© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2013] FCAFC 46
Federal Court of Australia (Full Court)
2013-05-16
Gilmour JJ, North J
Original judgment source is linked above.
Background facts 137 The following background facts form part of the relevant context to a greater or lesser degree. They are not controversial and are largely taken from the reasons of the primary judge. 138 In October 2005, M&C entered into an agreement with Aztec Resources to provide engineering services to assist in the development of a proposed iron ore offloading wharf at Koolan Island, off the coast of Western Australia, by providing engineering consultancy services. Mr Julian van der Meer, an employee of M&C, was the project manager for the Koolan Island wharf project. Other employees of M&C who worked on the project at the relevant time were Mr Alan Sweet, the contracts manager, Mr Steve Seclier, a piling foreman/supervisor, and Mr Patrick Quinlan, a project engineer. 139 One of the tasks which M&C was required to perform pursuant to its contract with Aztec Resources, was to arrange for the transport of a crane loaded on a barge, from Dampier, Western Australia, to Koolan Island. The crane and the barge were to be used in the construction of the iron ore offloading wharf at Koolan Island. 140 M&C decided to obtain advice from International Maritime Consultants Pty Ltd (IMC) in relation to the measures to be taken to ensure the stability of the barge and crane for the voyage from Dampier to Koolan Island and the undertaking of the piling works intended to be carried out at Koolan Island. 141 On 20 January 2006, Mr van der Meer and Mr Seclier met with Mr Robert Williams and Mr Tiju Augustine, who were employed by IMC. During the course of the meeting, Mr van der Meer said words to the effect that M&C was thinking of towing the barge with the crane onboard from Dampier to Koolan Island and that as M&C did not have a means of assembling the crane at Koolan Island, it would need to be towed with the boom assembled so that it would be ready for use when it arrived. Mr van der Meer then asked whether IMC could undertake the design for the sea-fastenings of the onboard equipment and the crane, and prepare a towing plan and undertake a barge stability analysis. Mr Williams, on behalf of IMC, replied that IMC could meet the requirements of M&C. 142 Mr van der Meer sent a facsimile to Mr Williams dated 20 January 2006, in the following terms: We are planning to mobilise the barge to Koolan Island in the following sequence: 1. Take delivery of barge from mooring in Dampier around mid February. 2. Assemble 250T Sumitomo Crawler Crane onto barge in Dampier. Note that the crane will need to be fully assembled for mobilisation to Koolan Island, which will require the fabrication of a boom rest. Note that the boom length will be 67.05m. 3. Tow barge to Port Hedland for completion of equipment installation. 4. Tow barge to Koolan Island, where the storm mooring will be installed, and piling operations will commence. Also attached is the specification for the tug that will be chartered for the duration of the works. Structural drawings and stability books for the two other construction barges will follow in the coming week. Please advise us of your fee for the above works and invoice quoting the number on the attached purchase order. 143 On 2 February 2006, Mr Augustine sent M&C a stability analysis in respect of the barge and crane. This analysis dealt with the proposed towing configuration and the piling configuration. In respect of the towing configuration, the analysis was made on the assumption that the boom of the crane would be held in position by a boom rest which would be located on the barge, and would support the boom at mid-span. 144 On 2 March 2006, Mr Augustine sent Mr van der Meer an email suggesting that advice be obtained from the manufacturer of the crane about the capacity of the crane to withstand bending movement during the transportation because this would determine the boom cradle position and arrangement. Mr van der Meer then contacted Mr John Buntain of Tutt Bryant Crane Hire (Tutt Bryant), the company from which M&C intended to hire the crane, and asked him whether the crane boom could be supported mid-span. Mr Buntain advised shortly thereafter, that the boom could only be supported at the butt and the head and was not designed to be supported anywhere else. 145 Mr van der Meer then relayed the content of his conversation with Mr Buntain to Mr Augustine. Mr van der Meer said to Mr Augustine: Perhaps we should simply lash the boom back with soft slings on either side, as suggested by John, so that the boom will be self-supporting but the slings will restrain it from moving laterally. 146 Mr Augustine then said that he would "have a look at that". 147 On 7 March 2006, there was a meeting between Mr Seclier and Mr van der Meer on behalf of M&C and Mr Williams and Mr Augustine on behalf of IMC. Nothing was said at that meeting to suggest that the advice from Tutt Bryant would cause a problem with the manner in which the crane was to be transported, or that the crane could not be transported safely in an assembled form. 148 On 8 March 2006, Mr Augustine sent Mr Seclier an email which attached the drawings for the sea-fastenings for the base of the crane. Importantly, these drawings did not contain any drawing of sea-fastenings for the boom of the crane. 149 At around this time, Mr Neil Brown, an insurance broker from Gault Armstrong Kemble Pty Ltd (GAK), insurance brokers, advised Mr Sweet that a warranty survey report would be needed as a condition for insurance cover. Mr Brown said that a report from SGS would be acceptable. 150 Accordingly, Mr Sweet sent an email to Mr Christopher James Tickner, the operations coordinator of SGS in Perth. The email dated 20 March 2006, read: Subject: Warranty Survey for Koolan Island Project As discussed last week Marine and Civil are constructing the iron ore offloading berth at Koolan Island. We require [a] maritime survey to be completed for onhire/offhire reports and warranty survey for towing purposes for tugs and crane barges mobilised from the following locations; Dampier Port Hedland Fremantle Koolan Island (off Derby) Could you please advise contact details and fee structures for SGS that would be suitable to allow these works to be organised. 