470 St Kilda Road v Robinson
[2013] FCA 1420
At a glance
Source factsCourt
Federal Court of Australia
Decision date
2013-12-20
Before
Kenny J
Source
Original judgment source is linked above.
Judgment (15 paragraphs)
BACKGROUND 7 The following facts were agreed between the parties. 8 At the relevant time, Mr Robinson was employed by Reed Constructions Australia Pty Ltd ("Reed") - a company now in liquidation - as its Chief Operating Officer ("COO"). Reed Construction was in the business of constructing medium to large buildings and other construction projects. Mr Robinson became Reed's COO in April 2011. Before that date he had been Reed's National Operations Director. Mr Robinson had commenced working with the Reed Group companies in 1987 as a Site Foreman. He re-joined the Reed Group in 1993 as a Project Supervisor, after spending three years with Baulderstone Hornibrook as a Site Manager. Mr Robinson was not at any time a director of Reed or any other company in the Reed Group. 9 In or about October 2010, the applicant in the principal proceeding, 470 St Kilda Road Pty Ltd, and Reed entered into a written design and construct contract ("the D&C Contract") relating to a construction project known as the 'Leopold Project' situated at 470 St Kilda Road in Melbourne. 470 St Kilda Road Pty Ltd was the 'Principal' and Reed was the 'Contractor' under the D&C Contract. Reshape Development Pty Ltd ("Reshape") was appointed as the Principal's Representative under the D&C Contract. The Building and Construction Industry Security of Payments Act 2002 (Vic) ("the SOP Act") applied to the D&C Contract. 10 The terms of the D&C Contract were contained in a formal instrument of agreement with annexures titled 'Design and Construction Contract for Major Domestic Building Projects in Victoria AS4902-2000 As Amended' and dated 25 October 2010. Under the terms of the D&C Contract: (a) Reed was required to claim payments for work performed under the D&C Contract on a progressive basis ("progress claims"); and (b) 470 St Kilda Road Pty Ltd could request that Reed provide documentary evidence in support of progress claims. From time to time, Mr Robinson made statutory declarations in support of progress claims that included details of payments made to subcontractors. 11 470 St Kilda Road Pty Ltd requested that Reed provide documentary evidence in support of Progress Claim No 15. In December 2011, Aaron Tranter, who was at that time employed by Reed as the Contracts Manager for the Leopold Project, requested that Mr Robinson execute a statutory declaration in support of Progress Claim No 15. Mr Robinson made a statutory declaration on 12 December 2011 in support of Progress Claim No 15 ("the Statutory Declaration"). Reed submitted the Statutory Declaration to Reshape on 12 December 2011. Reshape issued a Certificate of Payment for Progress Claim No 15 in the amount of $1,426,641.70 (inclusive of GST) to 470 St Kilda Road Pty Ltd on 21 December 2011. 12 Chubb issued a directors and officers liability insurance policy to Reed Building Group Pty Ltd and its subsidiaries (which included Reed) for the policy period 25 July 2011 at 4 pm to 25 July 2012 at 4 pm ("the D&O Policy"). Mr Robinson falls within the definition of an 'Insured Person' under the D&O Policy. 13 The principal proceeding was commenced by 470 St Kilda Road Pty Ltd against Mr Robinson on 3 April 2012. 470 St Kilda Road Pty Ltd claimed that: (1) Mr Robinson did not have a reasonable basis for making the Statutory Declaration submitted in support of Progress Claim No 15; and that he had thereby engaged in conduct that was likely to mislead or deceive and acted negligently in breach of his duty of care. St Kilda Road Pty Ltd further alleged that it had relied on the Statutory Declaration when it issued a Payment Schedule and certificate of payment on 21 December 2011 for $1,426,641.70 in relation to Progress Claim No 15, as a result of which 470 St Kilda Road Pty Ltd had suffered loss and damage. Mr Robinson denied the claims. 14 No party challenged the Court's jurisdiction. Jurisdiction with respect to the principal proceeding was said to arise under s 6(3) of the Competition and Consumer Act 2010 (Cth), because the Statutory Declaration was emailed to 470 St Kilda Road Pty Ltd. 15 Mr Robinson made a claim for indemnity under the D&O Policy in respect of losses that have been or will or may be incurred by him as a consequence of the principal proceeding. Chubb denied liability under the D&O Policy on the ground that exclusion IV(A)(v) of the policy applied. 16 As a consequence, Mr Robinson instituted the cross-claim against Chubb, in which he claimed an indemnity under the D&O Policy. Chubb denied its liability under the policy, relying on exclusion IV(A)(v). The only outstanding question in the cross-claim was whether Chubb was entitled to refuse to indemnify Mr Robinson by reason of exclusion IV(A)(v) to the D&O Policy. This is the question for determination.