The 21 July Addendum
60Before any payment was made by the Bank to Caprock on the 19 July demand, ALYK instructed solicitors to seek Court orders enjoining payment by the Bank to Caprock. On 25 July 2012 ALYK obtained ex parte interim orders preventing payment. But, in the background to the proceedings to enjoin payment, the parties were developing a compromise that would end the dispute. By 21 July 2012, the parties had reduced the terms of their compromise to writing; a compromise which they had partly anticipated in their November 2011 Memorandum, and which they now called, "the Addendum". With the Addendum finalised, on 25 July 2012 Caprock communicated, via its solicitor HWL Ebsworth, that there was nothing to be gained in debating the issue of payment on the 19 July demand and as such it would withdraw the 19 July demand. On 26 July 2012 the orders of 25 July 2012 were vacated.
61The Addendum substantially amended the parties' obligations with respect to the standby LC. It deleted clauses 4 and 5 of the Contract with respect to the first shipment (clause 1). It made detailed provision, for issuing two further LC's (clause 2) and for amending the standby LC (clause 3). The Addendum shows all the internal evidence of the parties' 11 months of frustrating negotiations in a dynamic market environment. It provides (in clause 4) for ALYK to pay Caprock a deposit of US$2 million "to the account of the seller", which Caprock could apply as it wished pending its further performance under the Contract.
"This Addendum shall form part of the contract for sale of iron ore fines between Caprock Commodities Pty Ltd as Trustee for the SAFE Fund (the Seller) and ALYK (H.K.) Limited (the Buyer) executed on 18 August 2011 (the 'Contract'), and supersedes addendum No. 1.
1.Clause 4 and 5 of the Contract shall be deleted and replaced with the following terms for the shipment only:
A. The Price CFR North China Main Port shall be calculated as at the 15th of the month prior to loading in accordance with the midpoint of Percentage 63.5% Fe Grade CFR North China Platts Index minus 3%.
2.The Buyer shall within five (5) banking days from the Seller's instruction to issue two documentary Letters of Credit, with the following terms:
a) Quantity 50,000DMT
b) Price $132.16/DMT
c) Tolerance +/-10%
d) Partial Shipments allowed
e) Irrevocable Transferable
f) Origin: Mexico/Chile
g) Valid for 120 days
h) Date of Last shipment - 90 days from issue
i) Advising Bank - China Constructions Bank - Sydney Branch (details previously provided)
j) Value of LC
i)USD$4,459,760.00 (97%)
ii)USD$138,240.00 (3%)
3.The Buyer shall give instructions to the Issuing Bank to amend the Standby Letter of Credit Number SBLC20110101 dated 11 November 2011, and copy of SWIFT MT799 from CCB Shandong to CCB Sydney requesting CCB Sydney to reissue the SBLC upon withdrawal of the demand, and that the the SBLC is to be negotiable, assignable and transferable in whole or in part by the beneficiary without presentation to the issuing bank and without payment of any transfer fees. The SBLC is to be issued by China Construction Bank Sydney to Caprock or its nominee by MT760 and not just in hard copy.
4.The Buyer shall deposit to the account to the Seller the amount of USD$2 million to be credited against first shipment, in exchange for a corporate Advance Payment Guarantee dated 21 July, 2012 and a commercial invoice from the Seller. This payment is not to be held in trust or on account of the Buyer and may be used by the Seller to meet its expenses. The Seller hereby seeks to amend the account details in The Contract for the purpose of the Deposit as follows..."
62Other consequential matters were provided for in clauses 5 to 7 and 10 and 11 of the Addendum, which, in its material terms, is reproduced below:-
5.This Addendum shall, subject to its terms, be binding on the parties and form part of the Contract which shall continue with full force and effect subject to the terms herein. Clause 1 to this Addendum shall not however apply to any shipment after the first shipment made pursuant to the Contract.
6.This Addendum is without prejudice to the rights of the parties that exist or may accrue on before the date of execution hereof.
7.A delivery Schedule for 2012 delivery is to be issued to the Buyer after first Shipment is completed.
...
10.Once clause 3 and 4 herein are satisfied, the Seller is obliged to promptly withdraw the demand made on the SBLC. The Amended SBLC in accordance with clause 3 above is to be issued to the Seller by MT750 in exchange for the withdrawal of the demand.
11.This Addendum is binding on all parties on and from the date on which the last party executes this addendum.
ALYK (H.K.) Limited acknowledges and accepts the terms and conditions of this Addendum, in accordance with the laws of its country of registration."
63Addendum, clause 3 became an obstacle to implementing the Addendum. The Bank raised problems with this clause. But this clause's treatment of the existing standby LC also became an important point in the Contract's construction. Within a further two months the problems with clause 3 had generated the current litigation.
The Present Dispute
64The present dispute arose at this point. After the Addendum the Bank did not issue an amended standby LC. The Bank's reasons for this and the course of events need only be explained in a summary form. The Court does not have to make findings on these matters in these proceedings.
65Caprock claims there is no evidence that ALYK ever instructed the Bank to amend the standby LC. ALYK disputes this and says that on 22 July 2012, it and another company in the Yankuang Group, made an application to the Bank to amend the standby LC, in accordance with the Addendum. There is certainly some evidence that this is what happened. ALYK also says that on 23 July 2012 the Bank replied to ALYK to the effect that the Bank would only consider the application following the withdrawal of the first demand made by Caprock.
66On 23 July 2012, ALYK paid the US$2m deposit provided for by Addendum, clause 4 to Caprock, which confirmed receipt of this sum the same day. The month after this payment was made a legal standoff had developed between ALYK and Caprock.