151 Later that day, Mr Tickner sent an email in response to Mr Sweet's email. The email stated: Thanks for your inquiry and we are pleased to offer you our following rates and information. For Onhire / Offhire reports: 1) Dampier - AU$1200.00 + AU$0.70 / km 2) Port Hedland - AU$1200.00 + AU$0.70 / km (would be serviced from Dampier) 3) Fremantle - AU$700.00 4) Koolan Island (off Derby) - AU$1500.00 + Airfares, Accommodation, Meals, Vehicle Hire = At cost + 15% (would be serviced from Perth) Warranty Surveys are only conducted by the Classification Society however we are able to provide you with a survey report. This is a report of our findings at time and place of intervention but I must stipulate is not a Certificate of Seaworthiness for towing. All work conducted is in accordance with SGS General Conditions of Service which I have attached for your reference. Captain Leo Rego is our Shipping Manager and his contact details are as follows: … Please do not hesitate to contact myself or Leo to discuss further. 152 On 28 March 2006, Mr Augustine sent Mr Seclier an email enclosing a document entitled "Towing Arrangement". The document contained towing resistance calculations but did not address the sea-fastening arrangements for the boom of the crane. 153 On 10 April 2006, Mr van der Meer had a telephone conversation with Mr Russell Parker from Tutt Bryant. Mr Parker told Mr van der Meer: When tying the boom back, soft slings must be used as there are fine tolerances on allowable damage to the boom. The boom must be restrained in two directions with equal tension on either side of the boom. 154 Mr van der Meer relayed this conversation to Mr Seclier. However, Mr van der Meer did not relay this information to IMC. 155 By email dated 11 April 2006, Mr Augustine forwarded to Mr van der Meer, the document referred to as "the towing plan" for the barge. This document did not reflect any sea-fastening arrangements in respect of the boom of the crane. 156 On 12 April 2006, the crane was delivered in pieces to the Dampier site by Tutt Bryant. During the period 13 April 2006 to 16 April 2006, Mr Seclier, who was in Dampier, supervised the assembly of the crane. Mr Seclier, also, oversaw the welding operations of the sea-fastenings on to the barge and the tie down. Mr Seclier followed the drawings prepared by IMC for the sea-fastenings for the base of the crane to the deck of the barge, which did not include any sea-fastenings for the securing of the boom of the crane to the barge. Otherwise, Mr Seclier used the lashings he deemed appropriate. Photographs were taken of the sea-fastenings which had been effected by Mr Seclier and sent to Mr Quinlan. The photographs were then used by Mr Quinlan, subsequently, when he prepared his "Tie-Down Works Methodology" document, to which I will refer later in these reasons. 157 On 19 April 2006, there was a meeting of employees of M&C. Mr van der Meer was present. Notes were kept of the meeting which included the following notation: 1. Mobilisation … Piling barge: - in Dampier, due to leave 24/4 (Mon),
M&C's misleading or deceptive conduct claim 184 In the final iteration of its statement of claim, M&C alleged that in providing the survey report, SGS had engaged in misleading or deceptive conduct in contravention of s 52 of the Act. 185 M&C pleaded at para 4 of the statement of claim, that on 20 April 2006, it retained SGS to provide a survey report on sea-fastenings for the barge with the crane "which report was expressed to be required prior to a proposed sea voyage of the Miclyn 131 under tow from Dampier to Koolan Island and to be required for insurance before cover was accepted for tow" (original emphasis). 186 M&C then pleaded that the written report was sent by SGS to Mr Sweet by an email on 28 April 2006 and that by the report SGS represented to M&C that: (a) A marine surveyor…had attended aboard the loaded barge to inspect the arrangements for towing bridle and sea fastenings; (b) The Crane and boom were secured on deck with straps and eye pads and plates welded onto the deck; (c) The sea fastenings were checked and appeared to be satisfactory. 187 M&C then pleaded in para 7 of the statement of claim, that the sea-fastenings did not appear to be satisfactory, and the arrangements for securing the boom of the crane and the proposed method of transporting the crane by barge with its boom assembled and erected were not safe, satisfactory or suitable arrangements for transporting the crane and its boom from Dampier to Koolan Island, because: (a) The boom was secured to the barge on each of the port and starboard sides by a single part 11 mm wire and eyelet, a tensioner and metal hook, all with a safe working load of no greater than 1.6 tonnes, which the sea fastenings were grossly inadequate for and would not have survived the proposed tow of a 250 tonne Crane with its boom extended; (b) The boom required, but did not have, on each of the port and starboard sides high tensile chains and high tensile securing components that secured the boom to the barge; (c) And/or alternatively: (i) The Crane with its boom fully assembled and extended could not be transported from Dampier to Koolan Island on a barge towed by a tug without significant risk of damage from the forces that may result from the wind and wave conditions that occurred in that area; and (ii) The safe method of transporting the Crane and boom by ocean going vessel entailed dismantling the boom and transporting it in pieces. 188 M&C went on to plead, in para 8 of the statement of claim, that SGS did not tell it of the matters pleaded in para 7 of the statement of claim. 189 It was then pleaded in para 9 of the statement of claim, that by reason of its conduct as pleaded, SGS, in trade or commerce: (a) Expressly represented that the sea fastenings appeared satisfactory and were satisfactory; (b) Impliedly represented that there were no matters the subject of the survey that required further investigation before the proposed sea voyage from Dampier to Koolan Island; (c) Impliedly represented that in relation to the sea fastenings of the boom there was no significant risk of damage occurring on the sea voyage. 