HEADNOTE
[This headnote is not to be read as part of the judgment]
The respondent, George Hanna, was the named insured in a policy of insurance with the appellant, AIG Insurance Ltd (AIG) (the Policy). The Policy related to a construction project (the Project). Pursuant to cl 5.00 of the Policy, AIG was required to indemnify Mr Hanna "for all sums that you become legally liable to pay as compensation", subject to conditions not relevant to the appeal. Clause 10.01 provided that, unless Mr Hanna obtained AIG's prior written consent, he was not to admit liability or settle any third-party claim.
In October 2018, whilst the Policy was in force, Mr Hasan, a formworker on the Project, was injured when he slipped and fell from scaffolding. In August 2020, Mr Hanna made a claim for indemnity under the Policy. In a telephone call with AIG's solicitor in relation to the incident, Mr Hanna said that although he was the registered builder on the Project, he was helping a friend who had asked him to give his builder's licence number; and it was his friend who controlled the site. Mr Hanna confirmed this information in a statement he signed in December 2020. This was inconsistent with the application submitted to his insurance broker, which included a signed copy of the construction contract naming him as the construction manager.
In May 2021, AIG avoided the Policy on the basis that Mr Hanna had made fraudulent non-disclosures regarding the Project, which (on his report) was not his project; had made a further non-disclosure in circumstances where the Project was performed by an unlicensed builder; and had entered into an unlawful agreement with his friend to loan his building licence.
In August 2021, Mr Hasan commenced proceedings against Mr Hanna in the District Court, seeking damages for negligence and breach of statutory duty. Mr Hanna admitted that he was the builder responsible for the Project and otherwise denied liability. On 4 May 2022, Mr Hanna also brought a cross-claim against AIG, seeking damages for what he alleged was AIG's wrongful termination of the Policy. In his cross-claim, and in his evidence, Mr Hanna asserted that he was, in fact, the builder in charge of the site, and that he had managed the build from the outset. He also gave evidence that he had deliberately not told AIG the truth in 2020.
On 2 August 2023, the primary judge gave judgment by consent in favour of Mr Hasan against Mr Hanna in the sum of $430,000 and an order that each party bear their own costs. AIG objected to the entry of the consent judgment, which the primary judge noted in the orders.
In giving judgment for Mr Hanna on the cross-claim, the primary judge found that Mr Hanna was the builder responsible for the performance and administration of the Project and that the Policy should have responded to Mr Hasan's claim. Thus, AIG had repudiated the Policy through its wrongful termination and Mr Hanna had no choice but to accept that fact. As to the scope of cl 5.00 of the Policy, her Honour held that the clause was activated by entry into the consent judgment per se, in circumstances where AIG's consent was not available given its avoidance of the Policy. Her Honour also determined that the settlement to which the consent judgment gave effect was objectively reasonable, based on a reasonable assessment of the risk that Mr Hanna faced as the defendant to Mr Hasan's claim.
AIG's notice of appeal alleged that her Honour erred by: making findings which, it contended, were not available on the admissible evidence and were relied upon to conclude that Mr Hanna incurred a liability to Mr Hasan to which the Policy responded (numbered grounds 2 to 4); holding that cl 5.00 responded to liability assumed pursuant to a consent judgment (ground 5); and, in the alternative to ground 5, entering the consent judgment over AIG's objection (ground 6).
In oral submissions, Senior Counsel for AIG said the central issue on the appeal was whether an insured, who gives false information to an insurer which then denies indemnity based on that false information, may rely on the avoidance as a basis for not having to prove the insured's liability to the third-party claimant. AIG sought leave to amend the notice of appeal to raise this point (proposed ground 5C). AIG also raised a further five grounds, alleging that the primary judge erred in: failing to find that Mr Hanna was required to prove that he was liable to Mr Hasan and that he had failed to do so (proposed grounds 5A and 5B); finding that a managerial failure in respect to a defect in the scaffolding was Mr Hanna's responsibility (proposed ground 5D) and that it was highly likely that Mr Hasan would have secured a verdict against Mr Hanna (proposed ground 5E); and finding that the settlement was objectively reasonable (proposed ground 5F).
Mr Hanna resisted AIG's application for leave to rely on proposed ground 5C, submitting that the manner in which AIG now framed its challenge was not run below; and that to permit AIG to run it now would cause him prejudice.
The Court held (Mitchelmore JA, Payne JA and Griffiths AJA agreeing), dismissing the appeal:
As to the application for leave to amend the notice of appeal:
(1) Leave to rely on proposed ground 5C is refused: [56]. The point was not run below: [51]. There would be prejudice to Mr Hanna if AIG were permitted to raise the point on appeal because, if AIG had run the point at trial, Mr Hanna would have had an opportunity to lead evidence that was directed to the question of what was before or otherwise available to the insurer at the time that it avoided the Policy, that disproved his statement to AIG that he was not the builder: [55]-[56].
(2) Leave to rely on the other proposed grounds of appeal is granted: [57].
As to ground 5:
(3) On its proper construction, the scope of cl 5.00 in the Policy includes liability that has been determined by a bona fide compromise agreement: [64]. This is consistent with cl 10.01: [65].
Post Office v Norwich Union Fire Insurance Society Ltd [1967] 2 QB 363; Vero Insurance Ltd v Baycorp Advantage Ltd [2004] NSWCA 390; 23 ACLC 199; Weir Services Australia Pty Ltd v AXA Corporate Solutions Assurance [2018] NSWCA 100; 359 ALR 314 considered.
As to ground 6:
(4) The consent judgment that the primary judge entered did not unilaterally determine AIG's liability under the Policy for the sum that Mr Hanna was ordered to pay Mr Hasan. The settlement did not preclude AIG from contending that it was not liable under the Policy, on the construction of cl 5.00 on which it relied and/or because Mr Hanna had not proved that he was liable to Mr Hasan, or that the settlement was not objectively reasonable: [68].
James Hardie & Co Pty Ltd v Seltsam Pty Ltd (1998) 196 CLR 53; [1998] HCA 78 distinguished.
As to grounds 5A and 5B:
(5) Mr Hanna did not need to establish that he was liable to Mr Hasan in the manner that Mr Hasan alleged in the amended statement of claim; and the primary judge did not need to be satisfied that Mr Hanna was so liable. Rather, it was for Mr Hanna to show that the amount of the settlement was reasonable having regard to the relevant circumstances, which included the position in which Mr Hanna found himself and what he might have been held liable to pay if there had been a contest leading to a judgment or arbitral award: [72].
Weir Services Australia Pty Ltd v AXA Corporate Solutions Assurance [2017] NSWSC 259 applied; Vero Insurance Ltd v Baycorp Advantage Ltd [2004] NSWCA 390; 23 ACLC 199; Weir Services Australia Pty Ltd v AXA Corporate Solutions Assurance [2018] NSWCA 100; 359 ALR 314 considered; CGU Insurance Ltd v AMP Financial Planning Pty Ltd (2007) 235 CLR 1; [2007] HCA 36 distinguished.
As to grounds 2, 3, 4, 5D and 5E:
(6) These grounds mischaracterise the inquiry that the primary judge was undertaking. When understood as an inquiry into the reasonableness of the settlement, and not an inquiry into Mr Hanna's liability per se, the primary judge's approach was consistent with an inquiry into the circumstances at the time of Mr Hanna's entry into the settlement. The settlement was objectively reasonable for the reasons given by the primary judge: [78].
As to ground 5F:
(7) The ground was premised on Mr Hanna needing to prove that he was liable to Mr Hasan as alleged in the amended statement of claim, which was rejected: [80].