Error in finding that fill extended to within 1 m of the boundary, proper construction of condition 19 and requirement for terracing across rear yard and the challenge to the amount awarded (Appeal Grounds 1, 2 and 3)
- The Tribunal's decision on this aspect of the case is found in paragraphs 132-157. At paragraphs 133-134 the Tribunal recorded the agreement of the experts in conclave, which we have set out above, that the fill was retained on site, that the contract drawings showed a graded site and landscaping with no terracing, that excavated soil was retained on site as terraces and that the cost of retaining those terraces would be $55,750.00.
- There was a dispute concerning who was responsible for placing the fill in terraces on the site. At paragraphs 140-142 the Tribunal resolved this dispute in favour of the respondent and found that excavated soil had been placed by the appellant, not a Mr Tokaji, who had apparently placed other "dirt" on site where the swimming pool was to be constructed. That finding was not challenged on appeal.
- The Tribunal also concluded at paragraph 139 that the contour plan attached to Mr Hickey's report "shows contours of the fill extending from boundary to boundary" and that "the contour plan shows fill at the rear of the residence that extends from boundary to boundary". That finding was challenged on appeal.
- Consequently, the Tribunal made the following findings at paragraph 143-145:
143 I find that the builder was contractually obliged to provide a retaining wall at the rear of the residence to retain the fill exiting (sic) there which extends to within one metre of the boundaries.
144 The builder has failed to discharge this contractual obligation and is therefore in breach of contract.
145 The owners will be entitled to an order in their favour in the agreed sum of $55,750.00 in connection with this item.
- The applicant challenges the conclusion concerning the proper construction of condition 19 and the award of $55,750.00.
- In relation to the issue concerning fill, the appellant says that the Member found that the "the contour plan shows fill at the rear of the residence which extends from boundary to boundary". However, the appellant says this was not the critical issue. Rather, the Tribunal was required to determine whether the placed fill extended to within one metre of the boundary. In this regard the appellant asserted that Mr Hickey's report provided no evidence in relation to this and there was no evidence to otherwise support the Tribunal's finding that fill extended to within one meter of the boundary.
- In relation to the award, the appellant says:
1. The amount does not represent the costs to bring the works done in breach of the contract into conformance with the contract provisions;
2. The work required under the contract was a grass slope that was not terraced;
3. The Tribunal should not have allowed the cost of retaining the terraced fill because that decision "has foist on the (Appellant) builder an obligation the builder did not assume as part of the contract".
- In our view, on a fair reading of the Tribunal's reasons, particularly paragraphs 136-143 inclusive, the Tribunal found:
1. that the appellant and not Mr Tokaji placed excavated material on what was an original gradually sloping site that was not terraced;
2. That the fill extended from boundary to boundary and was placed in terraces;
3. fill placed within one meter of the boundary was required to be supported by retaining walls by reason of condition 19 of the Development Consent; and
4. The failure to construct these retaining walls constituted a breach of the contractual obligation to comply with condition 19 of the Development Consent.
- The appellant submitted that there was no evidence to support the conclusion that fill had been placed within one metre of the boundaries.
- In our view, this submission must be rejected.
- Paragraph 6.38 of Mr Hickey's report records that fill had been in contravention of the approved plans and that there was a "significant amount of fill in this yard which had been shaped into large terraces". Mr Hickey also said that the fill which had been placed needed to be retained to prevent the fill "migrating towards the rear boundary". The placement of the fill is depicted on the contour plan shown on the right hand side of the two plans set out on page 74 of Mr Hickey's report: AB 156. It shows placement of fill right up to the boundaries depicted on the left side of the drawing and adjacent to the boundary on the top side of the drawing (approximately the north east boundary having regard to the orientation of the property as shown by reference to the site plan found at AB 288).
- There was no challenge to the finding on the appeal that the appellant was responsible for the placement of the fill. Further, it is evident from a comparison of the contour lines of the original site with the contour lines of the site after fill had been placed that there had been a substantial alteration of the contours of the site across its whole length right up until the boundaries: see drawings depicting "comparison contours" of the stamped plan (left side) and the existing terrace yard (right side) at AB 156. The photographs found at AB 157 and AB 158 depicting the terraces constructed by the placed fill support this fact.
- The respondent's expert, Mr Hanrahan, provided limited evidence in response. It would seem that the sole challenge to Mr Hickey's evidence in the opposing expert's report was that stabilisation of the fill which had been inappropriately placed in the backyard was not an appropriate method of rectification because such works were not otherwise required by the contract (which contemplated a relatively evenly sloping backyard from the proposed premises to the boundary on the north east side of the property).
- In our view, the evidence provided by Mr Hickey at paragraph 6.38 was sufficient to prove there was fill placed within one metre of the boundaries and the Tribunal was entitled to rely on this unchallenged evidence and make that finding of fact.
- Accordingly, the challenge to the Tribunal's decision on the basis that there was no evidence to support the conclusion that fill had been placed within one metre of the boundary must fail.