190 The primary judge found that the author of the survey report did not make an express unqualified statement that the sea-fastenings appeared to be satisfactory and were satisfactory but rather, qualified the statement as to the sea-fastenings by stating that they were inspected with the barge in a static condition and, in that condition, the sea-fastenings appeared to be satisfactory. Also, his Honour found that the statement was further qualified by the reference to the fact that SGS had not been provided with test certificates of the lashing material. 191 As the primary judge found, it is apparent from the matters pleaded in para 7 of the statement of claim in falsification of the representation, that M&C contended that the SGS representation was false because the sea-fastenings were not satisfactory for transporting the crane and its boom from Dampier to Koolan Island. However, his Honour found that the express language used by SGS did not make an express representation that stated that the sea-fastenings were satisfactory for transporting the crane and its boom from Dampier to Koolan Island. 192 However, M&C submit that these supposed qualifications did not detract from what was represented. 193 As to the first qualification, it submits that the sea-fastenings were necessarily checked with the barge in static condition because the barge was not under tow at the time of the inspection. It contends that the statement that the sea-fastenings "appeared to be satisfactory" in that condition raises the question: satisfactory for what? Given that SGS was expressly retained to prepare an "independent survey report that verifies towing bridle and sea-fastenings" that was "required prior to towing the Miclyn 131 Piling Barge from Dampier to Koolan Island", this, M&C submits, must mean satisfactory for that voyage. It argues that SGS cannot have intended to convey to M&C that the sea-fastenings were satisfactory for the purpose of the barge remaining in its then position, because SGS well knew that the voyage was imminent and that its report was required for the purpose of M&C obtaining insurance cover for the voyage. 194 Moreover, it submits that the statement in the survey report concerning the absence of test certificates did not qualify the representations as to the adequacy of the sea-fastenings in any meaningful way. Its argument goes this way. Mr Sweet's evidence was that SGS did not request test certificates for the lashing material prior to issuing the report. If the express statement that the sea-fastenings appeared to be satisfactory was subject to a proviso that SGS could not say whether or not they were satisfactory without reviewing test certificates for the lashing material, one would expect that to be clearly stated in the report. It was not. It is clear from Captain Hughes' unchallenged evidence that the inadequacy of the wires for the purpose of securing the crane boom to the barge would have been obvious to an experienced marine surveyor without test certificates. The safe working load (or SWL) of the steel wires could be calculated without test certificates, and it would have been obvious to an experienced marine surveyor in any event that wires of substantially higher gauge, more wires or chains were required. In addition, the tensioners were stamped with a 1.6 tonne SWL. That set the maximum SWL for the entirety of each lashing, and was obviously inadequate for the weight of the crane boom. It was the hooks which formed part of the tensioners that failed. 195 The primary judge was correct to find that the express representation alleged was not established. His Honour's reasoning referrable to the two qualifications contained in the survey report was apt. 196 The survey report was not commissioned nor provided, according to the terms of the retainer and the survey report itself, to give M&C advice as to the sufficiency of the sea-fastenings for a sea voyage. Captain Hughes' evidence does not alter this fact. I will return to this when considering the alleged implied representation. 197 It is evident from M&C's submissions, and from the rhetorical questions posed, that it necessarily looks beyond the express language used to the context in which the survey report was commissioned and provided. This approach, as I have mentioned, is orthodoxy in this area and was the approach adopted by the primary judge. This leads to a consideration of the asserted implied representation. 198 In order to challenge the finding of the primary judge concerning the representations, the appellant must demonstrate that the words used in the report conveyed the representations as alleged when considered in the context of all the circumstances. 199 The primary judge referred to Butcher v Lachlan Elder Realty Pty Limited (2004) 218 CLR 592, in which Gleeson CJ, Hayne and Heydon JJ stated at [37]: The plaintiff must establish a causal link between the impugned conduct and the loss that is claimed. That depends on analysing the conduct of the defendant in relation to that plaintiff alone. So here, it is necessary to consider the character of the particular conduct of the particular agent in relation to the particular purchasers, bearing in mind what matters of fact each knew about the other as a result of the nature of their dealings and the conversations between them, or which each may be taken to have known. and McHugh J observed at [109]: The question whether conduct is misleading or deceptive or is likely to mislead or deceive is a question of fact. In determining whether a contravention of s 52 has occurred, the task of the court is to examine the relevant course of conduct as a whole. It is determined by reference to the alleged conduct in the light of the relevant surrounding facts and circumstances. It is an objective question that the court must determine for itself. (Footnote omitted.) 200 At trial, M&C had contended, in particular, that by providing the SGS survey report in the context of the pleaded retainer, SGS made the implied representations pleaded. In support of its contention, M&C referred to the two last dot points of the email sent by Mr Sweet to Captain Bhalla on 20 April 2006, and placed particular emphasis on the fact that the email had stated that "[i]nsurance requires an independent report prior to accepting cover for the coastal tow". M&C had contended that the reference to insurance for a coastal tow implied that an opinion was sought in respect of a "dynamic" event, namely, the tow from Dampier to Koolan Island. 