Alta Building & Developments Pty Ltd v Brendan Jay McAllery and Tracey Catherine Margaret McAllery
[2014] NSWCATCD 107
At a glance
Source factsCourt
NCAT Consumer and Commercial
Decision date
2013-08-30
Before
Mr J
Source
Original judgment source is linked above.
Judgment (28 paragraphs)
reasons for decision 1These proceedings were commenced in August 2010 when the applicant sought the sum of $164,140.77 from the respondents being payments said to be due by the respondents under the terms of a building contract. 2In these reasons for decision, I will refer to the applicant as the builder and to the respondents as the owners. 3The owners have made a cross application against the builder which was heard simultaneously with these proceedings. 4The builder was self-represented in these proceedings and in the owners' cross application. 5The parties entered into an undated Cost Plus (Residential) building contract in a form prepared by the Master Builders Association (the 'contract'). The work to be carried out by the builder was described as 'New Gymnasium and Artists Studio'. The estimated cost of works pursuant to clause 30 of the contract was $297,819.50. The cost of the works exceeded $297,819.50. 6Part B of Schedule 1 to the contract provided that the owners would pay the builder a fee of $45,000.00 plus GST. 7The work was to be carried out at the owners property situate at 4 Emperor Place, Kenhurst. 8The work was in the nature of the construction of a new building at the residence which was to form part of the residence. 9There is no dispute that the Home Building Act 1989 applies to the work carried out by the builder and that I have jurisdiction pursuant to the Home Building Act to determine this application. 10On 24 November 2010 the builder filed and served points of claim in which it claimed a balance due under the contract of $54,199.97, the sum of $165.00 representing an amount paid by the builder to a hydraulic engineer, interest and costs. The builder's claim is set out in detail in annexures A and B to its points of claim. Annexure A sets out progress claims and calculates a balance due. Annexure B sets out calculations in support of an additional builder's fee. 11In short the builder claims $43,300.88 in connection with money claimed under the contract and not paid. It claims interest on that amount of $5,277.46 and ongoing interest. It then seeks to recalculate its building fee so to seek an additional $10,899.09. It also seeks to be reimbursed $165.00 for a plumbing invoice. This leads to a total of $43,300.88 + $10,899.09 +$165.00 = $54,364.97 plus interest claimed of $5,277.46 and accruing. 12At paragraph 7 of its points of claim the builder claims in the alternative a reasonable price for work done and materials supplied. There is no basis asserted by the builder in its points of claim or in its final submissions to justify a cause of action in quasi contract when it entered into an enforceable written contract