The quality of the Master Plan. Is it based on sound planning and urban design principles? Will it lead to a better outcome for the environment and the local community?
The public exposure that the Master Plan has received. Have the relevant landowners, stakeholders and the wider community been consulted?
The time frame for and likelihood of implementing the Master Plan. How long will implementation take? Is it likely that it can be implemented?
The impact of the Master Plan on the development potential of the site. Does the Master Plan unreasonably delay the development of the site?
The extent of inconsistency between the proposal and the Master Plan. Would approval of the proposal frustrate the implementation of the Master Plan?
4 With regard to the first criterion, the Court found that the Master Plan was based on sound urban design principles. With regard to the second criterion, the Court found that there was ample consultation with landowners, stakeholders and the general community over a considerable period. With regard to the third criterion, the Court accepted that there is a reasonable likelihood that the Master Plan can be implemented. There has been no new evidence to change the above findings.
5 With regard to the fourth criterion, the Court found that in the short-term it was not possible to develop the site in a way that is fully consistent with the Master Plan. Consistency would require the completion of a drainage system serving the Neil Street Precinct (thereby lowering the 1 in 100 year flood level by 1 metre), the amalgamation of the subject site with the Rositano site and construction of the New Road and the associated landscaped swale. While the evidence suggests a timeframe of 10 to 20 years for the implementation of the Master Plan, there was no conclusive material on the time it would take to put into place sufficient of the public works necessary for developing the subject site in conformity with the Master Plan.
6 During the hearing on 23 July 2004, Mr Beers told the Court that it would be three years before the site would be ready for development at the new flood level. In my opinion, this appears too optimistic, though three years might be sufficient time for the council to establish a time-specific program for public works. Regarding amalgamation with the Rositano site, Ms Hancock has put into evidence a drawing, referred to in the interim judgment, indicating an eight-storey apartment building on the subject site without amalgamation. The building would have a different footprint from that shown in the Master Plan, would have access from Terminal Place and would allow the development of the New Road and swale. While it would not fully comply with the Master Plan, it would be a variation that, in Ms Hancock's opinion, the Master Plan was robust enough to tolerate.
7 In my opinion, it would be unreasonable to put the development of this site on hold for three years, let alone for an indefinite period until the public works envisaged in the Master Plan are complete. If the subject site were developed now, any structures would have to relate to the current 1 in 100 flood level and the development would have to obtain its access, at least temporarily, from Terminal Place. Given the lack of a time-specific program of public works, inconsistency with the Master Plan to the latter extent would, in my opinion, be acceptable.
8 The crucial question for the Court is that asked under the fifth criterion in the interim judgment, namely whether the proposal is so antipathetic to the Master Plan that it would frustrate its implementation. The applicant submitted a drawing showing the 16 June 2004 proposal within the context of the Master Plan, including possible future access to the parking deck from the New Road when that road is constructed. The parking deck allows the construction of the New Road but it covers a large section of the landscaped swale. While the swale would be able to function as an element in the drainage system, it would no longer be an element in the urban landscape envisaged in the Master Plan.
9 The applicant submits that the amended proposal is sufficiently in sympathy with the Master Plan to justify the granting of a time-limited approval for 15 years. At the end of that period it will be clear whether sufficient progress towards the Master Plan's implementation has been achieved. A decision whether to extend the consent or require the supermarket's demolition could then be made. The subject site would be among the last reached by the public works required to implement the Master Plan. Therefore, an "intermediate" use of the site would be quite consistent with the Master Plan.
10 The council submits that the approval of the proposal would have a significant negative impact on the prospects of the Master Plan's implementation. Because of its manifest inconsistency in physical form and use shown in the Master Plan, it will deter potential investors in the Precinct, both public and private. It would compromise pedestrian links, terminate the landscaped swale under a concrete slab, sever the visual connection between the transport interchange, Terminal Place and the rest of the Precinct, and place an elevated parking deck in the location where there should be a landscaped focal point as an entry to the Precinct.
11 The council does not accept that the site is the last in the Precinct to be reached by the contemplated public works. On the contrary, the site, being at the entry point to the Precinct, may be where implementation will start.
Findings