201 SGS denied that it made the implied representations pleaded by M&C. SGS relied particularly on the terms of its survey report, and also, as part of the surrounding circumstances, on the email exchange between Mr Sweet and Mr Tickner on 20 March 2006. This clearly stated that SGS would not be providing a "warranty survey for towing purposes" but only a "survey report" which it said was "a report of our findings at time and place of intervention" and further stipulated that it was "not a Certificate of Seaworthiness for towing". 202 As to the meaning of a "warranty survey", Captain Hughes had agreed with a statement, which had been made in an expert report by Captain Douglas, that a warranty survey was a survey of guaranteed quality that was frequently used by marine insurers. Captain Hughes also accepted, in cross-examination, that a warranty survey would not refer to the state of the vessel in a "static" condition. 203 The primary judge, correctly in my view, found that an important qualification to the survey report was the express statement in it that the surveyor attended onboard the barge to inspect the "Arrangement of Towing bridle and Seafastenings (design and certification by International Maritime Consultants)". In the penultimate paragraph of the report, the writer refers to the report as expressing "our opinion of the Arrangement of Towing bridle and Seafastenings (design and certification by International Maritime Consultants)". The reference in two separate places to the fact of the sea-fastenings having been designed and certified by IMC was, as the primary judge correctly observed, significant. This is because, as his Honour reasoned, it is an indication that the surveyor was not taking responsibility for the suitability of the independent consultant's design and certification of the sea-fastenings for the conduct of the tow. His Honour, in my opinion, was correct to so find. Further, M&C did not provide Captain Sharma with any drawings of the sea-fastenings. These qualifications were entirely consistent with the limited nature of the survey report as described in the 20 March email from SGS to M&C. 204 The second qualification as found by the primary judge was that the survey report stated specifically that the sea-fastenings were checked in "static condition" and, in that condition, the fastenings "appeared to be satisfactory". The report emphasised this limitation on its opinion by stating expressly: "Please note that we were not provided with test certificates in respect of the lashing material". Indeed, it seems to me, that the author was stating that, unlike the towing bridles, he had not been able to confirm the sea-fastenings conformed to the test certificates. In other words, he was stating that because he did not have the certificates he could not "verify" the sea-fastenings. The words "appeared to be satisfactory" require to be considered in that context. Most importantly, this phrase was not referrable to the seaworthiness of the sea-fastenings. 205 Importantly, as the primary judge noted, Mr Sweet, during cross-examination, accepted that at the time of sending the email of 20 April 2006, he was conscious of the limitations on the nature of the report which SGS was prepared to provide, referred to by Mr Tickner in his email of 20 March 2006. During cross-examination, Mr Sweet said: So what you understood from that email that they were equipped to provide was on hire off hire reports; correct?---Yes. And a report of findings at the time and place of intervention?---I read it that they could provide a survey report but they wouldn't be providing a warranty - warranty survey. Yes, and they could provide a survey report which was a report of findings at the time and place of intervention?---Yes. And would not be a certificate for seaworthiness for towing?---Yes. 206 Further, Mr Sweet was cross-examined about the language he used in his email to SGS on 20 April 2006 as follows: Now, the fact that you didn't refer to "warranty survey" or "certificate" in that email was quite deliberate, wasn't it?---That's correct. Because you knew that all that you had been told by SGS in the email of 20 March 2006 was that they could provide "a report of our findings at the time and place of intervention, but I must stipulate it's not a certificate of seaworthiness for towing"?---That's correct. I knew SGS were not giving a warranty survey, that they were doing a survey before towing. No. You knew that what they had told you they could do was "a report of our findings at time and place of intervention which would not be a certificate of seaworthiness for towing"?---Correct. I acknowledge that. 207 The primary judge correctly concluded that there was an influential relationship between the email correspondence of 20 March 2006 and the later email correspondence between SGS and M&C on 20 April 2006, and, in particular, in concluding that the earlier correspondence should be taken into account in assessing Mr Sweet's knowledge in relation to the question of whether SGS made the implied representations alleged. 208 Moreover, Mr Sweet gave the following evidence: And the communications that you had back from the insurer, referred to "Please forward certificate" report/certificate?---Yes, that's correct. I read that as the SGS report. But you agree with me that obtaining a towage tow worthiness certificate from SGS, was something that as from 20 March 2006, you knew you couldn't get from SGS?---Correct, yes, not a warranty. As I said before, I thought that the certificate was part of the warranty survey. Yes. The point is whether it's a warranty survey or a separate certificate or whether the certificate is part of it, neither of those you knew you could get from SGS?---That's correct. 209 Further, the following exchange occurred with Mr Sweet: Well, it says "In that condition." It does not say, "We checked within static condition and they appeared satisfactory for the tow," did it?