© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2002] VSC 483
Supreme Court of Victoria
2002-11-12
HARPER J
Original judgment source is linked above.
[2002] VSC 483
ARBITRATION - Commercial Arbitration Act 1984, s.38 - Application for leave to appeal against interim award - Building dispute - Pioneer Shipping Ltd & Ors v B.T.P. Tioxide Ltd ("The Nema") [1982] AC 724; Promenade Investments Pty Ltd v State of New South Wales (1992) 26 NSWLR 203 considered - Obligations of an arbitrator who is required to hear and decide by reference to considerations of general justice and fairness - MBAV contract Form GCC3 (revised July 1994) clause 2(d).
"The project concerned the redevelopment of an existing wholesale butcher's building and an existing warehouse in Rosamond Road, Maribyrnong. The existing wholesale butcher's building was known as 159-163 Rosamond Road, Maribyrnong. This building was to be extended to house a proposed Ray's Tent Centre tenancy, which subsequently became a Betta Electrical tenancy. To the rear of the site, and known as 1-2, 12 Sloane Street, Maribyrnong was a warehouse to be redeveloped and extended into three showrooms, known as showrooms 1, 2 and 3. In order to comply with the town planning requirements for additional car parking an existing motor repairer's premises fronting Rosamond Road (on the corner of White Street) was to be demolished and the areas surrounding the redeveloped wholesale butcher's building and warehouse were to be reconstructed as a car park."
"The arbitrator must hear and decide any matter by reference to considerations of general justice and fairness, and is not bound to apply the rules of evidence and procedure."
"My lords, in view of the cumulative effect of these indications of parliament's intention to promote greater finality in arbitral awards than was being achieved under the previous procedure as it was applied in practice, it would, in my view, defeat the main purpose of the ... Act if judges when determining whether a case was one in which the new discretion to grant leave to appeal should be exercised in favour of an applicant ... did not apply much stricter criteria than those ... which used to be applied in exercising the former discretion to require an arbitrator to state a special case for the opinion of the court. Where, as in the instant case, a question of law involved is the construction of a 'one-off' clause the application of which to the particular facts of the case is an issue in the arbitration, leave should not normally be given unless it is apparent to the judge upon a mere perusal of the reasoned award itself without the benefit of adversarial argument that the meaning ascribed to the clause by the arbitrator is obviously wrong ... For reasons already sufficiently discussed, rather less strict criteria are in my view appropriate where questions of construction of contracts in standard terms are concerned. That there should be as high a degree of legal certainty as it is practicable to obtain as to how such terms apply upon the occurrence of events of a kind that it is not unlikely may reproduce themselves in similar transactions between other parties engaged in the same trade, is a public interest that is recognised by the Act ... So, if the decision of the question of construction in the circumstances of the particular case would add significantly to the clarity and certainty of ... commercial law it would be proper to give leave in a case sufficiently substantial to escape the ban imposed by the first part of s.[38(5)] bearing in mind always that a super abundance of citable judicial decisions arising out of slightly different facts is calculated to hinder rather than to promote clarity in settled principles of commercial law. But leave should not be given even in such a case, unless the judge considered that a strong prima facie case had been made out that the arbitrator had been wrong in his construction; and when the events to which the standard clause fell to be applied in the particular arbitration were themselves 'one-off' events, stricter criteria should be applied on the same lines as those that I have suggested as appropriate to 'one-off' clauses."
"Assuming that there is not a manifest error of law on the face of the award it may be argued that there is strong evidence that the arbitrator made an error of law and that the determination of the question may add, or may be likely to add, substantially to the certainty of commercial law. The requirement that the question be one the determination of which may add substantially to the certainty of commercial law indicates that it should be one of wider and greater importance than, for example, the construction of a one-off clause in the context of a particular agreement between the parties. One can discern here the sort of limitation which Lord Diplock had in mind."
"The [plaintiff] issued the notice of dispute ... as a consequence of the defendants' failure to make complete payment of a progress claim that had fallen due for payment. Exercising its rights pursuant to clause 22(e) of the ... contract ... the plaintiff suspended the works. In the event, the arbitrator's findings ... had the consequence ... that as at the date of suspension of the works by the plaintiff there was a balance outstanding from the plaintiff to the defendants in the sum of $29,540.69, as set out in paragraph 103 of the interim award."
