AAP Engineering Pty Ltd v Fernlog Pty Ltd
[2017] NSWDC 141
At a glance
Source factsCourt
District Court of NSW
Decision date
2017-02-03
Source
Original judgment source is linked above.
Judgment (11 paragraphs)
Background
- The background facts are as follows: 1. The plaintiff (or companies within its group) is the registered proprietor of a number of commercial properties at Kirrawee in Sydney; 2. One of the properties has erected on it a building which includes the Premises; 3. The defendant, which traded at all relevant times as Colorfen Constructions, is a company engaged in the manufacturing and installation of home improvement products; 4. The Lease was entered into in about September 2007 between the plaintiff and the defendant for the Premises which, as set out above, was part of a building owned by the plaintiff as shown in Annexure B to the Lease; 5. Upon expiry of the Lease, the defendant continued in possession of the Premises on a month to month basis and departed at the end of either April or at the beginning of May 2015; 6. At the time the Lease was entered into in 2007, there was no separate electricity meter for the Premises. Whilst there was a separate water meter for the Premises that water meter also covered two fire hoses and a tap on that part of the building not leased to the defendant. In addition, after the Lease commenced, a further tap was installed at the request of Mr Warwick Williams, a director of the defendant, by a plumber, Mr Maidment, on the plaintiff's side of a dividing wall in the factory which separated that part leased which is the Premises from the remainder of the building. The circumstances in which the tap was installed are discussed further below. At no time were utility invoices received directly by the defendant from the relevant utility authority for water services provided in relation to the Premises; 7. In about September 2008 Mr Williams of the defendant arranged for a gas meter installer to connect a gas supply to the Premises which was separately metered by Origin Energy and paid for by the defendant directly; 8. At some stage in 2009 a separate electricity meter was installed purporting to be for the Premises but which included the usage for some lights on the plaintiff's side of the building. This sub-meter was not installed by an electricity utility authority. Subsequent to the installation of the electricity sub-meter, the defendant received no invoices from any utility authority for the supply of electricity nor from the plaintiff in relation to the sub-meter; 9. Between September 2010 and April 2012 various building work was carried out by the defendant for the plaintiff at the plaintiff's request. There is no dispute that this work was done. The defendant claims that it has not been paid for or given the benefit of this work; 10. It was not until September 2012 that the then Financial Controller for the plaintiff, Mr John Straker, sought moneys from the defendant for electricity bills paid in relation to the Premises by the plaintiff since 2009. From September 2012 and following the plaintiff sought payment from the defendant for moneys said to be owing for the electricity bills and, in due course, for moneys paid for water bills; 11. Mr Williams, on behalf of the defendant, asserts in his affidavit sworn 10 August 2016, that he made some payments to the plaintiff for the electricity not because he thought the defendant was obliged to but because he was fearful that a director of the plaintiff would cut off the defendant's electricity as bills were sent not to the defendant for the electricity supply but to the plaintiff alone: see paragraphs 35 to 36 of Mr Williams' affidavit; 12. From about March/April 2013 the defendant paid to the plaintiff $5,000 per month towards electricity; 13. There was various email correspondence in October-December 2014 between the parties relating to the correct calculation for the electricity said to be owed in which the defendant's accountant apparently did not dispute the defendant's obligation to pay the electricity; 14. On 18 February 2015 the defendant made its last payment to the plaintiff for $5,000 towards the electricity. Mr Williams asserts (paragraph 49 of his affidavit) that he had not been satisfied any such amounts of $5,000 per month were payable by the defendant. The total paid by the defendant was $110,000; 15. The plaintiff also sought that the defendant pay amounts for water usage billed to the plaintiff allegedly for the Premises. No amount was paid by the defendant towards the water bills; 16. At some date in either April or May 2015 the defendant vacated the Premises pursuant to a Notice to Quit; 17. As indicated above, it is agreed that construction work was performed by the defendant for the plaintiffs. The plaintiff has given credit to the defendant for approximately $39,000 towards the amounts said to be owing for the water and electricity bills. An amount of $13,000 for work apparently completed has not been credited but is no longer disputed by the plaintiff; 18. The plaintiff has made claims for the amount which it says to be owed to it for the electricity and water supplied. The defendant has not paid any of those moneys since it vacated the Premises.