---It doesn't say that, no, but - - - And you knew from what you had been told before that they wouldn't provide a certificate as to the satisfactory nature for the purposes of a tow?---That's correct. They weren't doing a towage certificate. You were the only one, I want to suggest, that knew that that was the limitation that they had already indicated to you, because you were the only recipient of that email of 20 March 2006?---You have established that before, but as I said, I believe I discussed it with the insurer but I can't explain it more than I already have. 210 There was ample evidence, therefore, to support the finding of the primary judge that from 20 March 2006, Mr Sweet, on behalf of M&C, knew from Mr Tickner's email that any survey report which would be provided by SGS would be confined to expressing an opinion as to the surveyor's "findings at time and place of intervention" and would not provide a report which certified suitability of the loaded barge and the sea-fastenings to undertake the proposed tow from Dampier to Koolan Island. 211 M&C, in support of its contention that SGS had made the implied representations, placed considerable emphasis on the fact that Mr Sweet's email of 20 April 2006, stated that "[i]nsurance" required an independent report before accepting cover for the coastal tow. The question is what each party knew, or is to be taken to have known, about each other, in relation to this matter. The primary judge was correct to reject Captain Hughes' evidence on this matter because his opinion did not take account of the impact of Mr Tickner's email. 212 As the primary judge correctly found, SGS would, after 20 March 2006, have known, or at least must be taken to have known, that Mr Tickner had advised Mr Sweet that SGS would only be prepared to provide a survey report that reported on their findings at the time and place of intervention, and would not provide a report certifying the seaworthiness of the loaded barge for the tow. SGS was entitled to think, as the primary judge held, that its retainer to provide the report was subject to the conditions previously stated by Mr Tickner. SGS would also be taken, therefore, to have regarded Mr Sweet's reference to the need for the report for insurance purposes, as being consistent with the previously stated limitations on the nature of the survey report which it was prepared to provide. SGS would be taken to have concluded that Mr Sweet had made the limitations known to M&C's insurance brokers and the insurance brokers were content for a survey report of limited scope to be provided. 213 Mr Sweet was aware of the terms of the email from Mr Tickner and accepted in his evidence that he knew that SGS was only prepared to report on the state of the loaded barge at the time of its intervention, and was not prepared to provide a report which certified the suitability of the loaded barge to undertake the voyage from Dampier to Koolan Island. 214 The primary judge, in these circumstances, was correct in concluding that the failure of SGS to refer to the matters in para 7 of the statement of claim was not to be taken as an element of conduct giving rise to the implied representations pleaded. Accordingly, there was a clear foundation in the evidence for the primary judge to find as he did that having regard to the qualified nature of the language used in the survey report, and having regard to what each of the parties knew, or is to be taken to have known about the other party, and applying an objective test, that SGS did not make the implied representations pleaded by M&C. 215 M&C submits that SGS accepted an appointment to provide an independent report verifying the sea-fastenings prior to the voyage. It then submits that in that context, it does not follow from the fact that SGS believed the sea-fastenings had been designed by a third party that it made no implied representation that the sea-fastenings did not require further investigation prior to the voyage. It poses the rhetorical questions: What was SGS verifying? What were they inspecting and in what sense were they doing so independently? What value was SGS adding for the $1,000 fee charged to M&C? 216 The answer to these rhetorical questions is, as was found by the primary judge, that SGS's retainer was to inspect and to report as to their findings: what was on board in a static condition, and particularly relevantly, whether the towing bridles and sea-fasteners were in position and conformed to IMC's specifications. The bridles and sea-fasteners might, for example, have not been present at the time of the inspection by SGS. SGS was not, as M&C well knew, and as the primary judge found, taking any responsibility for the suitability of the design and certification of the sea-fastenings for the conduct of the tow. Indeed, it was M&C's insurers, not M&C, who required an inspection by SGS, and ultimately expressed the requirement of the survey by SGS as concerning "[l]ashing/stowage of cargo to comply with project engineers recommendations". This, of itself, provides utility to the survey report and is a further answer to the rhetorical questions. Mr Sweet of M&C understood the reference to project engineers specifications by the insurers to be a reference to IMC. This is entirely consistent with the terms of the SGS retainer considered in context. The scope of services provided by M&C to SGS expressly referred to the fact that design and certification of the sea-fastenings, and therefore their suitability for the voyage, was to be by IMC. M&C had taken detailed advice from IMC about the design and suitability of the sea-fastenings that were required for the voyage. M&C dealt in detail with IMC about whether the lashings that were in place on the barge conformed to IMC's advice and SGS was not involved in that process. Further, M&C had taken its own steps with IMC to make sure IMC was happy with what had been done. M&C itself did not need verification. 