- In relation to the construction of the contract and condition 19 of the Development Consent, it is necessary to consider the provision of condition 19 which is in the following terms:
Excavations or fill extending to within one (1) metre of boundary or adjacent to an easement must be supported by retaining wall/s. Erection of retaining walls is not permitted within an easement.
REASON: To ensure that excavated areas are adequately retained.
- In our opinion, this condition is unambiguous in its terms. That is it requires that "excavated areas" (being areas of excavation or fill) are to be adequately retained.
- Condition 1(c)(i)(c) requires that any work done under the contract must comply with the conditions of any relevant development consent.
- Where a contractor constructs the works in a manner different to that detailed in the plans and specifications, the work is still done under the contract and is still required to meet the conditions of any relevant Development Consent, including in this case condition 19.
- The construction of the contract advanced by the appellant would mean that a builder could construct the works under the contract other than in accordance with the plans and specifications and thereby be relieved of any obligation to comply with the terms of the Development Consent. This is an illogical submission and should be rejected.
- Inter alia, such an interpretation would mean that non- conforming work that was subsequently accepted by a homeowner or was not required to be rectified would not need to comply with any relevant conditions of Development Consent.
- Further, there was no dispute on appeal that the appellant was responsible for carrying out the landscaping work. Consequently, to the extent that any landscaping in the rear of the yard had been altered by the appellant's work or affected by what the appellant had done, those works needed to be undertaken in a manner required by the Development Consent, including complying with condition 19 in the event there was excavation or fill works extending to within one metre of the boundary or adjacent to an easement.
- Accordingly, to the extent that retaining walls were required to retain fill extending to within one metre of the boundary or adjacent to an easement, in our opinion the Tribunal was correct to conclude that condition 19 obliged the appellant to support such excavation or fill material with retaining walls.
- It follows that this ground of appeal fails.
- The final ground of appeal on this issue relates to the award of $55,750.00 and the submission that this amount does not represent the costs to bring the works done by the appellant in breach of contract into conformance with the contract revisions.
- In this regard, the appellant relies upon the decisions of the High Court in Bellgrove v Eldridge (1954) 90 CLR 613.
- In our view this submission should be rejected.
- As indicated above, there was no dispute in this appeal that fill had been placed by the appellant in the rear yard and that this constituted a breach of contract. Further, it is clear from the evidence provided by Mr Hickey on behalf of the respondent that the material which had been placed in the backyard needed to be retained so as to prevent migration of the fill. There was no evidence to the contrary from the appellant's expert Mr Hanrahan.
- There was no evidence to suggest that an appropriate rectification method to maintain stability of the site was to remove the fill that had been placed in breach of contract and undertake any other necessary remedial work.
- The appellant offered no evidence concerning the nature and extent of the fill which it had placed in contravention of the contract and simply sought to argue that the claim for the costs of stabilising the site should be rejected because the placement of fill was not works originally contemplated by the contract. The appellant chose not to provide any evidence as to the costs that would have been incurred in removing the fill placed in breach of contract and carrying out any necessary remediation work so as to reinstate the site to its original state. The appellant provided no evidence that such a rectification method was possible or appropriate.
- There was agreement between the experts that a way to rectify the damage caused by the placement of the fill in terraces was to construct works to stabilise the terraces and that the amount to do so would be $55,750.00. As recorded in the Tribunal's reasons at [133], the hand written notes of a conclave held 15 October 2012 indicate the experts "agreed with the value of $55,750.00 to rectify". In this regard the experts have qualified this opinion by inserting the words before it "if found" and appear to have agreed that the works under the contract did not require terracing. However the experts do not otherwise suggest that if found that the fill has been placed by the appellant in terraces at the rear of the site and the appellant is responsible for that work that some other method of rectification to that proposed by the respondent's expert, Mr Hickey was appropriate.
- As the parties are well aware, the obligation of experts is to assist the Tribunal as required by the current Procedural Direction 3 - Expert Witnesses and the Expert Code of Conduct which previously applied to proceedings commenced in the Consumer, Trader and Tenancy Tribunal. The joint report records areas of agreement and disagreement.
- The only "disagreement" appears to be a legal question about whether or not a reasonable method of rectification of the appellant's breach of contract in placing fill in terraces within one metre of the boundary without adequate retention was to stabilise the existing site rather than remove the fill and restore the site to the state contemplated by the original plans and specifications.
- In the absence of any evidence to the contrary and in the absence of the experts providing an opinion that some other method was reasonable and appropriate to rectify the damage caused by the appellant by reason of placement of fill material in terraces, in our view there is no basis to conclude that the Tribunal was in error awarding $55,750.00 as the reasonable cost to rectify the damage which had been caused by the appellant. Further, to the extent the terraces were to be retained, no error is shown by including in awarding an amount for the cost of constructing any necessary retaining walls as required by condition 19 of the Development Consent.
- Accordingly, this ground of appeal also fails.
- It follows that in so far as these grounds of appeal require leave that leave should be refused as it is not shown the appellant may have suffered a substantial miscarriage of justice.