© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2019] NSWCA 270
Court of Appeal (NSW)
2019-10-17
Gleeson JA, White JA
Original judgment source is linked above.
Background facts
Relevant terms of the contractor agreement
Claim for unpaid invoices
The primary judge's reasons
Disposition of the appeal
First issue: whether Advanced had earned the contract price
Advanced's submissions
Daintree's submissions
Reasoning
Contracts requiring personal performance
Application of principles to the facts
Conclusion
Second issue: whether cl 4.5 excludes any accrued right of Advanced after termination of the agreement by Daintree
Conclusion and Orders
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 05 November 2019
Advanced National Services Pty Ltd
Daintree Contractors Pty Ltd
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.] HEADNOTE [This headnote is not to be read as part of the judgment] Advanced National Services Pty Ltd (Advanced) brought District Court proceedings against Daintree Contractors Pty Ltd (Daintree) claiming monies owed under a contract to perform commercial cleaning services or, alternatively, damages for breach of contract. It was accepted by both parties that approximately 90 per cent of the cleaning services were carried out by subcontractors. The primary judge found this to be a breach by Advanced of an express clause of the contract that prohibited it from assigning or subcontracting any portion of the contract without Daintree's prior written approval. Having noted that Advanced did not make any claim based on quantum meruit, the primary judge held that it was only entitled to payment of approximately 10 per cent of the liquidated sum it sought, representing the component of cleaning services that were performed by Advanced itself. Advanced appealed against that part of the District Court decision which rejected the balance of its liquidated claim. Daintree filed a notice of contention seeking to uphold the decision on grounds that did not entirely accord with the primary judge's reasoning. The principal issues raised were: Whether, as at the date of termination of the contract by Daintree, Advanced had performed the cleaning services such that it had 'earned' the whole of the liquidated sum it sought. If the first question was answered affirmatively, whether an express term of the contract affected an accrued right to receive the contract price after the valid termination of the contract by Daintree. Gleeson JA (White JA and Barrett AJA agreeing), dismissing the appeal with costs, held: Advanced was required by the express terms of the contract to undertake the cleaning services personally or through the use of an authorised subcontractor in order to discharge its performance obligations. Other terms of the contract, which placed great significance on the particular manner and conditions of performance and provided important protections for Daintree's benefit, supported that construction and would otherwise be set at naught if Advanced could discharge its performance obligations by the use of unauthorised subcontractors: [65]-[75], [87]. Australis Media Holdings Pty Ltd v Telstra Corporation Ltd; Australis Media Holdings Pty Ltd v News Corporation Ltd (1998) 43 NSWLR 104; Tolhurst v Associated Portland Cement Manufacturers [1903] AC 414; Bruce v Tyley (1916) 21 CLR 277; Davies v Collins [1945] 1 All ER 247, applied. As the first question was answered in the negative, it was unnecessary and inappropriate to address the second question which was hypothetical and also raised other issues which had not been raised at trial: [88]-[90]. Kuru v New South Wales (2008) 236 CLR 1; [2008] HCA 26, considered.
Judgment
[1933] HCA 25
[1985] HCA 28
[2015] HCA 37
(1998) 43 NSWLR 104
(1916) 21 CLR 277
(1982) 149 CLR 337
(2014) 251 CLR 640
(2008) 236 CLR 1
(1933) 48 CLR 457
(1985) 60 ALR 68
(2015) 256 CLR 104
(2019) 93 ALJR 582
(1936) 54 CLR 361
(1956) 99 CLR 560
(2004) 218 CLR 530
[2008] HCA 26