67On 25 July 2012, ALYK obtained orders from the Court restraining the Bank from paying against the 19 July demand. But on 26 July 2012, ALYK and Caprock filed consent orders dismissing the summons and vacating the orders of the previous day. As part of the settlement Caprock agreed to withdraw the first demand.
68Between 26 July 2012 and 31 July 2012 ALYK and Caprock corresponded about amending the standby LC. But by 1 August 2012, the standby LC had still not been reissued as was contemplated by Addendum, clause 3. So, on 1 August 2012, Caprock issued a notice of default to ALYK asserting the failure to reissue the amended standby LC in accordance with Addendum clause 3. Yet on the same day ALYK responded that it had instructed the Bank to issue the amended standby LC in accordance the Addendum.
69ALYK says it gave further instructions to the Bank to comply with Addendum, clause 3. ALYK says that it made a further request to the Bank on 6 August 2012. ALYK says that it also communicated with Caprock on 10 August 2012, in order to pass on to Caprock the Bank's comments that the Bank was unwilling to reissue an amended standby LC, when Caprock had not nominated who would be the transferee. ALYK's case is that on 14 August 2012, it gave yet further instructions consistent with Addendum clause 3, to both the bank's Shandong and Sydney branches.
70But why was there a standoff at this time? There were two main reasons: one had its origins with the Bank, and the other with Caprock.
71Perhaps no-one had consulted the Bank before Addendum, clause 3 was drafted. The Bank had problems with executing it. A close reading of the correspondence in my view shows that the Bank's position was not unreasonable. The Bank had a concern about a standby LC which "is to be negotiable, assignable and transferable in whole or in part by the beneficiary without presentation to the issuing Bank and without the payment of any transfer fees". The Bank was not prepared to accept the risk of the standby LC being divided into portions which may add up to claims against it that were greater than whole value of the standby LC. Nor was it prepared to accept the risk of the standby LC being assigned to multiple parties whose identities were unknown to it. The Bank's position was not unreasonable.
72But Caprock was also making allegations of breach that seem somewhat to stretch the words of clause 3 which requires the buyer, ALYK, to "give instructions to the issuing Bank to amend the standby LC". The instructions were to include a request to the Bank's Shandong branch to its Sydney Branch, asking the Sydney Branch to "reissue the standby LC upon withdrawal of the demand". Yet Caprock has insisted in correspondence that the provision required ALYK to ensure the issue of an amended standby LC. I do not have to decide this question, but though arguable that does not seem to be compelling reading of clause 3.
73There were many other small disputes between the parties in this period into which the Court does not have to enter. Suffice it to say that the standoff was contributed to by the Bank taking a reasonable view of its own future commercial exposure, and the parties' mutual point taking.
74Caprock then acted on what it claimed were ALYK's Contract defaults. On 22 August 2012, Caprock issued a notice of default: it cited ALYK's alleged failure to give proper instructions to the Bank and the non-issuance of the standby LC, as defaults.
75Then, on 6 September 2012, Caprock acted on its 22 August default notice: it gave ALYK notice of termination of the contract; and, made demand on the Bank under the standby LC for US$20m ("the 6 September demand"). In the 6 September demand Caprock recited: the 11 November 2011 standby LC, the amount of its claim of US$20 million and that "ALYK (HK) Ltd (the Principal) is in breach of his obligations in accordance with the contractual conditions" and, that it was not in breach of contract. The particulars of the "respect in which the principal is in breach" as required by the standby LC (4) were stated in the 6 September demand:-
"In accordance with clause 6 of the Contract, ALYK (HK) Limited (the Principal) failed to issue a Documentary Letter of Credit at least thirty (30) days before the date of the first shipment, being 20th May, 2012. On 12 June 2012, Caprock Commodities Pty Ltd ATF SAFE Fund (the Beneficiary) issued to the Principal a Notice of Default complaining of the breach. As at the date of this Demand the breach by the Principal has not been rectified and the Principal remains in breach (the First Breach).
On 19 July 2012 the Beneficiary issued a First Demand in respect to the First Breach which was withdrawn on 25 July 2012 on the basis of an agreement between ALYK and Caprock Commodities Trading Pty Ltd (the 'Addendum') dated 21 July 2012. The terms of the Addendum have not been complied with.
Clause 3 of the Addendum requires the Principal:
'to give instructions to the Issuing Bank to amend the Standby Letter of Credit Number SBLC20110101 dated 11 November 2011, and copy of SWIFT MT799 from CCB Shandong to CCB Sydney requesting CCB Sydney to reissue the SBLC upon withdrawal of the demand, and that the SBLC be negotiable, assignable, and transferable in whole or in part by the beneficiary without presentation to the issuing bank and without payment of any transfer fees. The SBLC is to be issued by China Construction Bank Sydney to Caprock or its nominee by MT760 and not just in hard copy'.
Clause 10 of the Addendum provides that the 'Amended SBLC is to be issued to the Beneficiary by MT760 in exchange for the withdrawal of the demand'. The First Demand was withdrawn on 25 July 2012 and the amended SBLC has not been issued to the Beneficiary.
On 1 August 2012 and 22 August 2012, the Beneficiary issued a two further Notices of Event of Default complaining of the breach. As at the date of this First Demand the breach by the Principal has not been rectified and the Principal remains in breach."
76The next day, 7 September 2012, ALYK approached the Duty Judge in the Equity Division of this Court, Rein J. The Court granted an interim injunction that day, until further order, preventing payment under the standby LC. The matter then came before Nicholas J on 11 September, when further procedural directions were made. It was mentioned before me as Duty Judge on 26 September and then was heard on 5 October 2012. The parties were allowed time to lodge supplementary written submissions to deal with some issues that had not been anticipated before the 5 October hearing, which at relatively short notice had become a final hearing. Those submissions were received after the 5 October hearing and judgment was reserved on 19 October 2012.