Mr Dell went on to suggest to Mr Henry ".. that we could terminate the contract where it is and continue the job on a do and charge basis" or "the second … option would be that we could renegotiate the remainder of the contract at a fixed price."
21 According to Mr Dell, Mr Henry stated that "… the drafting was the problem on the first instance of all the work that we were doing and the hold ups were in the paint shop. He has engaged two more drafting companies to complete the project and a new painting contracting and this would resolve a lot of the problems that were occurring."
22 No decision was reached at the meeting on or about 5 May.
23 In Mr Dell's evidence of his telephone conversation with Mr Henry on or about 8 May he said that "Mr Henry rejected our proposal and stated to me that I had a contract and I had to finish the job at that contract." Mr Dell told Mr Henry "that I was not prepared to continue in the basis of the job the way it was going."
24 After that telephone conversation, Mr Dell "… went to the site, … [and] informed … Allmen … that I would be removing my personnel and equipment off site, that we have struck an intolerable situation and cannot continue." Mr Dell then directed Action's employees to leave the site, but left some of its equipment on site temporarily so that Allmen "could continue doing some work for rectification without any delays."
25 The trial judge's reasons for holding that Allmen repudiated the parties' contract were stated in the following passages:
"…
I accept the general tenor of the plaintiff's evidence that this project was very very significantly behind time. I accept that it was so significantly behind time by way of failure of delivery of steel or delivery of faulty steel, that in fact the defendant company was never in a position to honour its portion of the contract, which I find was, amongst other things, to keep the supply of steel up to the plaintiff so that the work could be carried out within the time-frame envisaged.
…
Matters obviously reached a head approximately early May …
…
The contract was clearly not capable of being performed in the manner in which the plaintiff had agreed to perform it and I think that the plaintiff was entitled to regard the defendant's refusal, and there was a refusal, because I accept Mr Dell's version of what was said at this conversation of 5 May, and I accept the outcome of it. There was a refusal to renegotiate or have anything to do with it, anything to do with any renegotiation and indeed Mr Henry agrees that he said words to Mr Dell to the effect, "Look you've signed a deal and you're going to carry it out and there's going to be no problem about it." Because Mr Dell taking the view with the plaintiff company that they were entitled to an amendment to the contract or an entirely new contract because they had, as best they could, performed the contract in the manner in which the defendant was prepared to allow them up to 5 May. That is, they had been there ten weeks full time instead of two weeks on and off, they had had their workmen there all the time. They have clearly on any view of the evidence as to damages, expended the amount in terms of wages and crane hire and so on. I accept that a lot of that time was wasted by reason of the fact that they were re-fixing steel and were waiting on steel and were not able to pursue the contract in the manner in which they desired and the manner in which they had agreed with the defendant that they would. The defendant's refusal to and/or inability to alter that situation was, in my view, a repudiation of the contract which the plaintiff was entitled to accept and did accept."
26 The trial judge proceeded to award Action damages on the basis, broadly stated, that it was entitled to be paid the contract price (presumably on the basis that they had performed the contract, or possibly incurred all the costs associated with performance, although less than half the work was completed) with a deduction for "exigencies".
"I am left in no doubt that there ought be a verdict for [Action]. The difficulty is damages. It is not easy to glean from all of these documents what exactly is the length and breadth of [Action's] claim for damages. I bear in mind that damages are assessed and not calculated. I think there probably are one or two exigencies in relation to whether [Action] would ever have made the full profit out of this contract and certainly they have been paid for any variations that they submitted, although they claim of course they have not submitted any variations for what I loosely describe as "down time", that is, waiting for things and fixing things that should have been correct in the first place.
…
The statement of claim I think fairly sets it out.
…
The statement of claim, the one I am looking at, is the further amended statement of claim, which I think was the final version that came off the press, set out what I understand to be the correct figures …. . That was the contract price, the additional work, and consequently striking a total and then deducting what they had been paid in connection with the contract price and the additional work.
…
… I think the figures set out in the statement of claim are accurate when they say that the claim is the contract price plus the additional work less the amount paid by the defendant. … That would make their claim theoretically forty-nine thousand five hundred and thirty-nine dollars seventy-five. I do think however there was, (just simply having regard to the nature of the contract), I do not know that one could say with any certainty because the contract was never allowed to proceed in the manner in which perhaps it should have proceeded, that they would have made every dollar that they had anticipated. There may have been of course other additional work they would have claimed for. There may have been disputes about that, I do not know. Just, in all the circumstances of this contract and the manner in which it appears to have been conducted, I do not believe they would have ever made the full profit. I think there was likely to be some difficulties in the final completion of this matter.
I note also that they have an interest claim pursuant to s. 83A of the District Court Act. Using what I suppose some would describe as a broad brush approach, I propose to reduce the amount that they have claimed, in terms of exigencies, by something of the order of fifteen, perhaps twenty percent. But to that I would need to add an allowance for interest pursuant to s. 83A up to the present time.
Doing the best I can with all of the figures I propose to enter a judgment of the plaintiff in the sum of thirty-seven thousand five hundred dollars, and I intend to include in that amount whatever claim the plaintiff has to the present time pursuant to s.83A.
It is little more than a guesstimate in term of exigencies, but I do not think the plaintiff is entitled to all of its claim and interest on all of its claim, having regard to the ups and downs of this type of contract, and particularly this one.
There will be a verdict and judgment for the plaintiff against the defendant in the sum of thirty-seven thousand five hundred dollars and costs and I specifically say that sum is to include any 83A element in respect of interest.
…"
27 Action made an application "pursuant to the slip rule" and its judgment was increased. His Honour said:
"I felt that [Action] was entitled to the balance of that contract price, less somewhere between fifteen to twenty per cent for exigencies, and I also specifically said that I felt [Action] was entitled to the balance of that contract price, less somewhere between fifteen to twenty per cent for exigencies, and I also specifically said that I felt [Action] was entitled to the balance of the monies that [Action] had charged [Allmen] in respect of work on the Anzac weekend and, I think, the weekend following, I am just not sure, but the figure involved was agreed, or at least, not disputed, at $4289.75. I subsequently entered judgment when I did some mathematics on a pad, for $37,500. I am convinced, simply by the pure mathematical calculation, that I have intended to award approximately $4250 to [Action] which I did not include because on any version of the figures, I also said I had added in a component for s 83(A) interest in a global figure, and I recall doing that so the result must have been absent an allowance for that weekend work. I propose to round that figure down marginally from $4289.75 to $4250. I shall add that figure of $4250 to the judgment so that the judgment will now become $41,750 plus costs."