"It was not pleaded by the plaintiff and at no time during the arbitration hearing or in submissions was it submitted on behalf of the plaintiff that the contract works had reached practical completion in accordance with the general conditions whether deemed or otherwise. Indeed, the arbitrator found ... that it was obvious that the works had not been practically completed. It was common ground that the plaintiff served a notice dated 18 December 2001 suspending the works following which the plaintiff did not carry out any further works at the site ... At no time was it submitted on behalf of the plaintiff to the arbitrator that the works had reached practical completion on the grounds that the defendants had occupied and/or used the works. As it was never raised as an issue before the arbitrator, no evidence was called in relation to the circumstances in which Betta Electrical or Impact Furniture occupied the premises for the purpose of fit-out or otherwise, including whether the works were occupied pursuant to any consent, agreement or arrangement made between the plaintiff, the defendants and the tenants (who were not called as witnesses to the proceeding). Had the plaintiff raised the issue of alleged deemed practical completion during the arbitration hearing, I ... believe that all these issues and related issues such as variation, waiver and estoppel would have been the subject of relevant evidence and submissions before the arbitrator. The arbitrator was not requested by the plaintiff to decide the question of whether deemed practical completion had taken place under clause 19 of the general conditions of contract and did not do so. The issue was not pleaded by the plaintiff or argued by either party in the arbitration."
"I note the general conditions of contract were signed on or about 4 June 2001. I further note that by a letter dated 15 June 2001 [from the solicitors for the defendants to the plaintiff] includes (sic) among other things the following: 'We note ... that you are to provide us with detailed specifications in relation to this project.' No proper building specifications for the whole project were provided to the respondent during the course of the works or at this arbitration. The only building specifications provided were those supplied during the hearing ..., which specifications do not cover ... the way the works are to be performed and/or the materials to be used."
"Mr Unsworth acknowledged that these building specifications should be accepted as the specifications for the whole project but ... for building permit purposes only. Mr King [the plaintiff's estimator] also said that these building specifications were for building permit purposes only. I have accepted the evidence given by Mr Unsworth that these building specifications should be accepted for the whole project, but I have disregarded the evidence given by both Mr Unsworth and Mr King when they said that these building specifications were for building permit purposes only."[9]
"Site conditions - The proprietor makes no representations as to the site conditions. Assess the site conditions and cover all the requirements for the contract works."
"Should site conditions below the surface, and/or, in the case of alterations or extensions to existing buildings, shown or described in the specifications and/or drawings on which the contract sum was based differ from those encountered by the contractor, then the contractor shall notify the proprietor and obtain his instructions prior to proceeding with the works and any consequent variation to the works shall be dealt with in accordance with clause 14" [the subject matter of which is variations, and which provides (among other things) for the building owner to bear the additional cost properly incurred by the builder in effecting a variation].
The Exit Stairs and the First Floor Amenities Block
"The original plans were drawn for the building in December 2000. These plans included two sets of stairs and two sets of amenities (which were what was ultimately constructed). There were no additional stairs or amenities required and the respondents are entitled to a credit for these amounts in the amounts of $15,000 and $17,485 respectively."
"My evidence and the evidence of Mr King for the plaintiff was that the additional stairs and additional amenities block were added subsequently to the 7 December 2000 letter in various correspondence. I said that the additional exit stairs and additional amenities became part of the contract by the letter dated 4 June 2001. At all times during the course of the hearing both myself and Mr King when giving evidence on behalf of the plaintiff stated that the additional exit stair and additional amenities block in the building at 159-163 Rosamond Road, Maribyrnong were the second stair and the second amenities block in that building."
"Neither Mr Unsworth nor Mr King gave evidence that the additional stairs and amenities blocks were added subsequently to the 7 December 2000 letter in various correspondence. The plaintiff did not tender any alleged correspondence at the arbitration hearing. Neither Mr Unsworth nor Mr King gave evidence that the additional exit stairs and additional amenities block in the building at 159-163 Rosamond Road, Maribyrnong were 'the second stair and second amenities block in that building'. The arbitrator found that at all times there were to be two stairs and two amenities blocks in the building and that no additional stairs or additional first floor amenities blocks were provided ... Accordingly the defendants were entitled to a credit in relation to those amounts. Again this was a finding of fact open to the arbitrator upon the evidence before him."