217 As it happens, SGS could report nothing about whether the sea-fastenings conformed to the IMC's specifications. M&C seeks to place an interpretation on the expression in the 20 April 2006 email from Mr Sweet to Captain Bhalla of SGS "… an independent survey report that verifies … sea fastenings (design and certification by (IMC) …" as though SGS were to express an opinion as to the suitability and reliability of the design and materials employed in the sea-fastenings. It was quite evident, as the primary judge correctly held, that this was not the case. 218 The evidence of marine surveyor Captain Hughes, that the boom restraints were "manifestly inadequate" and "would have failed as soon as the barge experienced open ocean conditions, even in the lightest of weather conditions" does not alter this conclusion. The SGS retainer specifically excluded the provision of the kind of opinion Captain Hughes proffered. The content of the survey report necessarily requires to be considered in that light as was the approach of the primary judge. The M&C effectively seeks to avoid the fact that the report emphasises that its findings as to the sea-fastenings were in a "static condition". It asks again, rhetorically: what would be the point of that given that the barge was to embark on a sea voyage? Actually, the converse is the case. It is the inclusion of the expression "static condition" that points up that it is not representing anything about suitability for a sea voyage. As SGS submits, and I accept, a person providing advice as to the suitability of the lashings for a voyage would not qualify the statement that they appeared to be satisfactory by reference to the static condition of the barge. The qualification is fundamentally inconsistent with any such representation. Further, the notation about not having the certificates following what was said in relation to the towing bridle is consistent with providing a report limited to what could be seen and whether it conformed to IMC's design. Consideration of other matters referred to in the report is also consistent with this character. For example, the survey report concluded by following the terms of the scope of services provided by M&C. It stated "This report is submitted in good faith and constitutes our opinion of the Arrangement of Towing bridle and Sea fastenings (design and certification by International Maritime Consultants). The surveyor assumes no responsibility for any defects and is to be held harmless for conditions subsequently arising". This qualification shows that the survey report was confined to the terms of engagement which was to provide an inspection not a warranty survey. 219 Nor is it to the point to consider what a reasonable person with experience in the maritime industry or even a reasonable marine surveyor with such experience would have considered was meant by what had been stated in the survey report. Such evidence is of little value when the contextual material, necessary to understand what if any representations were made, would not be known by such a person. To the extent that the primary judge held a view concerning the first of these hypothetical persons does not detract from his conclusions otherwise well-founded. As for M&C, it submits that the evidence was irrelevant. I accept that submission. 220 The appellant has failed to establish that the findings of the primary judge as to the alleged representations were erroneous. To the contrary, the evidence well supports his conclusion that the respondent did not engage in misleading or deceptive conduct. 221 I would dismiss the appeal with costs. I certify that the preceding ninety six (96) numbered paragraphs are a true copy of the Reasons for Judgment herein of the Honourable Justice Gilmour.
ACN 055 378 240 Pty Ltd (formerly Marine & Civil Construction Company Pty Ltd)
SGS Australia Pty Ltd
Implied Representations 44 After again identifying the alleged implied misrepresentations, the primary judge referred to a passage in the judgment of French CJ and Kiefel J in Miller & Associates Insurance Broking Pty Ltd v BMW Australia Finance Limited (2010) 241 CLR 357 at [5]; [2010] HCA 31 at [5], which included: Where silence or non-disclosure is relied upon, the pleading should identify whether it is alleged of itself to be, in the circumstances of the case, misleading or deceptive conduct or whether it is an element of conduct, including other acts or omissions, said to be misleading or deceptive. 45 His Honour then observed that M&C relied on the surrounding circumstances referred to in [4] and [6] of the statement of claim, and said that this conduct: must be assessed objectively by reference to the conduct as a whole in light of the relevant surrounding circumstances. 46 The primary judge relied on the approach taken in Butcher v Lachlan Elder Realty Pty Limited (2004) 218 CLR 592 (Butcher), described in the judgment of McHugh J at [109] as follows: The question whether conduct is misleading or deceptive or is likely to mislead or deceive is a question of fact. In determining whether a contravention of s 52 has occurred, the task of the court is to examine the relevant course of conduct as a whole. It is determined by reference to the alleged conduct in the light of the relevant surrounding facts and circumstances. It is an objective question that the court must determine for itself. (Footnote omitted.) 47 The primary judge explained that M&C relied particularly on the following part of the M&C April email: • Insurance requires an independent report prior to accepting cover for the coastal tow. • SGS scope of services to provide an independent survey report that verifies towing bridle and seafastenings (design and certification by International Maritime Consultants) prior to departure. My collegue [sic] Mr Julian Van der Meer will send copies of the tow plan and the approved seafastenings by seperate [sic] e-mail. The vessel details and towing winch are to be verified by the operator (Mermaid). 48 M&C emphasised that the insurance was sought for a coastal tow and that suggested that the opinion was sought in respect of a dynamic event, namely the tow from Dampier to Koolan Island. 49 The primary judge then said that SGS denied the implied representations and relied on the terms of the report and on the SGS March email. 50 His Honour next explained why he found that SGS did not make the implied representations. 