The Costs of the Agents' Proceedings
5 Section 824(1) applied to the agents' proceedings. The agents submitted that Combined had, by the commission of 'an unreasonable act or omission', enlivened s 824(2). They nominated four such acts or omissions:
(a) the running of a defence of estoppel against the agents' claims;
(b) the failure by Combined to abide by Court directions, to attend directions hearings, to respond to requests for particulars and by reason of a late amendment;
(c) a failure to accept certain offers of compromise; and
(d) the filing by Combined of proceedings NSD 1860 of 2008 in this Court.
6 As to (a), the agents submitted that Combined's deployment of estoppel defences was 'misconceived in the sense of being incompetent or unsupportable on the authorities'. It is, perhaps, easy to have some sympathy for this argument. The inability of estoppel to work in an industrial context is not, as I pointed out in ACE Insurance Ltd v Trifunovski (2011) 200 FCR 532 at [145], a new phenomenon. Nevertheless, in the case of each statutory régime, it is necessary to identify whether its policy excludes the operation of principles such as estoppel. The answer given with respect to any one statutory regime cannot be determinative of the answer given with respect to another.
7 As my reasons referred to above show, the conclusion that the statutory framework excluded the operation of doctrines such as estoppel had not been formally reached until that judgment: see [135]-[142], particularly [141]-[142]. It is true that other courts had previously concluded that the legislation, as it stood before 2006, evinced such an intention, but no such holding had yet been made about the form of the legislation after 2006. In my opinion, Combined had a difficult argument to advance on this topic because the differences between those two régimes are hard to discern from this perspective. Nevertheless, the defence was not, as a matter of formality, excluded by authority. I do not accept that the assertion of an estoppel could be, in those circumstances, unreasonable in the requisite sense. I reject argument (a).
8 Argument (b) turned upon what were said to be procedural defaults by Combined. The solicitor for the agents pointed to these matters in his affidavit. The first of these was said to be Combined's failure to appear in the five matters at a directions hearing held on 19 December 2008 in the Chief Industrial Magistrates Court. The matters were adjourned in consequence to 21 January 2009. Mr Arthur, the solicitor for Combined, gave evidence about this. He disputed the agents' claim for costs in relation to the appearance on that day. What had happened, according to Mr Arthur, was that the parties had not known that the matter was to be listed on 19 December 2009. This was because when the matter had last been before the Court it had been listed for further directions on 21 January 2009 (not 19 December 2008). Mr O'Donnell had noticed the matters in the list for 19 December 2008 and had contacted one of Mr Arthur's employed solicitors, Mr Dooley. In the ensuing discussion between Mr Dooley and Mr O'Donnell both had agreed that the listing was in error and that Mr O'Donnell would mention Mr Dooley's appearance, calling him once more if attendance was necessary.
9 All of these matters were then recorded in a letter written by Mr Arthur to Mr O'Donnell on 20 January 2009. Mr Arthur put this letter before me and there was no attempt by Mr O'Donnell thereafter to contradict this account. I accept it. It follows that there was nothing unreasonable about the failure of Mr Dooley (or Mr Arthur) to appear on 19 December 2008. Consequently, no reason is shown to depart from the ordinary position that there be no costs.
10 The second procedural default relied upon by the agents was on 21 January 2009. However, although this was advanced in the agents' written submissions, I did not apprehend from Mr O'Donnell's evidence anything more than that there had been a directions hearing on that day and that Combined had been ordered to file its evidence by 4 March 2009. If I had concluded that the proceedings' adjournment to that day had been the result of unreasonable conduct on 19 December 2008 some scope might then have appeared for an argument that the subsequent directions hearing (and inferentially the costs associated therewith) might also have been unreasonably incurred. This argument does not, however, appear to have been advanced. In any event, I have rejected the premise upon which it would have rested, viz the unreasonableness of the events of 19 December 2008. Perhaps another form of the argument was the notion that Combined had not filed its evidence by this date and that this had required the further adjournment of the proceedings. If such an argument was advanced, I do not accept that this was unreasonable without knowing more about what led to the timetable breach.
11 The third procedural default relied upon is said to have occurred on 9 March 2009. The evidence of Mr O'Donnell was that on this date the agents' claims were adjourned to 20 April 2009 to allow Combined to put on its evidence. As already noted a similar adjournment had also occurred on 21 January 2009.
12 The agents' submissions did not explain why this might justify a departure from the ordinary costs position. I think it likely that the submission is that the failure of Combined to file its evidence in accordance with the direction of 21 January 2009 meant that the directions hearing on 9 March 2009 was a waste of time. I do not accept this argument. To conclude that this conduct was unreasonable I would need to know why the evidence had not been filed. Common experience with litigation well-shows that timetable breaches are not necessarily unreasonable. Further, I know nothing of what occurred on 9 March 2009. Just because the timetable for Combined's evidence was extended does not mean that other matters were not usefully discussed. Hence it is not possible to say that it was a waste of time.
13 The fourth procedural default was said to arise from a costs order made by me on 8 March 2011. On that day I permitted Combined to amend its pleadings in NSD 1860 of 2008 and ordered it to pay the costs thrown away by reason of the amendment: Combined Insurance Company of America trading as Combined Insurance Company of Australia v Trifunovski (No 3) [2011] FCA 238. I am at a loss to understand how this event interacts with the agents' proceedings. Regardless, there was nothing 'unreasonable' about the amendment application which could enliven s 824(2).
14 The fifth procedural default relied upon what was said to be a failure by Combined to respond to a request for particulars which had, in turn, necessitated the agents bringing an interlocutory application. Mr Arthur gave evidence which contradicted this allegation: the prayer of the motion seeking the response to the request for particulars was not pressed by the agents (following further correspondence) and I dismissed the balance of the notice of motion (which sought to dismiss the proceedings on jurisdictional grounds) with costs: Combined Insurance Company of America trading as Combined Insurance Company of Australia v Trifunovski [2009] FCA 525. I see nothing unreasonable in any of this conduct.
15 Equally importantly, this request was made in proceedings NSD 1860 of 2008 which were not proceedings under the Workplace Relations Act so that, subject to some remarks below, s 824 did not apply.
16 As to (c), through the course of the litigation the agents made two sets of offers of compromise. These offers (together with the final judgment sums awarded) were as follows:
5 November 2008 December 2010 Judgment
Mr Trifunovski $79,604 $80,000 plus combined to pay $20,000 in costs $79,226.31 (plus interest)
Mr Peries $384,001.31 $300,000 plus Combined to pay $20,000 in costs $70,657.50 (plus interest)
Mr Perez $48,610 $45,000 plus Combined to pay $20,000 in costs $64,428.34 (plus interest)
Mr Dicinoski $13,778 $10,400 plus Combined to pay $10,000 in costs $16,759.21 (plus interest)
Mrs Dicinoski $9,500 $7,200 plus Combined to pay $10,000 in costs $13,416.43 (plus interest)