"I refute the allegations contained [in paragraph 15 of Mr Singh's first affidavit] ... At the hearing I gave evidence to the arbitrator that the original concept was for the existing first floor area to be serviced by the existing entry stair, but reconfigured. I gave evidence that subsequently the defendants asked me to install additional exit stairs and an additional amenities block on the first floor. I explained to the arbitrator that this was because Ray Frost of Ray's Tent City wanted the stairs to the first floor located in a specific place within the Ray's Tent City tenancy. This meant that the proposed extra area on the first floor was too large to comply with building regulations with only one stair, and a second stair was required for egress purposes and to serve two tenancies. The additional amenities block (second) was required because the defendants wanted a dual tenancy capacity on the first floor."
"I refer to paragraph 3.7 of Mr Unsworth's second affidavit. I strongly deny that Mr Unsworth gave the evidence in relation to the additional first floor stairs and first floor amenities block before the arbitrator which he now asserts he did ... Mr Unsworth ... did not give evidence that the 'original concept was for the existing floor area to be serviced by the existing entry stair, but reconfigured'. He did not give evidence that he was subsequently asked to install additional exit stairs and an additional amenities block on the first floor or that this was as a result of a request by Ray Frost. He did not give evidence that 'the proposed extra area on the first floor was too large to comply with building regulations with only one stair, and a second stair was required for egress purposes and to serve two tenancies'. He did not give evidence that the additional amenities block was required 'because the defendants wanted a dual tenancy capacity on the first floor'."
"90. The respondent is claiming a credit of $15,000 for an additional exit stair to first floor that was not in fact installed. The claimant's letter dated 4 June 2001 ... includes an amount of $15,000 for an additional exit stair to the first floor. 91. All the exhibits were provided in connection with the Ray's Tent City/Betta Electrical building at this arbitration only show two sets of stairs to the first floor area. There are still only two sets of stairs to the first floor, however the configurations are different from the original design, but there are still only two sets of stairs. In the letter of the 4th June 2001 ... the following is written 'additional exit stair to first floor - $15,000'. This express notation is for the first floor. I therefore find that there was no additional stair installed and accordingly the respondent is entitled to a credit of $15,000. 92. The respondent is claiming a credit of $17,485 for an additional new first floor amenities block. The claimant's letter dated 4 June 2001 ... includes an amount of $17,485 for an additional new first floor amenities block. 93. Again all the exhibits ... that were provided in connection with the Ray's Tent City/Betta Electrical building at this arbitration show the same number of plumbing fixtures on them. There are minor alterations and also the repositioning of one toilet block, but when on site I could not see where there was a new first floor amenities block as written in the claimant's letter dated 4 June 2001. 94. Both Mr Unsworth and Mr King failed to convince me that the respondent was not entitled to this credit. I therefore find the respondent is entitled to the credit of $17,485 for the allowance of an additional new first floor amenities block that was not constructed."
"where an arbitrator either ... self-evidently purports to determine questions arising during an arbitration according to law (and without any reference, express or implied, to considerations of justice and fairness); or ... purports to determine questions arising during an arbitration by reference to considerations of general justice and fairness, but only relies upon the law (without any reference, express or implied, to considerations of general justice and fairness) ... the arbitrator is obliged to make those findings in accordance with the law. If he repeatedly does not do so, this must constitute misconduct."[14]
[1] [1982] AC 724 at 742-743
[3] The information which follows was not presented in this form during the hearing. It is the product of my own attempt to find my way through a large volume of material.
[4] Written outline of submissions of the plaintiff in the application for leave to appeal, paragraph 8
[5] First affidavit of Peter John Unsworth, paragraph 21
[6] First affidavit of Angpal Singh, paragraph 13
[10] It might be argued that one possible condition precedent was that "site conditions below the surface ... differ from those encountered by the contractor". But this is a nonsense.
[11] First affidavit of Peter Unsworth, paragraph 32
[12] First affidavit of Angpal Singh, paragraph 15
[13] Affidavit of Garry King, paragraph 4
[14] Written submissions of the plaintiff dated 12 September 2002
[15] First affidavit of Angpal Singh, paragraph 7
[16] First affidavit of Peter Unsworth, paragraph 16
Allmore Constructions Pty Ltd
Failli [2002] VSC 483
(1992) 26 NSWLR 203