51 The report did not purport to express an opinion about the fitness of the loaded barge or the sea fastening for the purpose of undertaking the tow from Dampier to Koolan Island because the report was qualified in two respects. First, the report stated that the surveyor attended onboard to inspect the "Arrangement of Towing bridle and Seafastenings (design and certification by International Maritime Consultants)". The same expression was used near the end of the report to explain the nature of the opinion being expressed. The primary judge said at [117]: The reference in two separate places to the fact of the sea fastenings having been designed and certified by IMC is significant. This is because it is an indication that the surveyor was not taking responsibility for the suitability of the independent consultant's design and certification of the sea fastenings for the conduct of the tow. Further, Marine & Civil did not provide Captain Sharma with any drawings of the sea fastenings. 52 The second qualification of the report was that the sea fastenings were checked in "static condition", and in that condition, the sea fastenings appeared to be satisfactory. The limitation was emphasised by the notation: "Please note that we were not provided with test certificates in respect of the lashing material". 53 His Honour then accepted the evidence of Captain Hughes that a reasonable person in the maritime industry would not have relied on the report as a basis for being satisfied that the crane was appropriately secured for the voyage. The primary judge did not accept the evidence of Captain Hughes that his view was inapplicable to M&C because M&C lacked the necessary experience in such matters. His Honour rejected a distinction sought to be made between experience in the maritime industry and experience, which M&C had, in marine construction. He found that the opinion adopted by Captain Hughes addressed the question of how a reasonable client who had commissioned a marine surveyor to provide a report in respect of a proposed tow of a loaded barge would have understood the report. His Honour explained: 122 … the relevant participants are marine surveyors and their clients who are organising sea going voyages and tows, and require a survey report. Mr Sweet accepted in cross-examination that Marine & Civil was experienced in organising charters, tows and surveys, and it was commonplace for Marine & Civil to receive and read documents related to these activities. 123 I find, on that basis, that Marine & Civil was not inexperienced in dealing with marine surveyors in relation to the procuring of survey reports for proposed charters or tows. Further, Mr Sweet deposed during cross-examination, that he had dealt with and obtained survey warranties from at least two other marine surveyors. It follows that I do not accept Captain Hughes' evidence that his opinion expressed…above, did not apply to Marine & Civil because it was not experienced in the maritime industry. 54 The primary judge then addressed M&C's contention that SGS made the implied representations by not mentioning the risks attending the voyage in the context of the relevant surrounding circumstances. 55 SGS particularly relied on the SGS March email which included the following: Warranty Surveys are only conducted by the Classification Society however we are able to provide you with a survey report. This is a report of our findings at time and place of intervention but I must stipulate is not a Certificate of Seaworthiness for towing. 56 M&C argued that in assessing what M&C knew or should be taken to have known from previous dealings with SGS, the inquiry should be confined to the M&C April email, and should leave out of account the SGS March email. His Honour rejected that argument. 57 Not only was there reference in the M&C April email to matters dealt with in the SGS March email, but Mr Sweet, in cross-examination, accepted that he knew of the limitations of the nature of the report SGS was prepared to provide. His Honour referred to two passages from the cross-examination of Mr Sweet as follows: So what you understood from that email [the SGS March email] that they were equipped to provide was on hire off hire reports; correct?---Yes. And a report of findings at the time and place of intervention?---I read it that they could provide a survey report but they wouldn't be providing a warranty - warranty survey. Yes, and they could provide a survey report which was a report of findings at the time and place of intervention?---Yes. And would not be a certificate for seaworthiness for towing?---Yes. … Now, the fact that you didn't refer to "warranty survey" or "certificate" in that email [the M&C April email] was quite deliberate, wasn't it?---That's correct. Because you knew that all that you had been told by SGS in the email of 20 March 2006 [SGS March email] was that they could provide "a report of our findings at the time and place of intervention, but I must stipulate it's not a certificate of seaworthiness for towing"?---That's correct. I knew SGS were not giving a warranty survey, that they were doing a survey before towing. No. You knew that what they had told you they could do was "a report of our findings at time and place of intervention which would not be a certificate of seaworthiness for towing"?---Correct. I acknowledge that. 58 The primary judge therefore found that the SGS March email should be taken into account in assessing Mr Sweet's knowledge in relation to whether SGS made the implied representations. 59 In taking into account the SGS March email, the primary judge considered an argument advanced by M&C concerning the use of the term "Certificate of Seaworthiness" in the email. M&C contended that, although the phrase was capitalised, there was no evidence that it was used as a term of art. Hence, there was no basis on which the expression should be viewed as being used in contrast to the expression "survey report" and, consequently, should not be treated as an indication that SGS indicated that it would not pronounce on the seaworthiness of the barge for the voyage. 