ADVANCE FLOORING CO PTY LTD v ARIEL STOLIAR
[2003] NSWSC 12
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2003-01-03
Before
Dowd J
Source
Original judgment source is linked above.
Judgment (6 paragraphs)
Background Facts 3. Advance Flooring Co Pty Ltd ("Advance") the defendant before the Local Court performed work for the defendant in these proceedings, Ariel Stoliar, in a newly constructed home unit in Drummoyne. Advance on 21 November 1996 offered to supply and install parquetry flooring, the work commencing in April 1997 and ceasing in June 1997 when the parties were in dispute. 4. Proceedings were commenced by Stoliar by way of statement of claim in the Local Court for $40,000.00. There was an amendment of the statement of claim to which a defence was filed and the matter proceeded to arbitration in November 1998 when there were further amendments. Stoliar on 6 July 1998 further amended the statement of claim and after amended grounds of defence were filed on 2 November 1999 the matter was heard by Barnett LCM. Judgment was delivered on 18 August 2000 and orders were made, after argument, as to costs. 5. The learned magistrate found for Stoliar in the sum of $7,390.15 and dismissed Advance's cross claim. His Worship further ordered that Advance pay Stoliar's costs which his Worship assessed at $24,244.20.
Facts of the Dispute 6. Stoliar owned a unit in a block of units he was developing and engaged Advance to lay parquetry flooring throughout the unit. Stoliar alleged in the proceedings that the flooring was defective and for this claim, claimed the sum which became the amount of the judgment. He further claimed a sum of $20,500.00 being forty one week's rent at $500.00 per week which the plaintiff said he was forced to expend because of the delay. He also claimed interest. There was a cross claim by Advance seeking payment of $1,674.20 from Stoliar being the balance of the contract price and wages for two employees and interest. 7. Advance's claim was based on the offer made to Stoliar of 21 November 1996, which Stoliar accepted, and the conditions of contract which accompanied that quote. There is a dispute between the parties as to when those conditions arrived but not that they were received by Stoliar some time prior to the commencement of work. 8. The work should have concluded about mid May. Stoliar took a very close personal interest in the work and described himself as "pedantic, fastidious". He expressed concern about the quality of work in progress and disputes occurred with Advance. 9. Advance contended that they were locked out of the job and, in fact, the work was not finished. There were clear problems with the flooring underneath as well as with quality of workmanship, it being conceded at the hearing in the defence case that there were some sixteen boxes of parquetry blocks that had to be replaced. The blocks were not of the appropriate grade and were not properly machined, causing gaps in the pattern and creating difficulty aligning the blocks. There were also disputes about cracks within blocks, the colour of blocks and the location of different colours adjoining. 10. There were disputes concerning the sub-floor and levels of undulation, the levelling and the question of the coating which it was given before the laying of the tiles. There was not issue between the parties that the slab on which the parquetry work was fitted had been laid to take carpet and that there had been some rain damage and levelling work in one corner. 11. An agreement had been made as to the preparation of the base of the parquetry but only six bags of the ten bags of base ordered were ever used on the floor by Advance's workmen. 12. A dispute arose in late June, Advance demanding payment of the balance owing under the contract notwithstanding that the work had not been completed, it being proposed that this money be held by the legal representative to ensure payment on completion. 13. Ms Leslie Wong, barrister for Stoliar, advised on 20 June that Advance should return to complete the work by 23 June. Advance faxed Ms Wong, stating: "Please advise your client that we refuse to carry out any further work after 12 pm Monday 23rd until such time our contract is signed and all outstanding monies are held by yourself". 14. Advance's case was that two employees turned up and were able to get onto the site but not into the unit in question.