP applies, other than land that is zoned such that cll 23 and 24 apply. It is most unlikely that this is the legislative intent, for if it were, the result would be that clearing is unregulated in any zone to which cll 23 and 24 do not apply. I do not accept that merely because clearing is expressly prohibited in eight zones by cll 23 and 24, then clearing is permitted in all other zones.
Second issue: was clearing incidental to survey and design work required by conditions of consent?
95 Secondly and alternatively, Connelly and the developer submitted that they were permitted to clear the trees because the conditions of the development consent contemplate detailed survey and design work to which the clearing of the trees was necessarily and reasonably incidental. They referred to conditions B5 and B9, which must be satisfied prior to the issue of a construction certificate. Condition B5 requires engineering design drawings to be provided to the council for civil works, relevantly including for the construction of a roundabout at the intersection of Angels Beach Drive and the proposed "entry Road 1", and for temporary turnaround facilities at the appropriate boundaries of the road network. Condition B9 requires final road design plans to be prepared by a qualified practising civil engineer. Therefore, they submitted, before they could be issued with a construction certificate, they needed to prepare engineering design drawings and final road designs.
96 The proposed development involves construction of a roundabout at the intersection of Coast Road and Angels Beach Drive. The proposed entry Road 1 flows from the proposed roundabout into the development site in an approximately north-westerly direction. Entry Road 1 will form a continuation of Coast Road through the roundabout into the development site. However, it appears from the site plans that the width of entry Road 1 will be less than that of the Coast Road. There is a proposed triangular traffic island on entry Road 1, just prior to where it meets the roundabout.
97 The area that was cleared formed part of the approach of entry Road 1 from within the development site to the roundabout. Connelly and the developer submitted that a critical part of the roundabout design, being the direct path to the roundabout, occurred within the area of shrubby trees that was cleared. They argued that the clearing occurred to facilitate the detailed design and survey work necessary to obtain the construction certificate and that the clearing was done directly in the area where the design and survey work for the roundabout needed to be undertaken. They argued that they could not carry out the requisite work without clearing the trees and, therefore, the clearing was necessarily and reasonably incidental to the work required by the conditions of consent.
98 The only evidence before me of the area cleared is that in annexure B to the affidavit of Mr Lee Andresen. Mr Andresen visited the site on 8 and 10 January 2008 and observed the clearing work. Annexure B is a map of the development site, on which Mr Andresen has marked the area of clearing that he observed. This marked area is a semicircle, with a diameter significantly longer than the width of the Coast Road. As noted above, the proposed entry Road 1 appears to have a shorter width than that of the Coast Road. Connelly and the developer objected to annexure B, urging me not to accept Mr Andresen's evidence because he did not say he had entered the land and he did not claim to be a surveyor or to have paced out the distance. They did not put forward any evidence to contradict Mr Andresen's evidence nor did they cross-examine him. I accept his evidence.
99 I do not accept the submissions of Connelly and the developer. First, they put forward no evidence that it was not possible to carry out the survey and design work without clearing the trees. Thus I cannot accept that it was necessary to clear the trees to perform that work. Secondly, they cleared an area that seems to go far beyond anything that could be said to be part of the roundabout. The area cleared appears to include at least in part the proposed entry Road 1, but is far wider than the width of this proposed road. In those circumstances, it cannot be said that it was reasonably and necessarily incidental to the requisite design and survey work that the trees be cleared. It is unnecessary to address the correctness of the assumption in their submissions that if clearing is necessary in order to carry out survey and design work, then the clearing is implicitly authorised by the terms of the development consent.