60 The primary judge rejected the argument of M&C. He said: 135 …the juxtaposition of the words, in the first part of the sentence, that the survey report would be a report as to the findings "at time and place of intervention" in relation to the words which followed, "but I must stipulate is not a Certificate of Seaworthiness for towing", was intended to contrast the difference between two types of reports; and to emphasise that SGS would not report on the sea-worthiness of the loaded barge for the proposed tow. 61 Further, his Honour found that Mr Sweet acknowledged in cross-examination that he understood from the SGS March email that SGS would not be providing a certificate of seaworthiness for the barge for the purposes of the tow. His Honour referred to two passages in the evidence of Mr Sweet as follows: And the communications that you had back from the insurer, referred to "Please forward certificate" report/certificate?---Yes, that's correct. I read that as the SGS report. But you agree with me that obtaining a towage tow worthiness certificate from SGS, was something that as from 20 March 2006, you knew you couldn't get from SGS? Correct, yes, not a warranty. As I said before, I thought that the certificate was part of the warranty survey. Yes. The point is whether it's a warranty survey or a separate certificate or whether the certificate is part of it, neither of those you knew you could get from SGS? That's correct. … Well, it says "In that condition." It does not say, "We checked within static condition and they appeared satisfactory for the tow," did it?---It doesn't say that, no, but - - - And you knew from what you had been told before that they wouldn't provide a certificate as to the satisfactory nature for the purposes of a tow?---That's correct. They weren't doing a towage certificate. You were the only one, I want to suggest, that knew that that was the limitation that they had already indicated to you, because you were the only recipient of that email of 20 March 2006?---You have established that before, but as I said, I believe I discussed it with the insurer but I can't explain it more than I already have. 62 The primary judge then made the following finding: 139 I find, therefore, that from 20 March 2006, Mr Sweet, on behalf of Marine & Civil, knew from Mr Tickner's email [SGS March email] that any survey report which would be provided by SGS would be confined to expressing an opinion as to the surveyor's "findings at time and place of intervention" and would not provide a report which certified suitability of the loaded barge and the sea fastenings to undertake the proposed tow from Dampier to Koolan Island. 63 The primary judge then considered certain cross-examination of Mr Sweet as follows: 145 Mr Sweet deposed in cross-examination, that, notwithstanding, Mr Tickner's email, he believed that SGS would report on the suitability of the loaded barge and the sea fastenings to undertake the voyage to Koolan Island. To the extent that Mr Sweet may have believed, when he sent the email of 20 April 2006 [M&C April email], that SGS would provide a report which opined upon the suitability of the loaded barge to undertake the proposed voyage, that belief was not objectively warranted, for the reasons referred to in the preceding paragraphs. Likewise, a belief or understanding that because, following the receipt of Mr Sweet's email of 20 April 2006 [M&C April email], SGS did not refer in its report to the matters pleaded in para 7 of the statement of claim, SGS, thereby, made the implied representations, was objectively not warranted by a person possessed of the knowledge which Mr Sweet then held or is to be taken to have held. This is because the absence of any express reference in the report to the suitability of the loaded barge to undertake the voyage to Koolan Island, was explicable on a basis other than that SGS had agreed to opine upon the sea-worthiness of the loaded barge and was of the opinion that the loaded barge was suitable for the undertaking of the voyage. The other explanation was that in issuing a report which did not address the sea-worthiness of the loaded barge, SGS was doing what it said it would do in Mr Tickner's email of 20 March 2006 [SGS March email]. It is this explanation which is objectively warranted having regard to what each of the parties knew, or is to be taken to have known, about the other party. 64 His Honour concluded: 146 …having regard to the qualified nature of the language used in the SGS survey report, the expert evidence as to the manner in which the SGS survey report would be understood by a reasonably experienced person in the maritime industry, and, having regard to what each of the parties knew, or is to be taken to have known about the other party, I find that, applying an objective test, SGS did not make the implied representations pleaded by Marine and Civil.
Relevant principles 133 It is common ground that determining whether liability for misleading and deceptive conduct arises requires a consideration of circumstances and context. As part of the inquiry, it is relevant to consider what the words are capable of conveying. If they cannot convey that which is claimed, then there is no misleading conduct. However, it is necessary to determine what was conveyed by the words in all the circumstances having regard to the characteristics and knowledge of the person to whom they were addressed and what else was known to the parties through their dealings or otherwise. 134 These general principles are well established: Butcher v Lachlan Elder Realty Pty Limited (2004) 218 CLR 592 at [37]-[39], [109]-[112], [139]; Miller & Associates Insurance Broking Pty Ltd v BMW Australia Finance Limited (2010) 241 CLR 357 at [14]-[15], [20], [87], [91]. 135 The inquiry is an objective one concerning what was conveyed to the claimant. This is the "anterior question". The intentions of the party engaging in the conduct and the subjective beliefs of the claimant are both irrelevant in answering this question. Only if the conduct is objectively misleading do subjective questions of reliance arise: Butcher at [37]; Miller at [85] and Owston Nominees No 2 Pty Ltd v Clambake Pty Ltd (2011) 248 FLR 193 at [62], [82], [220]-[222], [234]-[235]. 136 The trial judge properly approached the matter on that basis: Marine & Civil Construction Company Pty Ltd v SGS Australia Pty Ltd [2012] FCA 907 at [109]-[110], [145]-[146].
(2004) 218 CLR 592
(2009) 238 CLR 304
(2010) 241 CLR 357
(2011) 248 FLR 193